- Logging Actuals From the Planner in EDGEBIC
In EDGEBIC by User Solutions, the Log Actuals dialog is the planner-side path for recording what really happened on an operation: its real start, the hours and pieces worked each day, and its real end. It is the counterpart to the shop-floor kiosk, and it captures exactly the same actuals into exactly the same model. If your plant runs kiosk terminals, operators punch the data in. If it does not, or if a supervisor needs to enter or correct a day from the office, the Log Actuals dialog does the whole job. This is shop floor data collection driven from the planner rather than the machine.
Actuals are facts, kept strictly separate from the plan. The scheduled dates are never overwritten by what you log, so every screen and report can compare plan against reality. This article walks the dialog end to end so you know what each field writes and what happens when you save.
Opening the Dialog
There are three ways in, and they all reach the same place.
- From the Schedule View Gantt: right-click the operation's bar and choose Log Actuals.
- From the Job View tab: click the Log Actual header button and pick the work center that did the work.
- From the Actual Live view: double-click the step's progress card.
Actuals are logged per operation, meaning per work center, per day. So before you open the dialog you need to know which work center actually ran the step. If the operation has no actual start yet, the Edit Actual Dates dialog opens first.
Setting the Actual Start
An operation is not "in progress" until it has an actual start. In Edit Actual Dates you set Actual Start with one tap: Start = Now stamps the current moment, or Use Sched Start copies the planned start when the work truly began on time. An actual start is written once. If an operator later punches in at the kiosk, the kiosk will not overwrite a start you already recorded, and the reverse is true too.
If earlier operations in the same job have no actuals yet, a Batch Scheduling prompt appears: "Warning! No actual dates logged to prior workcenters!" It lists the missing work centers and explains that continuing will auto-log their planned values as actuals, tagged as system auto-filled. You have a clean choice. Cancel stops so you can log the earlier steps properly, which is the honest path. OK accepts the backfill and continues, and the backfilled days wear a badge so they stay recognizable for later review.
The Daily Hours Grid
With the actual start set, the Log Actuals grid opens. It has one row per calendar day of the operation's window.
| Column | What it holds |
|---|---|
| Date | The calendar day |
| Sched Hrs / Sched Pcs | What the plan expected that day |
| Actual Hrs | The real hours worked that day, type here |
| Actual Pcs | Good pieces produced that day, type here |
| Rate (Pcs/Hr) | The pieces-per-hour rate used to convert between the two |
| Source | Blank for hand-entered days, a badge on days the system filled from plan |
Leave Auto Calc Hours ticked to type just one side. Enter 6 in Actual Hrs and the pieces fill in from the rate, or enter the pieces and the hours derive. The rate comes from the routing step and the work center, and it is the same effective rate the kiosk uses, so a day logged from the planner and a day punched at the machine convert identically. For the full conversion mechanics, see how hours and pieces convert on the floor.
Any day showing the auto-filled badge holds a value the system guessed from plan. Edit it to replace the guess with reality, and the badge disappears the moment you change the value: that day is now a normal hand-entered day.
Saving, Reasons, and History
Click Save and the day values persist. Two things guard the record. First, if you changed values that had been reported before, EDGEBIC asks for a reason, which is stored in the logging history for audit. An empty reason cancels the save rather than silently overwriting. Second, the same prior-work-center prompt can appear here too, plus a prior-days variant if earlier days of this same operation are still empty.
Use View History to see every past entry and edit, with who, when, the old value, the new value, and the reason. History is append-only, so corrections are added, never erased. Use Log Actual Dates to adjust the operation's actual start and end from inside the dialog.
For a one-cell correction you do not need the full dialog at all: double-click the Actual Hours or Actual Pieces cell of an operation row in the Job View grid to open the Quick Log popup, with Date, Hours, Pieces, an Auto-calc toggle, and Save.
Marking the Operation Complete
Logging hours does not close an operation. Completion is explicit. Double-click the operation's Actual End cell in the Job View grid and set the end with End = Now or Use Sched End, then save. EDGEBIC refuses an actual end that is not after the actual start: an inverted pair is always a data-entry error, and the save is blocked with a clear message.
When you record completion without an explicit end time, EDGEBIC snaps the actual end to the end of the last day that has logged hours, meaning 23:59 of that day. That is why a job started at 08:00 and completed the same day never ends up finished before it began. An operation also counts as done when its logged hours have fully covered the planned hours, even if no end was stamped.
What Saving Changes
Saving actuals ripples across the platform in a predictable way.
| Surface | Effect |
|---|---|
| The operation row | Actual start, end, and per-day hours and pieces stored next to the plan |
| Gantt bar | Moves to its actual position, showing in-progress or completed |
| Job View header and Job Progress | Actual Hours, Remaining, and % Complete recompute from the schedule rollup |
| Parallel sibling rows | Automatically mirrored from the primary you logged |
| Logging history | Every entry and edit recorded with its reason |
| The next reschedule | The big one: completed work is frozen, remaining work re-plans from where you really are |
That last row is the whole point. Actuals are not bookkeeping after the fact, they steer the next scheduling run. Because completed work is immutable, the engine plans remaining work forward from reality, which is how a reschedule uses last night's actuals to keep every downstream promise honest.
The Bottom Line
The Log Actuals dialog gives a planner or supervisor full control over an operation's real dates, daily hours, and pieces without ever touching the plan. Set the actual start, type one side of the day grid and let the rate derive the other, give a reason on any change to a reported value, and stamp the end when the work is truly done. From there the same clean finite capacity scheduling loop that a kiosk feeds runs off your entries. See the whole cycle in the shop floor execution guide, or explore the platform at EDGEBIC.
Expert Q&A: Deep Dive
Q: I only have the planner app on my floor, no kiosk terminals. Can I still capture real hours per day?
A: Yes. The kiosk is one source of actuals, but the Log Actuals dialog in the planner is a complete second path. Open it on any scheduled operation, set the actual start if it has none, then type each day's real hours in the grid. For a single fast fix you do not even need the full dialog: double-click the Actual Hours or Actual Pieces cell on the Job View grid to open the Quick Log popup with Date, Hours, Pieces, and a Save button.
Q: I changed a Monday value that a supervisor had already reported and EDGEBIC asked me for a reason. Why?
A: Any edit to a value that was reported before requires a reason, and the reason is stored in the logging history for audit. This is deliberate: the first entry stands as a record, and every later change is tracked with who, when, the old value, the new value, and why. If you leave the reason empty the save cancels rather than quietly overwriting the earlier number. Open View History from the dialog to read the full append-only trail.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
The Schedule Reconciliation Report in EDGEBIC, Explained
Eight parameter checks over two exception grids. See how EDGEBIC reconciles the plan against the plant and shows only the rows that disagree.
Why a Dependent-Parallel Child Is Exempt From the Over-Booked Check
Three synchronized drills book 24 hours on an 8 hour day. That is real plant behavior, not a capacity breach, and flagging it would make the whole check useless.