Showing Live Progress on Routing Diagram Nodes in EDGEBIC
The routing diagram in EDGEBIC does not have to be a static drawing of how a product is made: on a scheduled job, each work center node can carry a live details line showing planned hours, actual hours, and dates pulled from that job's schedule. The same flow chart that planned the work becomes a status board in routing order, which is a genuinely different object from a Gantt.
This post covers where the setting lives, what it can show, why the pattern is deliberately separate from the Gantt's bar captions, and how to keep a large diagram readable once numbers land on it. It assumes familiarity with the canvas from the graphical routing designer tour in EDGEBIC by User Solutions.
Where Node Display Fields Live
This is a feature of the Scheduled Job BOR tab, not the standard routing designer, and the reason is straightforward: live progress requires a job. A standard routing is a recipe, and a recipe has no actual hours.
Open the Schedule tab, then the Scheduled Job BOR tab, pick a job in the Schedule Job selector, and switch to Designer. You are now editing that job's own frozen copy of the routing, with a live header strip above the canvas showing job progress, actual versus estimated hours, the current step, the projected finish, and the due date.
Select a work center node and find Node Display Fields in the Properties panel. It works as a small pattern builder:
- Pick a field from the drop-down (its watermark reads Data Source).
- Click Add to append that field's token to the pattern box.
- Repeat to combine fields.
- Tick Apply to all work centers to push the same pattern to every node on the diagram.
- Save with Update this Job BOR.
The pattern box's own hint states the default plainly: empty means the node shows only the work center name.
Why the Default Is Empty
Node boxes deliberately show a single title so large diagrams stay readable. Type and status live in the tooltip and the Properties panel, which is why hovering before editing is the standing advice on this canvas, covered in what a routing node tooltip tells you.
Node Display Fields follow the same restraint. A node stays a name until you opt fields back on, and there is deliberately no automatic fallback to the Gantt's bar caption pattern. That is a design decision worth understanding: every work center ships with a non-empty default caption pattern for the Gantt, so a silent fallback would put text on every node of every diagram the first time anyone opened one. Blank by default, instrumented on purpose.
Two Surfaces, One Token Idea
The Gantt's bar captions and the diagram's node lines are the same idea rendered by the same underlying mechanism, with separate patterns per surface.
| Gantt bar caption | Routing node line | |
|---|---|---|
| Where it is set | Scheduler configuration, per work center | Designer Properties panel, on the node |
| Scope | Every bar on that lane, all jobs | The job whose routing you have open |
| Default | A non-empty pattern identifying job and operation | Empty: name only |
| Best for | Reading the whole plant across lanes | Reading one job in routing order |
That split is the useful part. A milling lane on the Gantt can show remaining hours for every job that touches it, while the diagram for one late job shows planned versus actual on each step of that job specifically. The Gantt token language is covered in reading operation description fields on a Gantt bar.
A site-wide default node pattern per work center can also be set in the scheduler configuration, and the node-level pattern overrides it for the job you are looking at.
What to Put on a Node
The productive combinations are short. Planned hours next to actual hours answers "is this step behaving," which is the question a routing diagram is uniquely good at, because the eye reads the chain in process order rather than in calendar order.
A practical starting pattern:
- Planned hours and actual hours on every node. Two numbers, one comparison, in routing sequence.
- Dates on the constraint step and the final step only, where a slip has downstream meaning.
- Nothing at all on material and product nodes, which book no capacity and have no hours to report.
Two or three fields per node is the ceiling. Past that a diagram of any size stops being a diagram, and you would be better served by the Job View grid, which is built for dense per-operation numbers and is described in the Job View cockpit.
A Worked Reading
Take a job whose routing runs saw, mill, assembly, with the pattern set to planned and actual hours on all three nodes.
- Saw shows 20.5 planned and 20.5 actual. The step behaved, and it is complete.
- Mill shows 51.0 planned and 34.0 actual, and the header strip names it the current step. Two thirds of the way through and tracking to plan.
- Assembly shows 30.5 planned and no actual yet. Not started.
Now the value of the layout: those three readings sit in the order the product is built, so the eye moves the way the material moves. The projected finish in the header tells you where that chain lands, and the due date beside it tells you whether that is a problem. Nobody opened a report, and nobody had to reconstruct routing order from a date-sorted grid.
Save, Then Reschedule, in That Order
One habit prevents confusion. Update this Job BOR saves the recipe and the display pattern for that job's copy only. It does not move anything on the Gantt. The plan changes when you reschedule, and even then, completed steps are never re-planned.
That separation is the same contract that makes per-job routing edits safe on a live floor, described in editing a live job's routing. Change the recipe deliberately, reschedule deliberately, and the two acts never surprise each other.
The Drawing That Reports on Itself
A routing diagram that carries live numbers is a small feature with an outsized effect on how a job gets discussed. Planners argue about sequence in front of a picture of the sequence. Supervisors see which step is eating hours, in the order the parts flow, without translating a calendar back into a process.
User Solutions has been building that kind of shared picture with manufacturers since 1991, from small job shops to organizations including the US Navy, GE, BAE Systems, and Cummins. It is the same reason visual production scheduling beats a table: the picture answers the question the room is actually asking.
See the full EDGEBIC platform, start from the visual scheduling pillar guide, or bring one late job to a demo and let US show you its routing reporting on itself.
Node Display Fields is a per-node setting in the Scheduled Job BOR designer that adds a live details line under a work center node's title, resolved from that job's schedule. You pick a field from the Data Source drop-down, click Add to append its token to the pattern, and repeat to combine fields. Tick Apply to all work centers to push the same pattern across the whole diagram.
Node boxes deliberately show a single title so large diagrams stay readable, with the step's type and status living in the tooltip and the Properties panel instead. The empty default for Node Display Fields follows the same logic: a node shows only the work center name until you deliberately opt fields back on. There is no automatic fallback to the Gantt's bar caption pattern.
They are the same token idea with deliberately separate patterns per surface. The Gantt's caption is set per work center in the scheduler configuration and drives every bar on that lane. The node pattern belongs to the routing diagram and is edited in the designer's Properties panel for the job you are looking at, so each surface stays tuned to its own job.
Expert Q&A: Deep Dive
Q: Our daily standup happens in front of a routing diagram, not a Gantt. Can the diagram carry the numbers?
A: Yes, and that is exactly what Node Display Fields are for. Open the Scheduled Job BOR tab, pick the job, select a work center node, and add planned hours, actual hours, and dates to the pattern, then tick Apply to all work centers so every node carries the same line. The diagram then reads as a status board in routing order: each node shows what it was supposed to take and what it has taken, and the header strip above shows job progress, actual versus estimated hours, current step, projected finish, and due date.
Q: We set a pattern on one node and the rest stayed blank. Did it fail?
A: No, that is the intended scope. The pattern is per node so you can instrument only the steps that matter, such as the constraint machine and the final operation feeding shipping. Tick Apply to all work centers when you want it everywhere, and save with Update this Job BOR. Keep the pattern short either way: two or three fields per node is the practical ceiling before a large diagram stops being readable, which is the reason the boxes ship showing only a name.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
Staged Changes on the EDGEBIC Planner Board
Nothing on the Planner board is written until you press Save Changes, and a machine-only change writes no actual dates at all. What staging protects, and what saving actually records.
Why EDGEBIC Refuses a Drop on the Planner Board
A refused drop is never silent and never destructive. EDGEBIC keeps the machine, keeps your time shift, and puts the reason on the status line. Here is every refusal and what it means.
Why Planner View Focus Is Never Saved in EDGEBIC
Clicking a bar re-orders the machine block for as long as you are looking at it. It is a way of seeing, not a setting, so it never touches your saved configuration.