Worked Examples

Running a Weekend on a Capacity Override to Hit a Due Date in EDGEBIC

User Solutions TeamUser Solutions Team
|
8 min read

Running a weekend on a capacity override in EDGEBIC by User Solutions means opening a single closed day for one work center so the engine can place work there and hit a due date, without touching the recurring shift calendar. This walkthrough recovers a job that would finish late over a closed weekend by adding one Saturday override, and watches the engine create a synthetic override-day slot to hold the work. It is one of the worked examples we publish so the mechanics are visible in numbers.

An override is the lighter touch next to a permanent second shift, covered in adding a second shift to break a bottleneck. For the calendar model underneath both, shifts and calendars explained is the companion.

The Cast: One Assembly Job, One Closed Weekend

Brightwater Assembly has a job that the calendar is about to make late:

ItemValue
Work centerASSY-1, 1 instance, Day Shift Mon to Fri 08:00 to 16:00 (8 h/day)
WeekendSaturday and Sunday closed, no shift
Job20 hours of assembly, earliest start Friday 08:00
Due dateMonday, end of day

Step 1: See the Late Result

Run Drive Schedule as it stands. ASSY-1 can offer 8 hours Friday, nothing on the closed weekend, then 8 hours Monday and 4 hours Tuesday:

DayAvailableHours placedRemaining
Friday8 h812
Saturdayclosed012
Sundayclosed012
Monday8 h84
Tuesday8 h40

The job finishes Tuesday. It is due Monday. The weekend gap is real calendar time that costs zero machine-hours, and it pushed the finish a day past the due date. The whole shortfall is those two closed days.

Step 2: Open Saturday With an Override

Rather than add a permanent Saturday shift, open just this one Saturday for just this one machine. Add a capacity override of 8 hours for ASSY-1 on this Saturday. You can double-click the capacity cell for ASSY-1 and that date on the Dashboard, or open the capacity chart from the Work Center grid and enter the hours there.

An override is read at top priority. The engine resolves a day's capacity in a fixed order: a per-day override first, then a broader date-range override, then the shift formula. So the 8 hours you entered for Saturday are used verbatim, regardless of the fact that Saturday has no shift in the recurring calendar.

Step 3: Watch the Synthetic Slot Appear

Reschedule. At the start of the run, the engine rebuilds its capacity slots. Because the override covers a day that has no configured shift, it creates a synthetic override-day slot for Saturday: a slot with no regular shift attached, carrying the 8 override hours. This synthetic slot is considered after the regular-shift candidates, so the engine reaches for it exactly when it needs the extra day.

Now the job flows:

DaySlotHours placedRemaining
FridayDay Shift812
SaturdayOverride Day (synthetic)84
Sundayclosed04
MondayDay Shift40

The job runs 8 hours Friday, 8 hours on the Saturday override, and its last 4 hours Monday morning, finishing Monday at noon. On time. One override for one date recovered the due date, and the recurring calendar is untouched: next weekend ASSY-1 is closed again unless you add another override.

Step 4: The Same Dial, Three Directions

The override is not only for opening closed days. Because it wins over the shift formula, it sets a day's capacity in any direction:

  • Open a closed day. The weekend case above: a day with no shift gets a synthetic slot and real hours.
  • Raise a working day. Enter more than the normal shift hours for a crunch day, and the engine offers the higher number for that date. An override above the normal clock window still contributes its full hours.
  • Lower a working day. Enter fewer hours for a partial closure, a training morning, or planned maintenance, and the engine offers only that.

All three are one-time, per work center, per date, and none of them edit the recurring calendar. For a broad, planned capacity change across a range of dates you would use a date-range override; for a single day, the per-day override is the precise tool.

What This Walkthrough Proves

  1. An override sets one day's capacity exactly. It is read ahead of both the date-range override and the shift formula.
  2. A closed day can be opened for one run. The engine creates a synthetic override-day slot for a day with no shift and places work there.
  3. The synthetic slot is used when needed. It is considered after regular-shift candidates, so the engine reaches for it to hit a due date.
  4. The recurring calendar is untouched. The override is a one-time, per-date change, not a new shift.
  5. The dial goes both ways. The same override opens a closed day, raises a busy one, or lowers a partial-closure day.

If a capacity override does not seem to take effect on the next run, the two usual causes are that it is on the wrong work center or date, or that the work never reaches that day because earlier shifts absorbed it. Both, along with the subtler timing cases, are covered in a daily capacity override was ignored.

From One Override to a Responsive Plant

A capacity override is the surgical capacity move: one day, one machine, no permanent change. It sits alongside the blunter levers of a second shift or a new work center. When the shortfall is a real weekly pattern rather than a one-off, adding a second shift to break a bottleneck is the durable answer, and when a job is late because of a disruption rather than a closed calendar, the machine breakdown reschedule walkthrough shows the recovery path.

User Solutions has helped manufacturers flex capacity to hit dates since 1991, work that took GE Railcar from 30 percent to 90 percent on-time. Contact us for a demo and bring one at-risk due date: we will find the day worth opening with you.

Use a capacity override. You can double-click the capacity cell for a work center and date on the Dashboard, or open the capacity chart from the Work Center grid, and enter the hours for that specific date. The override is read at top priority, ahead of any date-range override and ahead of the shift formula, so it sets that day's capacity exactly. It is a one-time change for one date and does not touch the recurring shift calendar.

When a capacity override covers a day that has no configured shift, such as a Saturday, the engine creates a synthetic override-day slot for it. The slot carries the override hours and is picked up after all regular-shift candidates for other days are considered, so the engine will place work there to hit a due date. The weekend day contributes real machine-hours for that run only, without adding a permanent shift to the calendar.

A per-day override wins first, then a date-range override, then the shift formula. So if you set a specific day's capacity with the daily override dialog, that number is used verbatim regardless of the shift formula or any broader date-range override. This lets you raise a single day above its normal capacity, lower it for a partial closure, or open a day that has no shift at all, all without editing the recurring calendar.

Expert Q&A: Deep Dive

Q: A 20-hour assembly job is going to slip to Tuesday because the plant is closed this weekend, but it is due Monday. Can I just open Saturday for that one machine?

A: Yes. Add a capacity override of 8 hours for that work center on Saturday. On the reschedule, the engine creates a synthetic override-day slot for Saturday and places 8 of the job's hours there. In this walkthrough the job runs 8 hours Friday, 8 hours on the Saturday override, and its last 4 hours Monday morning, finishing Monday at noon instead of Tuesday. One override for one date recovered the due date without a permanent second shift or a calendar change.

Q: If I add a weekend override and my next planning run does not use it, what should I check?

A: First confirm the override is on the exact work center and date the job needs, since it is read per work center per date. Then confirm the job actually has hours left to place on that day; if earlier shifts already absorbed the work, the override slot simply goes unused. An override that raises a day's capacity above its normal clock window still contributes its full hours, but the work must reach that day for the slot to matter. The known failure modes and their fixes are documented separately.

Frequently Asked Questions

Ready to Transform Your Production Scheduling?

User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.