How to Show Setup and Queue Time on the Gantt in EDGEBIC
To show setup and queue time on the EDGEBIC Gantt, open the Schedule View Configuration tab, go to the Manufacturing tab, and use the Setup and Queue Time card: turn on Show Setup Time and Show Queue Time, optionally Show Teardown Time and Show Move Time, then click Save and Apply Now Configuration. In EDGEBIC by User Solutions this draws setup, queue, and transport time as their own segments on each bar so the board reads honestly, and it is display only: the times come from your routing and the card changes only how they are shown.
This post covers one display card. For the wider map of what is presentation versus what is policy, see the settings that change how your schedule looks in EDGEBIC; the full task library is at the EDGEBIC how-to hub.
Before You Start
- You can reach the Schedule area and its Schedule View sub-tab.
- Your routings actually carry setup or queue time, or there is nothing new to draw.
- You understand these are display settings, saved per station, that never change the plan.
The Steps
- Open the Configuration tab. In the Schedule area, open Schedule View, then the Configuration tab beside the scheduler.
- Go to the Manufacturing tab. Inside Configuration, select the Manufacturing tab.
- Find the Setup and Queue Time card. Locate the card labeled Setup and Queue Time.
- Turn on the segments you want. Tick Show Setup Time to draw setup as its own segment at the start of the bar, and Show Queue Time to draw the queue buffer as a zone before the operation. Both are on by default.
- Add transport segments (optional). Tick Show Teardown Time and Show Move Time if you want those zones drawn. Both are off by default.
- Simplify if needed. Tick Combine Setup with Runtime to merge setup into the run segment for a cleaner bar.
- Apply. Click Save and Apply Now Configuration at the bottom. Reset to Defaults returns the whole tab to factory settings.
What Changes When You Save
| Surface | Effect |
|---|---|
| Show Setup Time | Setup renders as its own segment at the start of each bar. |
| Show Queue Time | The queue buffer renders as a zone before the operation. |
| Show Teardown / Show Move Time | Draw those zones after or between operations when on. |
| Combine Setup with Runtime | Folds setup into the run segment for a single cleaner block. |
| The plan and the data | Nothing. The times come from routing and work-center data; only the display changes. |
How to Check It Worked
After applying, open a job whose routing has setup or queue time and look at its bar. With Show Setup Time on, the changeover should appear as a distinct segment at the start; with Show Queue Time on, the buffer should sit as a zone before the operation. Turn a segment off and apply again to confirm it disappears while the operation stays where it was. Because these are display settings, the bar's overall position never moves.
Common Mistakes
Expecting new time to appear. These settings draw times that already exist in your routing. If a bar shows no setup segment, the routing may carry no setup time, not a display fault.
Cluttering every bar with every segment. Teardown and move segments are off by default for a reason. Turn on only what the reader of the board needs.
Confusing the two setup controls. Show Setup Time draws setup as its own segment; Combine Setup with Runtime hides it inside the run. Pick one intent, not both.
Assuming everyone sees your bars. Display configuration is per station. Export your configuration and have colleagues import it if you want a shared look.
What to Do Next
Bar segments are one of several display choices; labels and layouts are the others. The settings that change how your schedule looks in EDGEBIC draws the full line between display and policy, and how to rename on-screen labels in EDGEBIC covers renaming captions to your vocabulary. To keep a tuned board portable, how to restore a default grid layout in EDGEBIC covers the grid side, and the EDGEBIC product page shows where the Gantt lives in the platform.
Expert Q&A: Deep Dive
Q: Our paint booth has long color changeovers and supervisors keep asking why a bar starts before the operation seems to. Can I make the changeover visible?
A: Yes. Turn on Show Setup Time on the Setup and Queue Time card, found on the Configuration tab under the Manufacturing tab. Setup then renders as its own segment at the start of each bar, so the changeover is visible rather than hidden inside the run, and a supervisor can see that the early part of the bar is preparation, not production. If a queue buffer sits before the operation too, turn on Show Queue Time to draw that as a zone before the bar. Click Save and Apply Now Configuration. Because these are display settings, the plan does not change; the board just reads honestly, which is what your supervisors are actually asking for.
Q: The bars are getting cluttered with segments and I only care about the operation's overall span. How do I simplify them?
A: Trim the segments you do not need on the Setup and Queue Time card. Leave Show Teardown Time and Show Move Time off, which are off by default, so the bar does not carry those zones. If setup is still adding noise, turn on Combine Setup with Runtime, which merges setup into the run segment for a single cleaner block, or turn Show Setup Time off entirely. Then Save and Apply Now Configuration. These choices are display only and per station, so you can keep a lean board while a colleague who cares about changeovers keeps the segments on, and neither of you changes the plan.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.