The prior-operations warning in EDGEBIC is a data-integrity safety gate, and it has no off switch by design: you stop it firing by logging actuals on earlier operations first, or by accepting the one-click auto-backfill it offers. The adjacent drag warnings do have configuration toggles, but the missing-prior-actuals prompt in EDGEBIC by User Solutions is deliberately not one of them, because turning it off would let gaps into a job's history that the reschedule engine cannot reason about.
This post covers that one prompt and its neighbors. For what the safety prompts are protecting and why, read EDGEBIC Gantt safety prompts and prior operations; the full task library is at the EDGEBIC how-to hub.
Before You Start
- You have hit the Batch Scheduling prompt that reads "Warning! No actual dates logged to prior workcenters!" when saving a change on the Gantt.
- You understand the prompt fires when a later operation gets an actual while its earlier operations in the same job have none.
- You can reach the scheduler configuration if you want to adjust the related, toggleable warnings.
The Steps
You cannot switch the missing-priors prompt off, so the task is really "stop it appearing." Two paths do that, and two related warnings can be disabled outright.
- Log front to back. Record actuals on the earliest operation first and work forward. By the time you save a later operation, its priors already carry actuals and the prompt never appears.
- Or accept the auto-backfill. When the prompt appears, click OK. EDGEBIC fills the earlier operations with their planned dates as actuals, tagged so a report can tell auto-filled values from hand-logged ones. Click Cancel instead if you would rather go and log them properly.
- To silence the target-start warning, enable Disable Target Start Date Check in the scheduler configuration. This stops the status-bar warning about dragging a bar before its target start.
- To silence the out-of-sequence warning, untick Scheduler Update Warning on the configuration's General tab. This stops the post-save prompt about jobs that may have fallen out of order.
What Changes When You Save
| Setting or action | Effect |
|---|---|
| Log priors first | The missing-priors prompt does not fire; nothing to accept or cancel. |
| Accept the auto-backfill (OK) | Earlier operations get planned dates as actuals, tagged as auto-filled; the save completes. |
| Disable Target Start Date Check | The drag-before-target-start warning stops appearing; the engine still respects the date on the next run. |
| Untick Scheduler Update Warning | The post-save out-of-sequence prompt stops appearing. |
| The missing-priors prompt itself | Always on. There is no toggle for it. |
How to Check It Worked
Save a change on a downstream operation whose priors you have just logged. The prompt should not appear. Then drag a bar before its target start with Disable Target Start Date Check enabled; the status-bar warning should stay silent. If the missing-priors prompt still appears after you thought you logged the priors, one earlier operation is still without actuals; the prompt lists exactly which work centers are missing.
Common Mistakes
Treating the missing-priors prompt as a bug to suppress. It is a guard, not a nag. Logging front to back removes it cleanly; there is no supported way to turn it off, and that is intentional.
Confusing the three warnings. The missing-priors prompt, the target-start-date check, and the out-of-sequence warning are three separate things. Only the last two have configuration switches. Turning off one does not affect the others.
Disabling the target-start check to fix accidental early drags. The warning exists to catch exactly those accidents. Turn it off only if your planners pull operations earlier than their target start knowingly and routinely; otherwise leave it on.
Forgetting the auto-backfilled tag. When you accept the auto-fill, those actuals are marked as system-filled. If you later reconcile actual hours, treat the tagged values as estimates from the plan, not as floor-reported truth.
What to Do Next
The prompt is really about actuals hygiene, so the durable fix is a clean logging habit: how to backfill actuals for earlier steps in EDGEBIC walks through doing it deliberately rather than by prompt. For the wider set of drag behaviors and switches on this screen, drag and drop rescheduling in EDGEBIC is the overview, and the EDGEBIC product page shows how the Gantt fits the whole scheduler.
Expert Q&A: Deep Dive
Q: I log actuals from the last operation backward and the prompt fires every single time. How do I make my workflow smooth?
A: Reverse the order you log in. The prompt fires because you are stamping an actual on a downstream operation while its upstream operations still have none, so log front to back, earliest operation first, and by the time you reach a later step its priors already carry actuals and the prompt never appears. If you genuinely do not track the early operations and only ever confirm the last one, click OK when the prompt appears and accept the auto-backfill; it fills the priors with their planned dates, tagged System auto-filled so a report can tell them apart from hand-logged values. Either path is faster than fighting a warning that has no off switch.
Q: My planners keep getting a warning when they drag a bar before its target start. Can I stop that one so they stop asking me?
A: Yes, that specific warning is configurable, unlike the prior-actuals prompt. In the scheduler configuration, enable Disable Target Start Date Check and the status-bar warning about dragging before a target start date stops appearing. Be deliberate about it: the engine still respects the target start date on the next scheduling run, so all you are turning off is the visual heads-up, not the underlying rule. If your planners routinely and knowingly pull operations earlier than their target start, silencing the warning is reasonable; if they do it by accident, leave it on so the warning keeps catching the mistake.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.