- Home
- Blog
- EDGEBIC How-To
- How to Run the OEE Report in EDGEBIC
The OEE report in EDGEBIC by User Solutions is in the Reports hub under Executive / KPI: it takes a date range and returns availability, performance, quality and overall equipment effectiveness for every work center. It is the one report that tells you not just whether a machine was busy, but whether the time it spent busy was worth anything. Here is how to run it and read each factor to the action it implies.
For the catalog this sits in, see EDGEBIC reports explained. For the concept itself, overall equipment effectiveness covers the arithmetic in general terms. Every task in this library is mapped on the EDGEBIC how-to hub.
Before You Start
- Work centers have shifts assigned, since availability measures logged hours against what the calendar says was available.
- Actual hours are being logged, or availability reads near zero on stations that ran all week.
- Kiosk punches record good, scrap and rework pieces. Without them, quality and therefore OEE read n/a.
- Routing steps carry pieces per unit and required hours, or performance falls back to an hours-based approximation.
Step 1: Open It and Choose a Window
Open Reports and click OEE in the Executive / KPI group. Set From and To, then OK.
Pick the window to match the question. A single day answers "what happened on Tuesday". A full week smooths out one bad shift. A month is the right grain for a trend conversation, and comparing two consecutive months is how you spot a station drifting downward.
Step 2: Read the Three Factors, Then the Product
| Factor | What it compares | What a low number means |
|---|---|---|
| Availability % | Actual hours against the hours the calendar made available | The station was not running when it could have been |
| Performance % | Actual pieces against theoretical pieces from the routing cycle time | It ran slower than the routing says it should |
| Quality % | Good pieces against good plus scrap plus rework | It made parts that could not be sold |
| OEE % | The three multiplied together | Read the factors, never this alone |
Multiplying is what makes OEE unforgiving. Three respectable factors of 90, 95 and 98 percent give roughly 84%. That is the arithmetic behind the world-class benchmark of above 85%, and it is why chasing the composite number without reading its parts leads nowhere.
Rows arrive sorted with computable OEE first and the n/a rows collected at the bottom, so the readable data is at the top of the grid.
Step 3: Chase a Low Availability
Availability is the factor that moves most in a job shop, and it has two honest causes and one data cause.
- Confirm the work center has its shifts assigned. A station with no shift assignment falls back to a standard assumption, which can overstate available hours on a partial-shift station.
- Confirm the instance count. A station configured with fewer instances than it physically has distorts the available-hours side of the fraction.
- Confirm actuals are being logged for the window. Availability compares logged hours against available hours, so a shop that does not punch will show a low availability on a machine that never stopped.
Cross-check the same station and window in the work center utilization report, which computes available hours from the same shift calendars and shows a per-day picture.
Step 4: Chase a Low Performance
Performance needs the routing to carry a cycle time. When both the pieces per unit and the required hours are present on the steps routed to that station, the report computes theoretical pieces and compares them with what was actually made. When either is missing, it falls back to comparing actual hours against planned hours, which is a much blunter reading.
So the first check on a low performance figure is not the machine. It is the routing. Open the steps routed to that work center and confirm the cycle-time fields are filled. If the station was imported with an efficiency of zero, re-import it with a real value, because there is no editor field for it on the work center dialog.
Step 5: Read Quality Only When Punches Exist
Quality divides good pieces by the sum of good, scrap and rework. All three come from shop-floor punches, so the column is honest about absence: no punches, no quality, and therefore no OEE. That n/a is deliberate, and it is a better answer than a fabricated 100%.
If quality is blank across the board, the fix is adoption rather than configuration. Logging good, scrap and rework at the point of work is covered in how to log actual hours and pieces.
Step 6: Export and Compare Periods
Click Export to Excel. OEE is most useful as a comparison, so run the previous period, export, run the current period, export, and put the two side by side. Stations whose OEE fell by more than a few points are your investigation list.
One condition on that comparison: it is only valid if the routing was the same in both windows. A cycle time edited between the two periods changes the performance denominator, and the two numbers stop being comparable.
What Changes When You Run It
Nothing. The report is read-only and queries fresh each time it opens.
What changes the score is the work behind it: assigning shifts, correcting instance counts, filling cycle times on routings, and getting punches logged. Each of those moves exactly one factor, which is why reading the factors separately matters.
How to Check It Worked
Re-run the same window after a fix and watch the specific factor you targeted. Filling routing cycle times should move performance and leave availability alone. Getting punches submitted should populate quality and lift availability at the same time, because both draw on logged work. If the composite number moved but no single factor did, you changed the window rather than the plant.
Common Mistakes
- Reading n/a as a broken report. It means quality could not be computed from the data available. It is an absence, not an error.
- Quoting OEE without the factors. Two stations at 62% can need completely different responses.
- Comparing across a routing change. Confirm the routing was stable across both windows before comparing two periods.
- Blaming the machine for a data gap. Low availability with no punches in the window is a logging finding, not a maintenance finding.
See how work center capacity and effectiveness fit into the wider plan on the EDGEBIC product page.
Expert Q&A: Deep Dive
Q: One station shows 45% availability and everyone insists it ran all week. Where do I look?
A: Check the two halves of the fraction before you check the machine. Availability compares logged actual hours against the hours the calendar says the station could have produced, so a low score means one of the two numbers is wrong. Most often the actual hours are missing because punches were not submitted, in which case the station really did run and the report is honestly reporting what it was told. The other cause is a shift setup gap: a work center with no shift assigned falls back to a standard assumption that can overstate available hours on a station that only runs a partial shift. Confirm the shift assignment, then cross-check the same station and window in the Work Center Utilization report, which builds available hours from the real calendars.
Q: Performance sits at 60% on a station that is visibly running flat out. Is the report wrong?
A: The report is measuring against your routing, and the routing is probably empty in the fields it needs. Performance compares actual pieces against theoretical pieces derived from the routing's cycle time, so it needs both the pieces per unit and the hours required on the operations routed to that station. When either is zero the calculation falls back to comparing actual hours against planned hours, which measures something quite different and usually reads low. Fill in the cycle-time fields on the routing steps for that station and the column becomes pieces-accurate on the next run. If the station was loaded through the work center import with an efficiency of zero, that also drives the theoretical pieces to zero, so re-import it with a real value.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.