The At-Risk Jobs grid on the EDGEBIC by User Solutions dashboard lists every job whose projected end runs past its due date, which makes it the earliest warning list you have. Nothing has been missed yet. That is exactly why it is worth reading before the day starts rather than after a customer calls.
For the wider board, see how to use the EDGEBIC dashboard tabs. Every task in this library is mapped on the EDGEBIC how-to hub.
Before You Start
- Jobs are scheduled. Every status figure on the dashboard is derived from the plan.
- Orders carry due dates. A job with no due date can never be flagged as at risk.
- Products carry an end-item lead time where one applies, because classification judges the date the item is actually ready to deliver.
Step 1: Open the Jobs Sub-Tab
Open Dashboard from the main navigation. You land on the CAPACITY tab. Switch to the Jobs sub-tab.
It holds two grids:
| Grid | What it shows |
|---|---|
| Scheduled Jobs | The current workload, the jobs the plan is carrying |
| At-Risk Jobs | The subset whose projected end passes the due date |
Click Refresh now before you read either one. The cockpit does not refresh in the background, so a board left open since yesterday is showing yesterday.
Step 2: Read At-Risk as a Forward Statement
An at-risk job has not missed anything. The plan says it will.
That is a useful distinction because it changes what you do. A job that has already missed its date needs a phone call. A job the plan says will miss needs one of four things: more capacity on a specific day, a different sequence, a different machine, or a renegotiated date. All four are still available to you while the job is on this grid.
Step 3: Cross-Check the Job Status Donut
Go back to the Overview sub-tab and read the Job Status donut beside the Active Jobs list. It buckets every active job into exactly one slice:
| Slice | Meaning |
|---|---|
| Late | The plan itself lands past the due date, or the job finished after it |
| Overdue | The plan met the date, but the date has passed and the job is not done |
| On time | The date is still open and the plan lands exactly on it, or the job finished on or before it |
| Early | The date is still open and the plan lands before it, so there is slack |
The Active Jobs list under the donut sorts worst-first, so it doubles as an attention queue. Whether a job has physically started is shown as an In progress badge on its row rather than as a slice of its own, because being started says nothing about whether a job will be on time. Full reading method: how to read the job status donut.
Expect the At-Risk grid and the Late slice to tell the same story. When they do not, the difference is usually a job with no due date.
Step 4: Drill Into the Late Jobs Report
The dashboard tells you which jobs. The report tells you why. Open Reports and click the 🚨 Late Jobs tile.
It ranks jobs worst-first and carries the columns that decide your response: Due Date, Scheduled End, Days Late, % Complete, Status of not started, in progress or behind, and a Blocker Hint such as no actuals so never started, significantly behind plan, or schedule slipped. See how to run the late jobs report.
The hint is the fastest triage tool on the report. A job that has never started and a job that is 80% done are both at risk, and they need entirely different mornings.
Step 5: Pick the Cheapest Fix
Work down the shortlist in this order:
- Is the capacity number wrong? Maintenance finished early, or overtime is agreed. Set that day's hours in the per-day capacity dialog: how to override capacity for one day.
- Can the work move? Another job on the same station has slack. Move it, or let the optimizer propose a better ordering.
- Can the work run elsewhere? Check the alternates and work center groups on the routing.
- Does the date need to change? If none of the above gives, the honest answer is a customer conversation held three weeks early rather than on the due date.
Then re-run the schedule. Nothing you read on a dashboard moves a job by itself.
A Five-Minute Morning Routine
The grid is most useful as a habit rather than as an investigation.
- Open the dashboard and click Refresh now.
- Read the Jobs sub-tab. Note how many jobs sit on the At-Risk grid and whether the count moved since yesterday.
- Read the donut on Overview. The top of the Active Jobs list is your worst job, sorted for you.
- Open the 🚨 Late Jobs report only for the names that are new, since the ones you triaged yesterday have not changed overnight.
- Fix at most two, then re-run the schedule.
A count that falls week over week means the plan is absorbing disruption. A count that climbs while the shop feels fine is the signal worth acting on, because structural lateness always shows up on the board before it shows up on the floor.
What Changes When You Read It
Nothing. The dashboards are read-only except for the per-day capacity override reached from them, and even that moves no job until the next scheduling run re-plans against the new hours. Switching tabs and clicking Refresh now change the displayed snapshot only.
How to Check It Worked
After you act and re-run the schedule, click Refresh now and return to the Jobs sub-tab. The job you fixed should have left the At-Risk grid, and on the Overview sub-tab it should have moved out of the Late slice of the donut. If the grid is unchanged, the change did not reach the plan, which almost always means the schedule was not re-run.
Common Mistakes
- Reading a stale board. The cockpit tabs load when you switch to them and otherwise wait for Refresh now.
- Expecting a job without a due date to appear. It cannot, on this grid or in the Late Jobs report.
- Treating at-risk as a failure. It is a warning with time still on the clock, which is the whole point of the grid.
- Fixing six jobs one at a time. Two at-risk jobs queueing on the same constraint are one sequencing problem.
- Quoting the dashboard in a customer conversation. The dashboard is the glanceable layer. The reports carry the authoritative formulas and the Column Details glossary behind every number.
See how early warning, capacity, and the plan stay in one system on the EDGEBIC product page.
Expert Q&A: Deep Dive
Q: Six jobs are on the At-Risk grid and I have time to fix two. How do I choose?
A: Rank by two things the grid alone does not give you. Open the Late Jobs report, which sorts worst-first and carries days late, percent complete, status and a blocker hint such as no actuals or significantly behind plan. A job that is 4 days out and 80% complete needs a day of overtime. A job that is 12 days out and has never started needs a different plan entirely, and possibly a customer call today. Then check which of the six touch your constraint work center, because two jobs queueing on the same bottleneck are one problem, not two, and fixing the sequence there can clear both.
Q: The At-Risk grid is empty but customer service says two orders will miss. Who is right?
A: Check the due dates before you check the schedule. A job with no due date can never be flagged at risk and can never appear in the Late Jobs report, because there is nothing to compare the plan against. That single gap explains most of these disagreements. The second explanation is the end-item lead time on the product: classification uses the date the item is ready to deliver, so if a product ships with a lead time that was never entered, the plan looks fine while the customer date does not. Fix the due date on the order and the lead time on the product, re-run the schedule, and the grid and the customer will agree again.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.