- Home
- Blog
- Glossary (EDGEBIC)
- What Is Planned Value? EDGEBIC Definition and Form…
What Is Planned Value? EDGEBIC Definition and Formula
Planned value is the amount of work, measured in hours, that a job's schedule said should have been finished by a given cut-off date. It is the plan's own answer to "where should we be by now?", and it is the yardstick every schedule performance measurement is taken against. In EDGEBIC by User Solutions it is computed by clipping each scheduled operation's planned window at the report's To date and summing the hours that survive the clip, so an operation straddling the cut-off contributes only its earlier portion.
This entry is part of the EDGEBIC glossary series on the platform overview; for the wider vocabulary of planning terms, see the manufacturing glossary. Planned value is one of three figures that make Earned Value Management work, alongside earned value and the frozen budget at completion.
How Planned Value Works
Think of a training plan for a long race. The full plan is the budget: every session, all the way to race day. Planned value is the mile marker the plan says you should have passed by this morning. It says nothing about how far you have actually run, and nothing about how tired you are. It only states the intention, dated.
That distinction is the whole reason the number exists. Comparing what a job has finished against what it should have finished by now separates two different failures that look identical on a status call. A job can be burning hours faster than budgeted while still being ahead of the calendar, and a job can be beautifully efficient while quietly slipping. You cannot tell them apart from a single completion percentage. You can tell them apart the moment you have a dated expectation to measure against, and that dated expectation is planned value.
The clipping rule is what makes it dated. EDGEBIC does not ask which operations are marked complete, and it does not look at actuals at all. It walks the job's scheduled operations, each of which has a planned start and a planned end, and asks how much of each window sits before the report's cut-off:
- An operation whose planned end is before the cut-off contributes all of its planned hours.
- An operation that straddles the cut-off contributes the hours before it.
- An operation whose planned start is after the cut-off contributes nothing.
Because the calculation reads the plan and only the plan, planned value is stable in a useful way. Logging actuals does not change it. Re-running the report with the same To date gives the same number. What changes it is a reschedule that moves the operations themselves, which is correct: a new plan carries a new expectation.
A Concrete Example
Take job J-100 for product Widget A, with five routing steps.
| Step | Work center | Planned hours |
|---|---|---|
| S1 Cut | Saw-1 | 8 |
| S2 Drill | Mill-1 | 12 |
| S3 CNC | CNC-1 | 24 |
| S4 Deburr | Finish-1 | 4 |
| S5 Inspect | QC-1 | 2 |
Budget at completion is 8 + 12 + 24 + 4 + 2 = 50 hours.
Now run the report with a cut-off that lands halfway through step S4. Steps S1, S2 and S3 are entirely in the past, so they contribute their full 8, 12 and 24 hours. S4 is half past the cut-off, so it contributes 2 of its 4 hours. S5 has not started in the plan, so it contributes nothing.
Planned value = 8 + 12 + 24 + 2 = 46 hours.
Against that, 55 hours have actually been logged on the job, which caps percent complete at 100 and puts earned value at the full 50 hours. Schedule performance index is therefore 50 divided by 46, or 1.09: the job is ahead of where the plan expected it to be. Cost performance index is 50 divided by 55, or 0.91: it is buying that lead with more hours than budgeted. Two honest facts, and neither is visible without planned value in the denominator.
How EDGEBIC Uses Planned Value
Planned value appears as the PV h column on the Earned Value report, sitting between the frozen BAC and the actual hours, and it feeds two of the report's own columns rather than standing alone:
- Schedule performance index is earned value divided by planned value. The report sorts ascending by this index, so the jobs furthest behind their dated expectation rise to the top of the grid.
- When planned value is zero, because nothing on the job was scheduled to finish before the cut-off, the index is returned as 1.0 rather than failing on a division by zero. That guard value is a placeholder, not a compliment.
The cut-off is the report's To date, so planned value is only as meaningful as the range you ask for. Running the report to a date in the far future pushes planned value up to the full budget and makes every job look behind. Running it to today, which is the usual intent, gives the comparison a planner actually wants. The walkthrough in how to run the Earned Value report shows where the columns sit and which date inputs drive them.
One last consequence worth holding onto: because planned value is built from scheduled windows rather than from logged completions, it is only as truthful as the schedule. A routing whose hours per unit were never corrected produces a confident, precise, wrong expectation. If a job's indices look strange before you have investigated the floor, look at the plan first.
Planned value is the amount of work, measured in hours, that a job's schedule said should have been finished by the reporting cut-off date. It is the plan's own answer to the question 'where should we be by now?'. EDGEBIC computes it by clipping every scheduled operation's window to the cut-off date and summing the hours that fall before it, so an operation that is half past the cut-off contributes half its hours.
Budget at completion is the total hours planned for the whole job and never moves once the job is scheduled. Planned value is the slice of that budget the schedule expected to be done by a particular date, so it grows as the cut-off date moves forward and equals budget at completion only once the last operation's planned end has passed. Budget at completion is the finish line, planned value is the mile marker for today.
For each scheduled operation on the job, EDGEBIC takes the planned window between the scheduled start and scheduled end, clips it at the report's To date, and adds up the surviving hours. Operations entirely in the past contribute their full planned hours, operations straddling the cut-off contribute the portion before it, and operations entirely in the future contribute nothing. The result appears as the PV h column on the Earned Value report.
Expert Q&A: Deep Dive
Q: My Earned Value report shows PV 46 hours against a BAC of 50. Why the gap?
A: Because the cut-off date falls partway through the job. In the book's worked example the job has five steps totaling 50 planned hours, and the report is run when the first three steps are fully past and the fourth is half past. Planned value adds 8 plus 12 plus 24 for the finished three, then 2 hours for the half-consumed fourth step, giving 46. The remaining 4 hours belong to work the plan never expected to be done yet, which is exactly why they are excluded. Once the cut-off passes the last step's planned end, PV climbs to the full 50.
Q: My SPI reads exactly 1.0 on a job nobody has touched. Is that real?
A: No, it is a guard value. Schedule performance index is earned value divided by planned value, and when planned value is zero because no operation was scheduled to complete before the cut-off, EDGEBIC returns 1.0 rather than dividing by zero. Read it as 'nothing to compare yet', not 'perfectly on schedule'. Move the report's To date past the first scheduled operation's planned end and the ratio becomes a real signal.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
The EDGEBIC Scheduling Glossary Index
A themed index to the EDGEBIC glossary: scheduling engine, capacity and calendars, materials and planning, shop floor, reporting, quoting, and data import terms, defined in plain language.
What Is the Critical Chain in Manufacturing Scheduling?
The critical chain is the longest dependent path through a plan once shared machine contention is counted, not just step precedence. Here is how it differs from the critical path.
What Does Finite Capacity Mean in EDGEBIC?
Finite capacity means the scheduler refuses to book more hours on a machine than that machine actually has. See exactly how EDGEBIC enforces it, day by day and shift by shift.
