- How to Cancel a Scheduling Run in Progress in EDGE…
To cancel a scheduling run that is already in progress, click Cancel on the Scheduling Manufacturing Orders progress overlay; the run stops, nothing partial is kept, and the plan you had before you pressed the button is still there. In EDGEBIC by User Solutions a run is computed and then written, never committed job by job, so an abandoned run leaves no wreckage to clean up.
This post covers only the mid-flight stop. For the run itself, start with how to run the production scheduler, and the full task library is at the EDGEBIC how-to hub.
Before You Start
- A run is actually in progress, which means the progress overlay is on screen and the order grid is locked.
- You understand the difference between canceling a run and clearing a schedule. Cancel abandons a calculation. Clearing a job's schedule deliberately removes an existing plan.
- You know what the run was going to touch. If you never read the Confirm Scheduling dialog, canceling is the right instinct, because you were about to move an unknown number of jobs.
The Steps
- Find the overlay. During a run, the Drive Schedule tab is covered by the Scheduling Manufacturing Orders overlay. It carries a progress bar, a status message naming the current phase, an elapsed-time readout, and a Cancel button.
- Read the status message once before you act. The message moves through phases: initializing the scheduler, loading configuration data, then scheduling the orders. A long pause inside one phase on a big run is normal, not a hang.
- Click Cancel. There is no second confirmation, because there is nothing to confirm away: no plan has been written yet.
- Watch the overlay close and the grid unlock. The status line reports that the operation was canceled.
- Check one job you expected to move. Its dates and its Scheduled or Unscheduled badge should read exactly as they did before the run.
- Fix whatever prompted the cancel, then run again. Usually that means re-ticking the correct Select checkboxes, or correcting a priority or due date that the lock had been stopping you from editing.
What Changes When You Cancel
| Surface | Effect of canceling mid-run |
|---|---|
| Selected jobs | No new dates. Every job keeps the plan it had before the run started. |
| Unselected jobs | Untouched, exactly as they would have been on a completed run. Their reserved capacity stands. |
| Recorded work | Untouched. Actual dates and logged hours are never in play during a run in the first place. |
| Blank due dates | Not backfilled. A blank due date is filled from a job's first planned end, and there was no planned end. |
| The order grid | Unlocks. Inline edits to priority, due date, and direction are available again. |
| Gantt, Job View, dashboards | Unchanged, because they were already showing the pre-run plan. |
| Elapsed compute time | Lost. This is the only real cost of canceling. |
The reason this is boring rather than dangerous is the write model. A run holds its result until it is complete, then saves. There is no per-job commit that could leave job seven planned and job eight stranded.
How to Check It Worked
Pick the job whose row you were watching before the run and compare three things against your memory or a screenshot: the Status badge, the Schedule Details line, and Days Late. All three should be identical to their pre-run values. A job that was Unscheduled should still read Not scheduled yet, not a half-filled set of dates.
Then confirm the grid is live again by typing into a Priority cell. If the cell accepts the keystroke, the lock has lifted and the run is genuinely over. Finally, open Job View on one job and confirm the hours header still shows the same Total Hours and Actual Hours it did before.
Common Mistakes
Assuming a canceled run left the plan half-done. It cannot. This is the single most common worry and it is unfounded. There is no partial-save state, so there is nothing to hunt for and nothing to undo.
Canceling the wrong Cancel. If you are running backward jobs with the review popup enabled, a separate dialog can appear at the end of the run listing jobs that cannot make their due dates. Its Cancel button also discards everything, but that is a decision about a completed calculation rather than an abandoned one. The distinction is explained in scheduling a job backward from its due date.
Canceling repeatedly instead of narrowing the scope. If runs keep taking longer than you are willing to wait, the fix is scope, not patience. Tick the specific jobs you need re-planned instead of accepting the Schedule All Orders offer, and see how to reschedule only the jobs that changed.
Trying to edit an order through the lock. The grid is disabled on purpose so an edit cannot land inside a calculation that already read the old value. Cancel first, edit, then run.
Treating the cancel as a way to preview. It is not a dry run. The overlay shows progress, not results, so nothing is revealed by letting it get most of the way there. The real preview is the Confirm Scheduling dialog, covered in how to see which jobs a run will touch before you commit.
Next Steps
Once you have canceled, the useful question is what you meant to run instead. If a single job needs a fresh plan, scheduling one job is faster and quieter than a plant-wide pass. If the run was going to take longer than you expected because it included everything, tighten the selection and re-read the confirm dialog. And if the plan that survived your cancel is itself wrong, the diagnostic order is capacity first, calendars second, as laid out in how to see why a job is late.
The takeaway
Canceling a scheduling run in EDGEBIC is a genuinely safe action, and knowing that changes how you plan. You can press Schedule and Re-Schedule to see how long a run takes, stop it, tighten the scope, and try again, without ever putting a committed plan at risk. That confidence comes from one design decision: the engine writes a complete result or it writes nothing. See where finite-capacity scheduling fits on the EDGEBIC product page, and if you are arriving from the earlier generation of User Solutions planning tools, the move from RMDB to EDGEBIC shows what carries over. Next, read how to run the production scheduler end to end, then how to check what a scheduling run changed so the run after this one needs no guessing at all.
Expert Q&A: Deep Dive
Q: I ticked the wrong rows and pressed the button. The overlay is already counting. Have I broken this week's plan?
A: No. Click Cancel on the progress overlay and the run stops without writing anything. EDGEBIC does not save a scheduling run in pieces as it goes, so there is no half-planned state to recover from: every job keeps the plan it had a minute ago, every reserved hour stays reserved, and the grid unlocks. Re-tick the rows you actually meant, press Schedule and Re-Schedule again, and read the Confirm Scheduling dialog this time. It tells you exactly how many jobs will be scheduled for the first time and how many will be re-planned, which is the cheap check that would have caught the mistake before the overlay ever appeared.
Q: The overlay has been sitting on the same message for a while. Should I cancel or wait?
A: Read the message before deciding. The overlay reports the phase it is in, moving from initializing to loading configuration data to scheduling the orders themselves, and it shows elapsed time beside a progress bar. A large run genuinely spends time in one phase, so a stable message is not evidence of a hang. If the elapsed time has grown well past what that plant normally takes, canceling costs you nothing but the wait, because the previous plan is untouched. Then reduce the scope: tick only the jobs you need moved rather than accepting the offer to schedule every order.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.