How to Resume a Job From Where the Shop Actually Is in EDGEBIC
To resume a job from where the shop actually is in EDGEBIC, log the actuals on its finished and running steps, then reschedule the job. EDGEBIC by User Solutions sets a resume point from those actuals and replans every not-started step forward from it, while completed steps stay frozen and only the remaining hours of a running step move. The habit is simple: log first, reschedule second.
This is the resume procedure. For what a reschedule preserves, read how EDGEBIC preserves completed work on reschedule; for a full narrative, see the partial completion reschedule walkthrough. It is one of the task guides in the EDGEBIC how-to hub.
Before You Start
| Prerequisite | Why it matters |
|---|---|
| Actuals are logged and current | The resume point is derived from your actuals; stale actuals produce a stale plan. |
| You know the job's real position | You are replanning the future around where the floor actually is. |
| You will reschedule the job after logging | Logging alone does not move the plan; the run does. |
The Three Zones
Every operation of the job falls into one zone, and resuming treats each differently:
| Zone | Condition | What resuming does |
|---|---|---|
| Completed | Real start and end recorded | Preserved verbatim. Never moved, shrunk, or recomputed. |
| In progress | Started, not finished | Logged hours locked on their real days; remaining hours replanned on the same machine. |
| Not started | No actuals | Replanned from the resume point against current capacity. |
Step by Step
- Log the actuals. At the kiosk or in the actuals path, record the real start and end of completed steps and the real start plus logged hours of the running step. See how to log actual hours and pieces for the mechanics.
- Reschedule the job. Tick the job on the Drive Schedule tab and press Schedule + Re-Schedule, or use the Re-Schedule button on the Job View tab for that single job.
- Confirm the prompt and let the pass complete.
The engine reads your actuals, sets the resume point to the later of the last completed step's real end and any in-progress step's projected end, and queues the not-started steps behind it.
A Worked Resume
Take a three-step job planned to run cut, mill, then assemble on a day shift. The saw hit a blade change and step 1 actually ran Monday 09:15 to 14:00 instead of the planned 08:00 to 12:30. Steps 2 and 3 have no actuals.
You log step 1 and reschedule. The engine:
- Preserves step 1 verbatim at Monday 09:15 to 14:00.
- Sets the resume point to Monday 14:00, step 1's real end.
- Replans step 2 forward from Monday 14:00 on the mill, spilling across shifts as needed.
- Replans step 3 behind step 2, respecting any queue time and the assembly calendar.
The job's end moves out to a date you can promise, and step 1's bar never moved a minute.
How to Check It Worked
- Open the job in Job View and confirm the completed step shows exactly the actual start and end you logged.
- Confirm the not-started steps now begin at or after the resume point, not at their old planned times.
- Read the hours header. Actual Hours must be unchanged by the reschedule; only planned timing moves.
- Press Job Audit to see the reschedule event with the job's old end next to its new end.
When to Resume and When to Leave It
Resuming is the right move whenever the floor has drifted from the plan and the drift matters downstream. A step that ran long, a blade change that ate a morning, a job that started late: each of these makes the old plan optimistic, and resuming replaces the optimism with a date you can actually promise. Shops that resume on a daily rhythm against fresh actuals keep their promise dates honest.
There are cases where you leave it alone. If a job is fully complete, resuming does nothing useful; the engine recognizes it as done and writes it back unchanged. If the drift is tiny and no downstream step or due date is affected, a reschedule just churns the plan for no gain. And if the actuals are not yet logged, resuming would replan against fiction, which is worse than not resuming at all.
The discipline that makes resuming trustworthy is the same one that makes any reschedule trustworthy: log reality first, then let the engine replan the future around it. Thirty seconds on the audit trail afterward confirms what moved and what did not before a customer asks.
Common Mistakes and Gotchas
- Rescheduling before logging. The resume point comes from actuals. If the floor moved on and nobody logged it, the job resumes from fiction. Log first.
- Expecting an in-progress step to become two operations. It stays one row whose window spans the logged portion and the replanned remainder. That is by design.
- Thinking completed steps moved. They cannot. If dates look different, check whether a different row of the same step's work center pair changed, using Job Audit.
- Missing early steps that were never logged. If a later step has actuals but earlier ones do not, the engine infers the earlier ones ran and backfills them, so the resume point stays honest. Log what you can to keep it accurate.
For the wider reschedule story, read EDGEBIC rescheduling explained, and to understand a step that finished with fewer hours than planned, see how to configure scheduling policy. When the resume is triggered by a machine returning to service, how to reschedule after a machine comes back online is the companion recipe.
Bring a job that ran off plan and we will resume it against your data in one session. Contact US to book it, or read the EDGEBIC product overview first.
Log the actuals on the completed and in-progress steps, then reschedule that job. The engine sets the resume point from your actuals, either the real end of the last completed step or the projected end of the step running now, and replans every not-started step forward from there. Completed steps are preserved and only the remaining hours of an in-progress step move.
The resume point is the earliest moment remaining work may begin. It is the later of the last completed step's real end and any in-progress step's projected end. The engine derives it from your logged actuals, then queues all not-started steps behind it. That is why logging actuals before rescheduling matters: a stale resume point produces a stale plan.
No. Completed steps are historical fact and stay exactly where they are, and a started step keeps its work center. Resuming only replans the not-started steps and the remaining hours of an in-progress step, forward from the resume point. If a completed step appears to have moved, what actually changed is a different row of the same step's work center pair, not the recorded work.
Expert Q&A: Deep Dive
Q: Step 1 finished two days late because of a blade change. How do I get steps 2 and 3 to reflect that instead of the old plan?
A: Log step 1's real start and end at the kiosk or in the actuals path, then reschedule the job. The engine preserves step 1 verbatim, sets the resume point to its real end, and replans steps 2 and 3 forward from there against current capacity. The job's end moves out to a date you can actually promise, and step 1's bar never moves a minute.
Q: An operation is half done. How does resuming handle the hours already logged?
A: The logged hours stay locked on their real days and only the remaining hours get a new future slot on the same work center. On your screens it stays one operation whose window now spans both the logged portion and the replanned remainder. The next step queues behind the remainder, so the whole tail of the job resumes from reality rather than from the original plan.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.