How to Extend Short Operation Bars on the Gantt in EDGEBIC
To extend short operation bars on the Gantt in EDGEBIC, open the Schedule View, go to the Configuration tab, and set Extend Op. if below Hours under the Operations group, then click Save and Apply Now Configuration. Operations shorter than that value are drawn wider so they stay clickable. It is a display setting only and does not change the schedule.
Short operations, a quick inspection or a setup-only step, can shrink to a sliver on a zoomed-out timeline and become impossible to click. EDGEBIC by User Solutions solves this with a display minimum: any bar below a chosen number of hours is drawn at least that wide. The true duration is untouched; only the drawing changes.
Before You Start
- You have short operations that are hard to click on the current timeline.
- You can reach the Configuration tab. It sits in the Schedule View beside the Scheduler sub-tab.
- You understand this is display only. Widening a bar never changes its real hours or the plan.
- You know your usual zoom level. The more zoomed out you work, the higher a value you may want.
Step 1: Open the Configuration Tab
Open the Schedule tab, then the Schedule View sub-tab, then select Configuration. Stay on the General tab.
Step 2: Find the Operations Group
Locate the Operations group. It holds the bar drawing options.
| Setting | Default | What it changes |
|---|---|---|
| Extend Op. if below Hours | 1.0 | Bars shorter than this many hours are drawn wider so they stay clickable, display only |
Step 3: Set the Value
Enter the minimum, in hours. A value of 1.0 means any operation under an hour is drawn at least an hour wide. Raise it if you work zoomed out and still lose short bars; lower it toward zero if you want widths to track true duration exactly.
Step 4: Apply the Change
Click Save and Apply Now Configuration at the bottom. The timeline redraws with short bars widened to the new minimum.
What Changes When You Apply
| Surface | Effect |
|---|---|
| Narrow bars on the Gantt | Drawn at least the minimum width, so they stay clickable |
| The operation's real hours | Unchanged, the engine still uses true duration |
| Reports and actual times | Unaffected, they always reflect real hours |
How to Check It Worked
- Find an operation you know is only a few minutes long.
- Confirm its bar is now wide enough to click and select.
- Open the operation and check that its real start, end, and duration are unchanged, only the drawing widened.
- If short bars still disappear when you zoom out, raise the value and apply again.
Common Mistakes
Expecting the schedule to change. The setting only widens the drawing. Real hours, dates, and capacity are untouched.
Setting it too high. A large minimum makes many short bars look the same width and can create visual overlap between quick back-to-back steps. Zoom in or lower the value if that bothers you.
Forgetting to apply. The change takes effect only after Save and Apply Now Configuration.
Reading widths as durations. When the minimum is on, a bar's width no longer maps exactly to its hours. Use the reports and actual times for precise numbers.
Next Steps
Bar width is one of several readability options on the Configuration tab. To control what each bar says, see how to change what a Gantt bar label shows, and to fit more or less on screen, see how to zoom the Gantt timeline. To carry your tuned settings to another machine, see how to copy your scheduler display settings. More single-task recipes live in the EDGEBIC how-to hub, and the platform overview is at /edgebic.
Expert Q&A: Deep Dive
Q: Some of our setup-only and inspection steps are just a few minutes long and vanish on the Gantt so I can't click them. What's the fix?
A: Open the Configuration tab in the Schedule View, and on the General tab set Extend Op. if below Hours in the Operations group to a value like 1.0, then click Save and Apply Now Configuration. Any operation shorter than that is drawn at least that wide, so those few-minute steps become a clickable bar you can select and open. Nothing about the schedule changes: the step still runs for its true few minutes, it is only drawn wider so you can work with it. If they still feel small when you are zoomed way out, raise the value further.
Q: After I set a minimum bar width, the timeline looks like several short steps overlap. Is my schedule wrong?
A: No, the schedule is fine. Widening short bars for readability can make adjacent quick steps look like they overlap on screen even though their real times are back to back. The engine still holds the true, non-overlapping durations. If the visual crowding bothers you, zoom in so each bar has room, or lower the Extend Op. if below Hours value so widths track real duration more closely. Trust the reports and the actual times over the widened display when you need the exact picture.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.