Availability is the OEE factor that measures lost time: the share of a machine's scheduled hours in which it was actually running. In EDGEBIC by User Solutions, availability is actual hours divided by available hours, where available hours come from the shift definition multiplied by calendar days and the instance count. A machine scheduled for 40 hours that ran only 32 has 80 percent availability. The number captures every reason the machine was not making parts when it should have been: breakdowns, holidays, an unrun shift, or a long changeover.
This entry is part of the EDGEBIC glossary series. For the wider planning vocabulary, see the manufacturing glossary. Availability is the first of the three factors that multiply into overall equipment effectiveness; the other two are performance rate and quality rate.
How Availability Works
OEE breaks equipment losses into three buckets, and availability owns the time bucket. It asks a single question: of the hours this machine was scheduled to run, how many did it actually run?
EDGEBIC builds the denominator, available hours, from the calendar rather than a guess. It takes each active shift's total hours, multiplies by the number of calendar days in the window, and multiplies again by the machine's instance count. Where no shifts are configured, it falls back to 8 hours times the number of workdays times instances. The numerator, actual hours, comes from the daily hour breakdown that actuals logging fills in as work happens.
Divide one by the other and you have availability, capped at 100 percent so an over-logged machine cannot report an impossible number. Everything that stopped the scheduled time from turning into run time (a breakdown, a public holiday inside the window, a shift that did not run) lands in the gap between available and actual hours and drags availability down. That is why availability is the honest first read on whether a machine is dependable, before you even ask how fast or how cleanly it ran.
A Concrete Example
Take CNC-1 over a Monday to Friday window, a single 08:00 to 16:00 shift (8 hours a day), one instance.
Available hours:
- 8h per shift times 5 days times 1 instance = 40 available hours
The daily hour breakdown records 32 actual hours, because only 4 of the 5 days ran:
- Availability = minimum of (100, 32 divided by 40 times 100) = 80 percent
The reading: CNC-1 was available 80 percent of the time and lost a full day, 20 percent, most likely to a holiday or a breakdown. In the same window the machine ran at about 86 percent of theoretical throughput and 95.5 percent quality, giving an OEE near 65.5 percent. Of the three factors, that 20 percent availability loss is the biggest single lever for lifting the machine's OEE, which is exactly the kind of steer the number is meant to give a supervisor.
How EDGEBIC Uses Availability
Availability is a column in EDGEBIC's OEE report, next to performance percent, quality percent, and the composite OEE. It is derived per work center for the date range you choose, drawing available hours from the shift and instance configuration and actual hours from the daily hour breakdown. The walkthrough in how to run the OEE report in EDGEBIC shows the full column set and how the three factors combine.
One point to keep straight: availability is not utilization. Utilization, in the Work Center Utilization report, asks how much of a machine's capacity was booked with scheduled work. Availability asks whether the scheduled work actually ran. A machine can look busy in the utilization view yet score low on availability because breakdowns stopped the plan from happening. Reading them together tells you both whether the machine is loaded and whether it is reliable, and that pairing is where OEE earns its place on a supervisor's scorecard.
Expert Q&A: Deep Dive
Q: CNC-1 shows 80 percent availability over a 5-day week. Where did the 20 percent go?
A: It went to a day the machine did not run. In the book's example, CNC-1 was scheduled 8 hours a day across 5 days for 40 available hours, but the daily hour breakdown recorded only 32 actual hours because just 4 of the 5 days ran. Availability is 32 divided by 40, or 80 percent. The lost day, most likely a holiday or a breakdown, is a full 20 percent of availability and is the single biggest lever for lifting this machine's OEE.
Q: Availability reads over 100 percent on one work center. Is that a bug?
A: No, EDGEBIC caps it. The formula is the minimum of 100 and actual hours divided by available hours times 100, so a machine that logged more actual hours than its shift-derived availability, perhaps from unrecorded overtime or a shift not modeled in the calendar, is clamped to 100 percent rather than reporting an impossible figure. If you see it hitting the cap often, check that the work center's shifts and instance count match how it is really run.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
The EDGEBIC Scheduling Glossary Index
A themed index to the EDGEBIC glossary: scheduling engine, capacity and calendars, materials and planning, shop floor, reporting, quoting, and data import terms, defined in plain language.
What Is the Critical Chain in Manufacturing Scheduling?
The critical chain is the longest dependent path through a plan once shared machine contention is counted, not just step precedence. Here is how it differs from the critical path.
What Does Finite Capacity Mean in EDGEBIC?
Finite capacity means the scheduler refuses to book more hours on a machine than that machine actually has. See exactly how EDGEBIC enforces it, day by day and shift by shift.