- What Is Shift Time in Production Scheduling?
Shift time is the definition of a single day's working slot within a shift, a start time, an end time, and a break, that the scheduler decodes into the productive hours a work center has that day. It is the smallest building block of the capacity calendar, and every scheduled hour ultimately rests on it.
This entry defines shift time and shows how it reads inside EDGEBIC by User Solutions. For the wider index of terms, see the manufacturing glossary; for the limits that sit on top of it, see what is an overtime allowance in shift scheduling; and for the full calendar setup, see EDGEBIC shifts and calendars explained.
How it works
A shift is a named pattern of working hours, and it holds a shift time for each weekday it runs. Each shift time carries three values: a start time, an end time, and a break duration. The scheduler computes the day's productive hours as the span between start and end, minus the break.
The default slot runs 08:00 to 17:00 with a one-hour break, which yields eight productive hours. A weekday with no shift time is simply not a working day for that shift, which is how weekends and closures are expressed without any special flag.
Those productive hours are the base, not the final capacity. The engine takes the day's hours from the shift time, then multiplies by the work center's instance count and applies its utilization percentage to reach the schedulable capacity. Because everything downstream builds on the shift time, an error here propagates, which is why it is the first thing to get right.
A concrete example
Think of a shop's door sign: "Open 8 to 5, closed 12 to 1 for lunch." Anyone reading it knows the shop is available eight hours that day. A shift time is that sign for one weekday, and the scheduler reads it exactly that literally: open at start, closed at end, minus the posted break.
Take a day shift set 08:00 to 16:00 with a one-hour break. The gross span is eight hours, minus one hour of break, so the day contributes seven productive hours per instance. If the work center has two instances and a 100% utilization setting, that is fourteen schedulable hours for the day. Change the break to half an hour and the day gives 7.5 productive hours per instance instead. The scheduler never places work outside that window.
How EDGEBIC uses it
In EDGEBIC, shift times are configured on each shift as its daily working hours and decoded into per-day capacity when the scheduler runs. A weekday present in the shift's daily hours is open for that shift; a weekday absent is closed, which is how non-working days are modeled without a separate rule.
From those base hours the engine layers the rest of the capacity picture: the work center's instance count, its utilization percentage, and any downtime or holiday that removes time. So the shift time is where the calendar begins, and every richer capacity number, including the limits an overtime allowance describes, sits above it.
Getting shift times accurate keeps the whole plan honest, because the engine will only ever schedule into the hours a shift declares open. To see the overtime ceiling and flag that ride on top, read what is an overtime allowance in shift scheduling; to configure the full calendar, read EDGEBIC shifts and calendars explained. For the general concept, see shift scheduling.
Expert Q&A: Deep Dive
Q: My day shift is set 08:00 to 16:00 but jobs are getting seven hours a day, not eight. Where did the hour go?
A: Check the break duration on the shift time, because productive hours are the span minus the break. An 08:00 to 16:00 slot is an eight-hour gross span, but a one-hour break leaves seven productive hours, which is exactly what you are seeing. If seven is wrong, adjust the break; if seven is right, the number is behaving correctly. Remember too that the work center's utilization percentage then scales these base hours further, so the schedulable capacity can be lower again once that factor is applied.
Q: I need Saturday capacity for a rush. Do I change the shift's start and end times?
A: No, start and end times only define the length of a day the shift already runs. To add Saturday, you give the shift a shift time for Saturday, with its own start, end, and break. Until Saturday has a shift time, the day is treated as closed and the engine will not place work there no matter how the weekday hours are set. Add the Saturday slot and the scheduler immediately has that day's productive hours available, then applies the work center's instance count and utilization as usual.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
The EDGEBIC Scheduling Glossary Index
A themed index to the EDGEBIC glossary: scheduling engine, capacity and calendars, materials and planning, shop floor, reporting, quoting, and data import terms, defined in plain language.
What Is the Critical Chain in Manufacturing Scheduling?
The critical chain is the longest dependent path through a plan once shared machine contention is counted, not just step precedence. Here is how it differs from the critical path.
What Does Finite Capacity Mean in EDGEBIC?
Finite capacity means the scheduler refuses to book more hours on a machine than that machine actually has. See exactly how EDGEBIC enforces it, day by day and shift by shift.