Glossary (EDGEBIC)

What Is a Daily Hour Breakdown? Definition and Example

User Solutions TeamUser Solutions Team
|
5 min read

A daily hour breakdown is a per-day record of the planned hours and actual hours, and where relevant the pieces, for one scheduled operation, so an operation that spans several days is reconciled day by day rather than as a single lump. It is a daily timesheet for one step: Monday, welding, planned 8 hours, actual 7.5 hours, 150 pieces. Where the schedule row says the operation runs from Monday to Wednesday, the daily hour breakdown says how those hours are distributed across the three days and how many were actually worked on each.

This entry is part of the EDGEBIC by User Solutions glossary series; for the broader vocabulary of production planning, see the manufacturing glossary.

How a Daily Hour Breakdown Works

Capacity is consumed one shift, one day at a time. A machine has eight hours on Monday and eight on Tuesday, not sixteen hours in a single bucket. So when a 20-hour operation spans several days, the scheduler needs to know how many of those hours land on each day, both to load each day's capacity correctly and to give the floor a day to log actuals against.

The daily hour breakdown is that record. Each row belongs to one operation and one date, and it carries the planned hours for that day and the actual hours once they are logged. On work centers measured in output, it also carries pieces. When an operation spans two shifts in a single day, a per-shift sub-row can further decompose the day.

The breakdown is where planned and actual meet at the finest grain. A reschedule recomputes the planned rows; the floor writes the actual rows. Reconciling the two, day by day, is what tells you which specific day a long job fell behind and by how much, rather than only that the whole operation ran long.

A Concrete Example

A 16-hour CNC operation is planned to run Monday and Tuesday. Its daily hour breakdown starts as two planned rows:

DatePlanned hoursActual hours
Monday8(to be logged)
Tuesday8(to be logged)

The operator logs the real work as it happens. By Tuesday evening the breakdown reads Monday 8 planned / 6 actual, Tuesday 8 planned / 4 actual: 16 planned against 10 actual. The plant can now see exactly where the shortfall sits and reconcile it. If the operator then marks the step complete with 6 hours unlogged, the site's partial-completion policy decides whether those hours forward-shift to a new slot or the short close is trusted. Either way the two logged days keep their real numbers.

How EDGEBIC Uses It

In EDGEBIC the daily hour breakdown backs the Log Actuals grid and every hours rollup.

  • It reconciles long operations day by day. Each day the operation touches has a row with planned and actual hours, so a multi-day job is loaded and logged against the right dates rather than as a single block.
  • It carries the auto-filled marker. When the system back-fills a day's actuals from plan because a downstream step was closed first, the row is tagged and shows an auto-filled badge in the grid, which disappears the moment you edit the value.
  • It rolls up cleanly. The end-of-day rollup recomputes daily breakdowns so job-level and work-center-level hour totals come from real daily data.
  • It is protected by anomaly checks. The persist boundary deduplicates daily rows so a reschedule cannot create duplicate or stray rows, and the anomaly report flags any day carrying actual hours with zero planned hours, or duplicate rows for the same operation and date, and a consistency drift check catches allocation hours and daily breakdowns disagreeing about the same number.

The daily hour breakdown sits one level below actual dates: the actual dates bracket the operation, and the breakdown fills in what each day held. The actuals tracking explained walkthrough shows how a shift's punches become the day's hours, and what is production scheduling sets the hours loop in context.

A daily hour breakdown is a per-day record of the planned hours and actual hours (and, where relevant, pieces) for one scheduled operation. Where a schedule row says the operation runs from Monday to Wednesday, the daily hour breakdown says how many of those hours fall on Monday, on Tuesday, and on Wednesday, and how many were actually worked each day. It is a daily timesheet for one operation: Monday, welding, planned 8 hours, actual 7.5 hours, 150 pieces.

Because an operation that spans several days needs to be reconciled day by day. Capacity is consumed per shift per day, so knowing that a 20-hour job is 8 hours Monday, 8 hours Tuesday, and 4 hours Wednesday is what lets the engine load each day correctly and lets the floor log actuals against the right date. A single lump sum for the whole operation would hide which day fell behind and would not net against daily machine capacity.

An actual date is a single point in time: when the operation started or finished. A daily hour breakdown is a set of rows, one per day the operation touches, each carrying planned and actual hours for that day. The actual dates bracket the operation; the daily hour breakdown fills in what happened between them, day by day. Together they let the schedule reconcile both when work happened and how much work each day held.

Expert Q&A: Deep Dive

Q: A 16-hour CNC run shows 6 hours logged Monday and 4 hours Tuesday, then the operator marked it complete. What happens to the missing 6 hours?

A: The daily hour breakdown holds 6 actual hours on Monday and 4 on Tuesday, a total of 10 against a planned 16, so there is a 6-hour gap. What happens next depends on the site's partial-completion policy. Under forward-shift-remaining, the engine reschedules the missing 6 hours onto the next available slot and the daily breakdown for the new block reflects them. The logged days keep their real numbers; nothing is invented or discarded.

Q: One of my daily rows shows actual hours with zero planned hours. Is that a data error?

A: It usually is, and EDGEBIC's anomaly checks flag it. A daily hour breakdown row with planned hours of zero but actual hours above zero is a stray row: a day is carrying logged time that no plan accounts for, which would let hours accumulate with nothing behind them. The persist-boundary merge deduplicates daily rows so a reschedule does not create these, and the anomaly report surfaces any that slip through so you can correct the source.

Frequently Asked Questions

Ready to Transform Your Production Scheduling?

User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team

User Solutions Team

Manufacturing Software Experts

User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.

Let's Solve Your Challenges Together