EDGEBIC How-To

How to Check a Machine's Available Hours on a Date in EDGEBIC

User Solutions TeamUser Solutions Team
|
7 min read

To check a machine's available hours on a date in EDGEBIC by User Solutions, open its per-day capacity view and read the shift default for that date. That figure, adjusted by any override in the Capacity column, is exactly the number of hours the scheduler will offer the machine that day, so it is the authoritative answer for a promise or a what-if.

Planners guess at machine availability all the time, and the guesses are usually wrong because they forget an instance count, a downtime window, or a holiday. The per-day capacity view removes the guessing. This page is how to read it and how to diagnose a zero. For the full formula behind the number, read how EDGEBIC calculates work center capacity.

Before You Start

  • You know the machine and the exact date you are checking.
  • You know which shift matters, because capacity is per shift. A machine that runs day and night has a separate figure for each.

Step 1: Open the Per-Day Capacity View

On the work center's row, click the 📊 per-day capacity button. The Per-Day Capacity dialog opens with a stacked bar per day and a grid of daily figures. Alternatively, in the Resource Calendar, read the machine's capacity row for the date.

Step 2: Set the Range to Include the Date

Adjust the From: and To: dates so the date you care about is in the list. The grid shows every day in the range with its figures.

Step 3: Read the Figures

For the target date, read across:

ColumnMeaning
Shift default (h)What the capacity formula gives: shift hours minus downtime and partial holidays, times instances, times utilization
Capacity (h)The effective hours after any override; equals the shift default unless a day override is set
Loaded (h)Hours already committed by the current schedule
OverriddenTicked when a manual override applies

The free hours are the capacity minus the loaded hours. That difference is what the machine can still absorb on the date.

How the Number Is Built

The shift default for a date comes from a fixed formula:

available hours = (shift hours - downtime - partial-holiday overlap)
                  x number of instances
                  x utilization %

A daily override, if present, replaces the whole calculation for that date and shift. That is why the Capacity column can differ from the Shift default column: an override is in play.

Diagnosing a Zero-Hour Day

If a date shows zero, work the gate chain in order. Any one of these produces a zero:

  1. The machine is marked unavailable, or its effective date is later than the date.
  2. The date is a work-center holiday for this machine.
  3. The date is a whole-day plant holiday, which zeroes every machine.
  4. It is a weekend and the machine does not run weekends.
  5. A daily override is set to zero for that date and shift.
  6. The shift does not run on that weekday, so it contributes no hours.

Checking these in sequence finds the cause fast. For the deeper version of this diagnosis, see capacity shows zero for a work center.

How to Check It Worked

  1. Confirm the shift default matches your mental math: for a one-instance 8-hour shift at full clock with no downtime, expect 8.
  2. Confirm the Capacity column equals the shift default unless you meant to set an override.
  3. Subtract loaded from capacity to get the genuinely free hours, and use that for the promise.

Common Mistakes

Reading the wrong shift. Capacity is per shift. A day-and-night machine has two figures; check the one the job would run on.

Confusing capacity with free hours. The shift default is total capacity, not what is left. Subtract the loaded hours to see what the machine can still take.

Forgetting the instance count. A three-instance machine offers three times a single machine's hours. If the number looks too high or too low, check the instance count.

Missing an override. If the Capacity column differs from the Shift default, an override is set. Read the Overridden tick and the reason before trusting either number.

Next

Reading a machine's available hours on a date turns a promise from a guess into a number the scheduler agrees with. Zoom out to the month with how to see a work center's load for next month, and change a single day with how to override capacity for one day. More single-task recipes are in the EDGEBIC how-to hub, and the platform overview is at /edgebic.

Expert Q&A: Deep Dive

Q: Sales asked whether the mill can take eight hours next Wednesday and I want a firm answer. How do I get it?

A: Open the mill's per-day capacity view and read next Wednesday's row. The Shift default column tells you the mill's total hours that day, the Loaded column tells you how much is already committed, and the difference is what is genuinely free. If the shift default is 8, the loaded is 3, and there is no override, the mill has 5 free hours that day, so an 8-hour job does not fit in one day and would spill. That is a firm answer grounded in the same number the scheduler uses, not a guess.

Q: A machine reads zero hours on a Tuesday and I cannot see why. What do I check?

A: Walk the gate chain in order. Confirm the machine is marked available and past its effective date. Check for a work-center holiday on that Tuesday and for a whole-day plant holiday. Confirm the shift actually runs on Tuesdays, since a shift with no Tuesday hours contributes nothing. Look for a daily override set to zero on that date and shift. And if the machine runs day and night, check the right shift, because capacity is per shift. One of those six is almost always the answer.

Frequently Asked Questions

Ready to Transform Your Production Scheduling?

User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team

User Solutions Team

Manufacturing Software Experts

User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.

Let's Solve Your Challenges Together