- How to Run the Late Jobs Report in EDGEBIC
The Late Jobs report in EDGEBIC by User Solutions lives in the Reports hub under the Supervisor / Planner group, asks for no date range, and ranks every scheduled job whose scheduled end lands past its due date, worst first. It is the shortest useful report in the catalog and the one most planners open before anything else in the morning. This is the task, start to finish: run it, read a row correctly, and turn the top of the list into a decision.
For the wider picture of which report answers which question, see the reports that answer "are we on time?". Every task in this library is mapped on the EDGEBIC how-to hub.
Before You Start
- Jobs have been scheduled at least once. The report reads the plan, so an empty plan produces an empty report.
- Due dates are set on the orders you want tracked. A job with no due date can never appear here.
- Actuals are being logged. Percent complete and the status label compare logged work against plan, so without actuals both read as if nothing has happened.
Step 1: Open the Report
Open Reports from the main navigation. The hub shows one tile per report under four group headers. Click Late Jobs in the Supervisor / Planner group.
No date range dialog appears. Late Jobs is a snapshot report: it describes the plan as it stands at the moment you click, the same way a stock count describes a shelf. That also means it queries fresh every time, so re-opening it is the refresh.
Step 2: Read the Ranking Before the Rows
The grid arrives sorted by Days Late descending, so the worst job is the first row. Days late is the whole number of days between the scheduled end of the job's last operation and its due date. A job whose plan meets the date is excluded entirely, which is why the report is usually short even in a busy shop.
Resist re-sorting immediately. The delivered order is the one the report was designed around, and re-sorting by customer or product before you have read the top five turns a triage list back into a data dump.
Step 3: Read One Row Properly
| Column | What it tells you |
|---|---|
| Job Number / Product | Which order, and what it makes |
| Customer | Who is waiting, which usually decides priority |
| Due Date | The date being missed |
| Scheduled End | Where the plan currently lands |
| Days Late | The gap, in whole days |
| % Complete | How much of the job is already done |
| Status | Not started, In progress, or Behind |
| Blocker Hint | Where to dig first |
Days late and percent complete have to be read together. Nine days late at 82% complete is a finishing problem. Four days late at 0% is a starting problem, and it grows every day nobody touches it.
Step 4: Use the Blocker Hint
The hint is generated per row from the job's own numbers, and it names the fastest place to look:
- No actuals, never started. The job is in the plan and nothing has been logged against it. Confirm with the shop floor whether it truly has not begun or whether actuals simply are not being logged.
- Significantly behind plan. Work started but progress is well short of where the plan expected it by now. Check capacity on the operations still open.
- Schedule slipped. The dates moved. The reschedule history report will tell you when and by how much.
Step 5: Drill Into the Worst Row
From a late job, three drills answer nearly everything:
- Job Progress, to see percent complete and the daily pieces track for the whole job.
- Work Center Progress filtered to that job, to see which specific operation is holding it. That is the difference between "the job is 60% done" and "the mill step has 41 of 101 hours logged and nothing in three days".
- Work Center Utilization, to see whether the station holding the job is over 100% loaded and what else is queued on it.
Full method for the first two is in how to check a job's progress.
Step 6: Export the Evidence
Click Export to PDF (or Export to Excel) in the report window footer if the list is driving a decision. Reports are point in time. Tomorrow's list will be different, and a dated export is what makes "we knew on Monday" provable.
What Changes When You Act
The report itself changes nothing. It is read-only, like every report in the catalog, and running it never touches a schedule.
The change happens where you act: move an operation on the Gantt, adjust a work center's capacity for a day, or re-run the scheduler. Whichever you choose, work already completed is never moved by a reschedule, so the fix lands on remaining work only.
How to Check It Worked
Re-run the schedule after your fix, then re-open Late Jobs. One of three things happens:
- The row is gone. The plan now meets the due date.
- Days late shrank. The fix helped but was not enough, and the new number tells you by how much.
- Nothing moved. The constraint is somewhere you have not looked yet, usually a station running above 100% for the whole window.
Common Mistakes
- Treating days late as a delivery fact. This is a projection from the current plan, not a record of a missed shipment. For delivered performance, use the on-time delivery report, which judges finished jobs by their actual end.
- Assuming an empty report means nothing is late. It can also mean due dates are missing. Spot-check a few orders before celebrating.
- Quoting the blocker hint as a cause. It is a heuristic pointer generated from the row's own numbers. It tells you where to look, not what is wrong.
- Reading percent complete on a shop that does not log actuals. Percent complete is built from logged hours. No logging means every job reads as barely started, and the hint on every row will say so.
See what EDGEBIC does with these numbers across the whole plant on the EDGEBIC product page.
Expert Q&A: Deep Dive
Q: The report opens with 22 rows on a Monday morning. Which do I work first?
A: Sort stays as delivered, days late descending, and then read the second column rather than the first. A row at 9 days late with 82% complete is nearly finished and may only need a shift of overtime on the last operation. A row at 4 days late with 0% complete and the hint No actuals, never started has not begun at all, so its 4 days will keep growing every day you leave it. Work the not-started rows and the customer-committed rows before the nearly-done ones, and take the top five into the planning meeting rather than all 22. The rest usually move on their own once the top five stop blocking capacity.
Q: A job shows 6 days late here but the supervisor swears it will ship on time. Who is right?
A: Both, and the difference is worth understanding. This report measures the plan: it compares the scheduled end of the last operation against the due date, so 6 days late means the current plan lands 6 days past the date. The supervisor is measuring intent, usually overtime or a sequence change that has not been entered anywhere. If the overtime is real, record it as a per-day capacity change on the work center and re-run the schedule; the plan will then either agree with the supervisor or show exactly how many hours short the idea is. A plan that disagrees with the floor is a data problem, not an argument.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.