To set a default setup time for a work center in EDGEBIC by User Solutions, enter the changeover time in hours in the work center's Setup Time field. New routing steps on that machine inherit the value, and the scheduler falls back to it whenever no more specific setup time applies to a step.
The default is the floor of a four-rung ladder, not the whole story of setup time. It is the right tool for a steady, always-applies changeover, and the wrong one for changeovers that depend on what ran before. This page covers the default and where it sits. For sequence-dependent changeovers, read how to build a setup matrix.
Before You Start
- The work center already exists (how to add a work center).
- You know the typical changeover for the machine, as a flat average in hours.
- You understand this is a baseline. If setup depends on the product sequence, a matrix will serve better than a flat number.
Step 1: Open the Work Center for Editing
Open the Workcenter tab. On the Work Center Management grid, click ✏️ Edit on the machine's row. The Work Center Configuration dialog opens on the Basic Information tab.
Step 2: Enter the Setup Time
In the Setup Time (hrs) field, enter the changeover time in hours. A 30-minute setup is 0.5; a 20-minute setup is roughly 0.33. This is the flat default the machine applies.
Step 3: Save
Click Save. New routing steps created on this machine will inherit the value.
Where the Default Sits in the Ladder
At scheduling time, EDGEBIC finds a step's setup time by walking a fixed order and taking the first value it finds:
| Rung | Source | When it applies |
|---|---|---|
| 1 | Setup matrix, product-pair entry | A specific from-product to-product changeover is defined |
| 2 | Setup matrix, family entry | A family-level changeover is defined |
| 3 | The routing step's own setup time | The step carries its own value |
| 4 | The work center default | Nothing above applies |
The work center default is the last resort. Any setup time on the step, and any matrix entry, wins over it. That is why a step can show a different setup time than the machine default without anything being wrong.
A Worked Example
A press has a default setup time of 0.33 hours, a steady 20-minute changeover. A new routing step created on the press inherits that 0.33. When a job runs the step, the operation's total time is the run time plus the inherited setup: a 6-hour run becomes 6.33 hours on the schedule, and that setup portion is protected so the plan does not promise the press back to back with no changeover.
Later the shop realizes that changing from a heavy die to a light one on the same press actually takes an hour, while like-to-like changes take almost nothing. That is a sequence-dependent pattern the flat 0.33 cannot capture: it over-promises the hard changes and pads the easy ones. The fix is not a bigger default, it is a setup matrix that says one number for the heavy-to-light pair and another for like-to-like, with the 0.33 default still sitting underneath as the catch-all for any pair the matrix does not name.
What Changes When You Save
| Surface | Effect |
|---|---|
| New routing steps on this machine | Inherit the default setup time |
| Existing routing steps | Keep the setup time they already carry |
| Steps with a matrix entry or their own setup | Unaffected; the default sits below them in the ladder |
| Next Drive Schedule run | Applies the resolved setup time per step |
How to Check It Worked
- Create a new routing step on the machine and confirm it picks up the default setup time.
- Schedule a job that uses the step and check that setup is included in the operation's time.
- If a step shows a different setup time, walk the ladder: check the step's own value and any matrix entry before assuming the default failed.
Common Mistakes
Using a flat default for sequence-dependent changeovers. If setup depends on what ran before, such as paint colors or alloys, a single number over-promises the easy changes and under-promises the hard ones. Use a setup matrix for those machines.
Expecting the default to override existing steps. It is inherited by new steps only. Existing steps keep their own values.
Assuming the default always wins. It is the last resort. A step-level setup time or a matrix entry takes priority, by design.
Entering minutes instead of hours. The field is in hours. A 30-minute setup is 0.5, not 30.
Next
A default setup time gives a machine a sensible changeover baseline so you are not typing the same number onto every routing step. Layer a setup matrix on top where changeovers depend on sequence, and keep an eye on the work center configuration mistakes that setup values commonly cause. More single-task recipes are in the EDGEBIC how-to hub, and the platform overview is at /edgebic.
Expert Q&A: Deep Dive
Q: Every job on our press really needs about 20 minutes to change over. Do I set that on each routing step or on the machine?
A: Set it once as the work center default so new routing steps on the press inherit it, rather than typing 0.33 hours on every step by hand. The default is the flat, always-applies changeover for the machine. If some product changes on that press take much longer than 20 minutes because of what ran before, that is a sequence-dependent case, and a setup matrix will serve you better than a single flat number. Use the default for the steady baseline and the matrix for the changeovers that depend on order.
Q: We set a work center default but one routing step still uses a different setup time. Is the default broken?
A: No, that is the ladder working as designed. The work center default is the last resort, so any setup time already on the routing step wins over it, and a sequence-dependent matrix entry wins over both. If a step shows a setup time you did not expect, check the step's own setup field and the setup matrix before assuming the default failed. The default only fills in where nothing more specific has been set for that step.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.