A punch adjustment is a supervisor-authored correction to a production punch, carrying the old value, the new value, a reason, and the adjuster's name. When an operator's kiosk record is wrong, a forgotten clock-out, a mistyped count, a punch left open, a supervisor does not quietly overwrite it. They record an adjustment that keeps the original value beside the corrected one and stamps who made the change and why. The result is a shop-floor record that is both accurate and traceable, so the number can be trusted and the correction can be seen.
This entry defines the punch adjustment and shows how it behaves inside EDGEBIC by User Solutions. For the wider index of planning terms, see the manufacturing glossary, and for the record it corrects, read what is a punch type in shop floor tracking.
How it works
A production punch is the raw capture of an operator's state on a machine: a segment of time from when they started to when they ended, tagged with what they were doing. Most of the time these punches are correct, because the operator taps start and end at the kiosk as the work happens. But human capture goes wrong in predictable ways. Someone walks off at the end of a shift without ending a run, so an automatic close leaves the punch running to midnight. Someone fat-fingers a piece count. Someone starts a punch on the wrong job.
A punch adjustment is the sanctioned way to fix these without destroying the original. It records four things: the value as it was, the value it should be, a reason for the change, and the name of the supervisor who authored it. The corrected value becomes the effective record for reporting, but the original stays attached, so a later reviewer can see that a correction happened rather than a suspiciously clean number.
That preservation is the whole point. A shop floor lives or dies on the trust people place in its numbers. If corrections were silent overwrites, no one could tell an accurate capture from a quietly rewritten one. By keeping the before, the after, the why, and the who, an adjustment turns a fix into evidence rather than a cover-up.
A concrete example
Joe runs a press on the afternoon shift. At the end of the day he heads home but forgets to tap "end" on his punch. The kiosk, seeing an open punch at the end of the shift, auto-closes it at midnight. The record now says Joe ran the press for eight extra hours he never worked.
The next morning the shift lead notices the runaway punch. Rather than deleting it and typing a fresh one, the lead opens a punch adjustment: original end time midnight, corrected end time five in the afternoon, reason "operator forgot to clock out," authored by the shift lead. The hours are now right, payroll and job costing get the real number, and the record permanently shows that this punch was corrected, from what, to what, and by whom. Anyone auditing the day sees the full story, not a laundered figure.
How EDGEBIC uses it
In EDGEBIC, operators capture their own work as production punches at the shop-floor kiosk, and supervisors correct those punches with punch adjustments when something needs fixing. An adjustment records the old value, the new value, a reason, and the supervisor's name, so the corrected actuals are accurate while the correction itself remains fully traceable.
This keeps a clean line between two different activities. Raw capture is an operator action, done live at the kiosk as the work runs. Correction is a supervisor action, done after the fact, and it always carries accountability because the adjuster's name is part of the record. Nobody has to guess whether a number is original or amended, because the adjustment carries both.
Correcting a punch is about getting the shop-floor record right, which is a separate concern from replanning the schedule. The plan and the actual dates that drive rescheduling flow through their own path, where completed work is preserved and only remaining work is replanned. A punch adjustment simply makes sure the captured hours and pieces are honest before any of that downstream reporting happens. To see the raw record it corrects, read what is a punch type in shop floor tracking, and for who recorded a punch in the first place, read what is a punch source in shop floor tracking. For the terminal where operators capture punches, see what is a shop floor kiosk.
Expert Q&A: Deep Dive
Q: An operator forgot to clock out and the system shows the machine running all night. How do we fix it without losing the record?
A: A supervisor makes a punch adjustment on that punch, changing the end time from the auto-recorded midnight to the actual finish time, and entering a reason such as missed clock-out. The adjustment stores the original midnight value, the corrected time, the reason, and the supervisor's name. So the hours are put right for reporting and payroll purposes, but the fact that the punch was corrected, and by whom, is preserved. You get the accurate number without erasing the evidence that it was fixed.
Q: Does adjusting a punch change what the scheduler already planned?
A: A punch adjustment corrects the recorded shop-floor time; it is about getting the actuals right, not about replanning. The planned schedule and the actual dates that drive rescheduling are separate concerns from the raw punch record, so correcting a missed clock-out sets the actual capture straight without silently rewriting the plan. If the corrected actuals need to flow into the schedule, that happens through the normal actuals and reschedule path, where completed work is preserved and only remaining work is replanned.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
The EDGEBIC Scheduling Glossary Index
A themed index to the EDGEBIC glossary: scheduling engine, capacity and calendars, materials and planning, shop floor, reporting, quoting, and data import terms, defined in plain language.
What Is the Critical Chain in Manufacturing Scheduling?
The critical chain is the longest dependent path through a plan once shared machine contention is counted, not just step precedence. Here is how it differs from the critical path.
What Does Finite Capacity Mean in EDGEBIC?
Finite capacity means the scheduler refuses to book more hours on a machine than that machine actually has. See exactly how EDGEBIC enforces it, day by day and shift by shift.