How to Set What Happens When a Backward Job Doesn't Fit in EDGEBIC
To set what happens when a backward job doesn't fit in EDGEBIC, open Settings, go to the Schedule tab, and under "When a Backward Job Doesn't Fit" choose either "Accept the forward schedule" or "Show a popup so I can review it," then click Save. The choice is site-wide policy, it applies to the next scheduling run, and it needs no restart.
Backward scheduling in EDGEBIC by User Solutions places a job just in time, so its last step ends on the due date and spare time sits deliberately in front of the work. Sometimes there simply is not enough free capacity to fit a job before its due date. Backward scheduling never fails outright in that case, because a forward fallback plan (start as early as possible and finish whenever the work allows) always exists. This setting decides one thing only: whether EDGEBIC applies that fallback quietly or stops to ask you first.
Before You Start
- You use backward scheduling. This policy only ever fires for jobs whose direction is Backward. If every job runs forward, the setting never has an effect. See how to set the default scheduling policy.
- You can reach the Settings tab. The Settings navigation tab is permission controlled.
- You understand this is behavior, not data. Nothing is stored on your orders; the setting only changes whether you are interrupted.
- You can run the scheduler. The new behavior applies on the next Drive Schedule run, not retroactively.
Step 1: Open the Schedule Policy Screen
Open the Settings tab from the main navigation. Select the Schedule tab. This screen holds the site-wide scheduling policy: the rulebook the engine reads on every run.
Step 2: Find the "When a Backward Job Doesn't Fit" Group
Scroll to the When a Backward Job Doesn't Fit group. It offers two options:
| Option | What it does |
|---|---|
| Accept the forward schedule | If a backward job cannot fit before its due date, EDGEBIC quietly keeps the earliest possible forward plan and the run completes |
| Show a popup so I can review it | The run pauses and shows the "doesn't fit" dialog so you can accept, adjust dates and re-run, or cancel |
Step 3: Choose the Behavior You Want
Pick Accept the forward schedule if you value uninterrupted runs and will catch slips on a report. Pick Show a popup so I can review it if a missed promise date must never pass unnoticed. The default is to accept the forward plan silently.
Step 4: Save
Click Save. The status line confirms the change. There is no restart: the next scheduling run reads the new policy.
What Changes When You Save
| Surface | Effect |
|---|---|
| The setting | Saved as site-wide policy immediately |
| Existing orders | Unchanged, no data is stored on any job |
| Next scheduler run | A backward job that cannot fit either applies the forward fallback silently or shows the review dialog, per your choice |
How to Check It Worked
- Create or keep a backward job with a due date that is realistically tight against current load.
- Run Drive Schedule.
- If you chose the popup, the doesn't fit dialog should appear for that job, showing the earliest possible forward plan. Accept, adjust and re-run, or cancel.
- If you chose to accept silently, the run completes without a prompt. Open the Late Jobs report and confirm the job appears there if its scheduled end now exceeds its due date.
Common Mistakes
Expecting the popup on forward jobs. The dialog only ever fires for jobs whose direction is Backward. A forward job simply schedules as early as it can and this policy is not consulted.
Thinking the setting can miss a date on your behalf. It cannot make a plan worse. The forward fallback is the same plan you would get either way. The setting only controls whether you approve it in the moment or read about it afterward.
Changing it and not re-running. Policy is read at the next scheduling run. Save, then run Drive Schedule, or nothing appears to change.
Turning on the popup on a rapid-experiment planning station. If your planner runs the scheduler many times an hour, the review dialog will interrupt every tight run. Leave it on accept for that workflow and rely on the Late Jobs report.
Next Steps
This policy is the safety valve on just-in-time planning: decide once whether an impossible finish date should stop you or be caught on a report. Pair it with a deliberate direction choice in how to set the default scheduling policy, and understand the forward fallback itself in forward vs backward scheduling. More single-task recipes live in the EDGEBIC how-to hub, and the platform overview is at /edgebic.
Expert Q&A: Deep Dive
Q: We promise firm dates to automotive customers and can never afford to miss one silently. Which option do we pick?
A: Choose 'Show a popup so I can review it'. With that setting, whenever a backward job cannot finish by its due date, the run pauses and shows the doesn't fit dialog with the earliest possible forward plan. You can accept it, adjust the dates and re-run, or cancel. The point is that a slipped promise date becomes a decision you make on purpose rather than a surprise on next week's Late Jobs report. The tradeoff is that busy weeks with several tight jobs will interrupt you more often, which is exactly the visibility you asked for.
Q: Our planner runs Drive Schedule dozens of times a day while experimenting and does not want popups every run. What should we set?
A: Keep the default, 'Accept the forward schedule'. Backward jobs that cannot fit just resolve to their earliest possible forward plan and the run completes without stopping. You then catch any slip by opening the Late Jobs report, which ranks jobs whose scheduled end exceeds their due date worst first. This keeps rapid what-if runs friction free while still giving you a clear place to check for at-risk dates once the experimenting is done.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.