How to Restrict the Job View to a Date Window in EDGEBIC

User Solutions TeamUser Solutions Team
|
7 min read

To restrict the Job View to a date window in EDGEBIC, set the Start and End date pickers on the Job View tab: the Gantt strip then spans only those dates, and clearing either picker falls that edge back to the job's own first or last date. The default window is today minus 7 days through today plus 3 weeks, which keeps recent history and near-term plan on screen without scrolling. The window is a view control in EDGEBIC by User Solutions, so narrowing it changes what draws and nothing about the plan itself.

This post covers the one task. To read the bars once they are on screen, see reading the EDGEBIC Gantt: planned versus actual; the full task library is at the EDGEBIC how-to hub.

Before You Start

  • At least one job has been scheduled, so the Job View has operations to draw.
  • You are on the Job View tab and have picked a job in the Select Job: dropdown.
  • You understand that the window filters the drawing only. The header hours roll-up always sums the whole job.

The Steps

  1. Open the Job View tab and select a job in the Select Job: dropdown.
  2. Set the Start: picker to the earliest date you want on the strip.
  3. Set the End: picker to the latest date you want.
  4. To open one edge, clear that picker. Start clears to the job's own first date; End clears to the job's own last date.
  5. To reset, clear both pickers and the strip spans the job's full first-to-last range.

The default window (today minus 7 through today plus 3 weeks) is already set when you open the tab, so most days you never touch the pickers at all.

What Changes When You Save

There is no save step. The window applies as soon as you change a picker.

SurfaceEffect
The Gantt stripDraws only operations that fall inside the Start-to-End window.
The summary headerUnchanged. Total, Actual, Remaining, and Percent Complete always roll up the whole job.
The per-operation gridShows the job's operations regardless of the strip window.
The planNothing. The window is a view bound; no schedule dates move.

How to Check It Worked

Read the strip against the pickers: the leftmost visible date should match Start (or the job's first date if Start is cleared), and the rightmost should match End. If an operation you expected is missing, confirm it falls inside the window before assuming anything is wrong. Operations before Start or after End correctly do not draw.

Common Mistakes

Reading a narrow window as lost work. The window trims the drawing, never the data. Every operation still counts in the header roll-up. Widen the pickers or clear one to bring bars back.

Setting End before Start. The view clamps to a single day rather than blanking. If the strip suddenly shows one column, check that End is later than Start.

Confusing this window with the scheduler Gantt's range. The whole-plant scheduler Gantt on the Schedule View is a different control with its own default (today plus 30 days) and its own Refresh. Changing the Job View pickers does not affect it.

Blaming the window for a filtered job. If a whole job is missing rather than a few operations, the cause is usually the job filter or an unscheduled operation, not the date window. Check the job's checkbox and its schedule status first.

What to Do Next

The date window bounds the drawing; the zoom controls change how tightly that window is spread across the screen. To combine the two, read how to zoom the Gantt timeline in EDGEBIC. When you are ready to act on what the window shows, drag and drop rescheduling in EDGEBIC covers moving the operations you have brought into view, and the EDGEBIC product page puts the Job View in the context of the whole scheduler.

Expert Q&A: Deep Dive

Q: A long job runs three months but I only care about this fortnight's operations. How do I focus?

A: Use the Start and End pickers on the Job View tab as a hard window. Set Start to the Monday of this fortnight and End to the Friday two weeks out, and the Gantt strip trims to exactly those operations while the summary header still rolls up the whole job's hours. The pickers filter the drawing, not the data, so nothing is hidden from the plan or the totals. When you want the whole span back, clear either picker and that edge falls back to the job's own first or last date, which for a three-month job means the full run reappears instantly.

Q: I set a window and now half my operations vanished. Did I lose work?

A: No, you lost visibility, not data. The date window only decides which operations draw on the strip; every schedule row still exists and still counts in the header roll-up of Total, Actual, Remaining and Percent Complete. The most common cause is a window narrower than the job, so operations before Start or after End simply do not paint. Widen the pickers, or clear one of them to let that side fall back to the job's own bound, and the missing bars return. If a bar is still missing after that, the cause is a job filter or an unscheduled operation, not the date window.

Frequently Asked Questions

Ready to Transform Your Production Scheduling?

User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team

User Solutions Team

Manufacturing Software Experts

User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.

Let's Solve Your Challenges Together