How to Reschedule Everything From Scratch in EDGEBIC

User Solutions TeamUser Solutions Team
|
7 min read

To reschedule everything from scratch in EDGEBIC, select every job on the Drive Schedule tab and press Schedule + Re-Schedule for a full rebuild that still preserves completed work, or press Clear Schedule first for a true blank-sheet reset. EDGEBIC by User Solutions decides the scope from your selection, not from a mode picker. Both paths are one button each, and knowing what each one keeps versus releases is the whole skill.

This is the plant-wide reset procedure. For the everyday pass, see how to run the scheduler in EDGEBIC; for the mechanism underneath, EDGEBIC scheduling modes explained covers what a full pass does internally. It is one of the task guides in the EDGEBIC how-to hub.

Before You Start

PrerequisiteWhy it matters
At least one active shift existsWith no active shift the run stops and offers to create one.
Every product on the plan has a routingAn order with no routing is reported as a failure and skipped; it never aborts the rest.
Calendars and capacity are currentA full rebuild plans against calendars as they are right now. Fix master data first.
You know whether you want a rebuild or a wipeA full reschedule keeps history; Clear Schedule deletes plan rows and reopens completed orders.

Path One: Rebuild the Whole Plan

This is the right choice most of the time. It replans every job while protecting recorded work.

  1. Open the Drive Schedule tab.
  2. Leave every Select checkbox unticked, or tick all rows explicitly.
  3. Press Schedule + Re-Schedule.
  4. If nothing was ticked, answer Yes to the Schedule All Orders prompt to include everything.
  5. Read the Confirm Scheduling dialog. It reports the split, for example "You are about to schedule 40 job(s): 5 new, 35 existing." Answer Yes.
  6. Watch the progress overlay to completion. Every scheduled job shows its Scheduled badge with dates filled in. If you realize mid-pass that you started the wrong run, cancel it from that overlay and the previous plan is left intact.

Each already-scheduled job releases its unfinished reservations so the engine can place them fresh, while completed and in-progress operations are kept exactly. The result is a rebuilt plan on the current calendar, not a wiped one.

Path Two: A True Clean-Sheet Reset

Use this only when the plan itself is untrustworthy, for example after a bad import.

  1. On the Drive Schedule tab, deselect all rows.
  2. Press Clear Schedule.
  3. Confirm the warning that all schedules will be cleared and the action cannot be undone.
  4. With the plan now empty, tick every job and press Schedule + Re-Schedule to build a fresh plan.

Clear Schedule deletes every production schedule, schedule, and resource row, sets each order back to unscheduled, and reopens any completed order with an auditable inventory reversal. It deliberately leaves your planner inputs, including each job's start time, untouched.

What Changes When You Run

SurfaceFull rebuild (Path One)Clear Schedule (Path Two)
Not-started operationsReplanned against current capacityDeleted, then replanned on the fresh pass
Completed operationsPreserved verbatimPlan rows deleted; completed orders reopened
Logged actuals in the recordPreservedPreserved in the underlying data, but orders reopened
Reserved capacityReleased and rebooked in one passFully released
Inventory postingsUnchangedReversed auditably for reopened orders
Job start timesKept (planner input)Kept (planner input)

How to Check It Worked

  1. After Path One, spot-check a job that was on time before: its Days Late should still read the value the current plan supports, not a surprise.
  2. Confirm completed steps did not move by opening a finished job in Job View and reading its Actual Start and Actual End against what the floor reported.
  3. After Path Two, verify the grid shows every job Unscheduled before you rebuild, then Scheduled after the fresh pass.
  4. Check the Scheduling Failure Dialog if it appears. It lists any job that could not schedule, with a category and a fix hint, so a full pass never silently drops work.

Common Mistakes and Gotchas

  • Reaching for Clear Schedule when a rebuild would do. Clear Schedule reopens completed orders and reverses inventory. If you only want the plan to reflect new master data, Path One is safer and keeps history clean.
  • Forgetting to fix master data first. A full reschedule plans against the calendar and routings as they are at run time. Edit shifts, holidays, capacity, and routings before you run, not after.
  • Assuming a rebuild wipes actuals. It does not. Recorded work is preserved and remaining hours resume from reality. Only Clear Schedule tears down plan rows.
  • Ignoring the failure dialog. On a plant-wide pass, a few jobs may fail pre-flight for a missing routing or an inactive work center. Read the fix hints and re-run the affected jobs rather than assuming everything scheduled.

A full rebuild is the right tool after a genuinely global change: a shift pattern edited across the plant, a wave of routing revisions, a capacity reset, or a fresh import that touched many products at once. It is the wrong tool for a single moved due date or one machine problem, where a rebuild churns dozens of jobs for a change that affected one. Match the size of the pass to the size of the change, and reach for a plant-wide rebuild only when the whole plan really does need to reflect new reality.

For narrower corrections, how to reschedule only the jobs that changed is the lighter tool, and how EDGEBIC preserves completed work on reschedule explains why a rebuild never rewrites the floor's history.

Bring an order export and a work center list and we will run a full rebuild against your data in one session. Contact US to book it, or read the EDGEBIC product overview first.

Select every job on the Drive Schedule tab and press Schedule + Re-Schedule, or answer yes to the Schedule All Orders prompt when nothing is ticked. Every already-scheduled job releases its unfinished reservations and is replanned against current capacity, while new jobs get a first plan. Completed and in-progress work is preserved throughout. There is no mode to choose; the selection is the scope.

No. A plant-wide reschedule preserves completed operations verbatim and keeps in-progress operations on their real days, replanning only the remaining hours. It rebuilds the future plan, not the history. The heavier Clear Schedule action does delete plan rows and reopen completed orders, so use it only when you truly want a blank slate.

Rescheduling everything replans all jobs in one pass while honoring actuals, so the plan rebuilds but history stays. Clear Schedule deletes all production schedule, schedule, and resource rows, sets every job back to unscheduled, and reopens completed orders with an inventory reversal. Clear Schedule is the true blank sheet; a full reschedule is a rebuild.

Expert Q&A: Deep Dive

Q: I changed several routings and shift calendars this morning. What is the cleanest way to make the whole plan reflect them?

A: Run a plant-wide reschedule: leave every row unticked, press Schedule + Re-Schedule, and answer yes to the Schedule All Orders prompt. Every job is replanned against the updated routings and calendars, and the confirm dialog reports how many are new versus existing before anything writes. Completed steps stay put. Reserve the harder Clear Schedule reset for a plan you no longer trust at all.

Q: My plan looks corrupted after a bad import. How do I wipe it and start over without losing my orders?

A: Deselect all rows, press Clear Schedule, and confirm. This deletes the plan output for every job and sets each to unscheduled, but leaves the orders and all master data intact. Be aware it reopens any completed order and reverses its inventory postings auditably. Then tick all jobs and press Schedule + Re-Schedule to build a fresh plan on clean data.

Frequently Asked Questions

Ready to Transform Your Production Scheduling?

User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team

User Solutions Team

Manufacturing Software Experts

User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.

Let's Solve Your Challenges Together