Independent parallel processing runs one operation on two or more machines at the same time, with the work split across them and each machine checking its own capacity, so the job finishes faster. Unlike a synchronized head where machines mirror one schedule, independent parallel machines each carry a real share of the load and each are genuinely capacity-checked. The result is throughput: an operation that would take sixteen hours on one machine finishes in eight on two.
EDGEBIC by User Solutions schedules these machines through a simultaneous-slot search so they all start together. This article defines the term and its trade-off. The full validation chain and worked cases are in how EDGEBIC handles parallel work centers.
How It Works
You mark a routing step as independent parallel and list the secondary machines as alternatives. Each secondary machine is set to be capacity-checked, which is what makes it independent rather than a mirror. When the engine schedules that step, it looks for a simultaneous slot: a date, shift, and start time where every machine in the group has open capacity at the same moment.
Once it finds that window, the operation's hours are split across the machines and each machine's capacity pool is consumed normally. The machines run at the same time on their own share of the work, and the job completes when they finish. Because the load is divided, the wall-clock time drops in proportion to the number of machines.
The catch is the all-or-nothing rule. Every machine in the group must be free at the same moment or none of them start. If one machine is down for maintenance, the engine does not let the others run alone. It searches forward for the next window where all machines are available, then starts the group there. That guarantees the operation is truly parallel, at the cost of waiting for a common opening.
A Concrete Example
Picture an assembly step that needs sixteen hours of work, with two identical assembly lines available. Run it on one line and it takes two full shifts. Mark it independent parallel across both lines and the engine finds a Monday day shift where both are free. It splits the work: eight hours on Assembly-1, eight hours on Assembly-2, both running Monday 08:00 to 16:00. The job finishes Monday at 16:00, eight hours of wall-clock time instead of sixteen. Throughput doubled by dividing the work.
Now suppose one line is down Monday and Tuesday for maintenance. The all-or-nothing rule kicks in. The engine will not start the free line alone. It searches ahead, finds Wednesday when both lines are open, and starts them together then. The job is delayed two days rather than run at half strength, because a parallel operation that runs on one machine is not a parallel operation at all.
When It Helps and When It Does Not
Independent parallel pays off when an operation can genuinely be divided and you have machines free at the same time. Splitting sixteen hours across two lines to finish in eight is a real gain. Adding a third and fourth machine shortens the wall-clock further, as long as they can all be free together.
The all-or-nothing rule is the ceiling on that gain. Machines that rarely share a free window will spend more time waiting for a common opening than they save by running in parallel, so a large parallel group across busy machines can finish later than a single dedicated machine. Two conditions decide whether it helps: the machines need overlapping calendars so a common shift exists, and they need genuine open capacity at the same time. Where those hold, parallel throughput is a strong lever. Where machines are chronically busy on their own work, forcing them into a parallel group just makes the job wait. Match the model to the reality of your capacity, not to the machine count on paper.
How EDGEBIC Uses It
Independent parallel appears wherever a routing step lists capacity-checked secondary machines. The engine runs the simultaneous-slot search, reports whether every gate passed, and splits the allocation across the machines when a common window is found. On the Gantt, you see the same job block on several machines over the same time span, each consuming its own capacity.
Because each machine's capacity is genuinely tracked, the plan stays honest: you cannot overbook a parallel machine, and the reporting shows real utilization on each. When you reschedule, the group re-solves against current capacity and completed work is never moved.
Independent parallel is one of two parallel models. The manufacturing glossary covers the related terms. When machines must instead run in exact lockstep as one physical operation, read what is dependent parallel processing, and for the complete engine behavior see the parallel work centers guide.
Expert Q&A: Deep Dive
Q: We have two identical assembly lines but a sixteen-hour job only ever runs on one of them. Can we cut the time in half?
A: Yes, that is exactly what independent parallel is for. Mark the assembly step as independent parallel and list the second line as a capacity-checked alternative. The engine then looks for a window where both lines are free at the same time, splits the sixteen hours into eight on each, and runs them together, finishing the job in one shift instead of two. The two lines each consume their own capacity, so the plan stays honest and you cannot accidentally overbook either one. The only requirement is that both lines can actually be free at the same moment, so the gain depends on having open capacity on both, not just on marking the step parallel.
Q: One of our two parallel machines went down for maintenance and the whole job slipped two days instead of just running on the good machine. Is that a bug?
A: No, that is the all-or-nothing rule working as designed. Independent parallel means the operation is split across machines that run at the same time, so a parallel operation that runs on only one machine is not parallel at all. When one machine is down, the engine will not start the other alone, because that would leave the operation half-planned and the split invalid. Instead it searches forward for the next window where every machine in the group is free together and starts them there. If the only common opening is two days out, the job waits two days. If you would rather the work run on whatever machine is available even when it cannot run in parallel, model the machines as true alternates instead, where one machine replaces the other rather than joining it.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
The EDGEBIC Scheduling Glossary Index
A themed index to the EDGEBIC glossary: scheduling engine, capacity and calendars, materials and planning, shop floor, reporting, quoting, and data import terms, defined in plain language.
What Is the Critical Chain in Manufacturing Scheduling?
The critical chain is the longest dependent path through a plan once shared machine contention is counted, not just step precedence. Here is how it differs from the critical path.
What Does Finite Capacity Mean in EDGEBIC?
Finite capacity means the scheduler refuses to book more hours on a machine than that machine actually has. See exactly how EDGEBIC enforces it, day by day and shift by shift.