How to Set Up Work Centers in EDGEBIC: A Field-by-Field Guide

User Solutions TeamUser Solutions Team
|
9 min read

To set up a work center in EDGEBIC you need three things in place before anything else: a shift that defines working hours, the real machine count, and a decision about whether this resource follows the plant calendar or its own. Everything else on the configuration dialog refines the plan. Those three decide whether it exists at all.

EDGEBIC by User Solutions puts work center creation behind one dialog with a small number of fields, most of which have sensible defaults. This guide walks through each field, says what it changes, and flags the two places where a wrong entry is silent rather than loud. If you want the concepts behind the settings first, read work centers explained.

Before You Start

PrerequisiteWhy it matters
At least one shift existsA work center with no working hours has zero capacity and never receives a job
You know the real machine count per stationInstances multiply capacity directly, so a guess here scales through every date
You know the real working patternThe scheduler believes the calendar literally
Import file access for the two flagsIs Bottleneck and One Per Day are set through the work center import, not the edit dialog

Shifts come first. Build the plant calendar before the machines, as described in how to set up shifts, holidays, and downtime.

Step 1: Open the Work Center Screen

Open the Workcenter tab from the main navigation. The Work Center Management page lists everything you have, with columns for the identifier, name, unit of measure, capacity type, instance count, shift calendar badge, One Per Day, Continuous-Process, and an actions column.

The actions column on each row carries four buttons worth knowing now:

  • Edit (pencil): reopens the configuration dialog.
  • Per-day capacity (chart): the override dialog covered in step 5.
  • Setup matrix (gear): sequence-dependent changeover times for this machine.
  • Remove (trash): blocked if anything still references the work center.

Step 2: Add the Work Center

Click Add Work Center. The Work Center Configuration dialog opens on the Basic Information tab.

FieldRequiredWhat it does
WC IdYesThe stable identifier used by routings, schedules, and reports. Auto-generated unless you override it
NameNoDisplay name. Auto-generated unless you override it
DescriptionNoFree-form note, for example 3-axis vertical mill, 40-taper
No.InstancesNo (default 1)How many parallel identical machines this work center has. Multiplies shift capacity
Setup Time (hrs)NoDefault changeover time in hours, inherited by new routing steps here
Use Global ShiftsNo (default on)On means inherit the plant-wide shifts. Off gives this work center a private calendar
Is AvailableNo (default on)Unavailable work centers are skipped by the scheduler entirely
Effective DateNoThe scheduler treats the work center as unavailable before this date. Use it for machines not yet commissioned
Cost per HourNoThe per-hour cost charged to jobs here. Read by quote simulation and cost rollup; new routing steps inherit it
Back / Fore / Border ColorNoGantt bar colors for this work center
Continuous-ProcessNo (default off)Selects the lot-streaming model. Check only for non-discrete output (chemicals, paint lines, food, pharma)

Two entries deserve a pause.

No.Instances is only for machines that are genuinely identical: same speed, same shifts, same tooling. If they differ, create separate work centers and pool them in a work center group instead. Keep the count a whole number; fractional values are accepted for a half-capacity unit, but whole numbers are the norm.

Cost per Hour feeds margin math. A work center saved at zero will quote a job that costs nothing to make.

Click Save. With Use Global Shifts checked, the work center immediately works every global shift and needs no further calendar setup.

Step 3: Confirm What the Grid Says

Read the new row before moving on. Two columns are the fast sanity check:

  • Instances should match the machines on the floor.
  • Shift Calendar should read a green Global badge for anything that follows the plant pattern.

If capacity looks half or double what you expect later, these two columns are where the answer usually is.

Step 4: Give One Machine Its Own Calendar (Only if It Needs One)

Most work centers should stay Global. Override the calendar when a resource genuinely runs a different pattern: a mill staffed only on nights, a cell that works Monday through Thursday, a subcontracted resource available on fixed days.

  1. Click Edit on the work center row.
  2. Select the Associated Shifts tab.
  3. Untick Use Global Shifts. The shift management buttons become editable.
  4. Build the calendar:
    • Add Existing Shift opens a picker; tick shifts and click Add Selected, which copies the pattern locally as a starting point.
    • Create New Shift defines a shift that belongs to this work center alone.
    • On each shift card you can rename it, toggle weekdays, and set start and end times per day.
    • Remove Selected Shift detaches one.
  5. Click Save. The grid now shows the amber Custom badge.

The badge is a warning as much as a label. A Custom work center no longer follows global shift edits, and the tooltip says so plainly. When the plant pattern changes, visit your exceptions or re-tick Use Global Shifts to rejoin the plant calendar.

Here is what the change buys. A 16-hour milling operation on a day-shift-only mill runs Monday 08:00 to 16:00 and Tuesday 08:00 to 16:00, finishing Tuesday afternoon. Move that mill to a 16:00 to 00:00 night shift and the same operation finishes at the same time, but the plant now has 16 hours a day of milling capacity across the two mills instead of 8. Day jobs stop queueing behind night work.

Step 5: Override Capacity for Specific Days

Use a per-day override for one-off realities the calendar should not absorb: approved Saturday overtime, a half-day PM window, a temporarily de-rated machine.

  1. Click the per-day capacity button on the work center row. You can also double-click a Total Capacity cell in Schedule > Resource Calendar.
  2. Pick the shift and adjust the date range.
  3. The dialog shows a stacked bar per day (loaded, free, over capacity) plus a summary card.
  4. In the grid below, type the new value in the Capacity (h) column for the target day and add a Reason.
  5. The change saves as you edit. The Overridden column ticks.
  6. To undo it, click Reset on the row.
ColumnEditableMeaning
DayNoThe calendar date
Shift default (h)NoWhat the formula would give
Capacity (h)YesThe effective hours for that day, used as-is
Loaded (h)NoHours already committed by the current schedule
OverriddenNoTicked when the day carries an override
ReasonYesAudit note stored with the override

The one rule that catches people: enter the total hours for the day, not per-machine hours. On a three-instance work center, "each machine gets 4 hours" is a Capacity (h) of 12. The engine does not multiply the override by the instance count.

Step 6: Set the Two Flags Through Import

Is Bottleneck and One Per Day are not on the edit dialog in the current release. They are loaded through the work center import (the toolbar import button), using the Is_Bottleneck and One_Per_Day_Flag columns. A truthy value (1, true, yes) switches the flag on, and re-importing updates existing work centers.

That import path is the same flexible Excel and CSV mask used to bring work centers in from an ERP export in bulk, which is how most implementations create the first thirty work centers rather than typing them. See EDGEBIC ERP integration.

Step 7: Take a Work Center Out of Service Correctly

Machines leave the floor, and how you record that matters more than it looks.

For a machine that is gone permanently: untick Is Available and save. The scheduler skips it entirely on the next run, jobs routed through it move to a configured alternative or slide, and every past schedule and report still resolves the name.

For a machine not yet commissioned: set an Effective Date. The work center exists, routings can reference it now, and capacity appears on the date the machine does.

For a bounded outage: use a per-day or date-range capacity override across the affected dates instead. The override carries a reason, expires by itself, and leaves the instance count and availability describing the plant as it really is. Dropping an instance count for a three-week rebuild works too, but it removes capacity from every date with no record of why, and it depends on someone remembering to restore it.

For a single machine inside a multi-instance work center: mark that instance unavailable. The engine skips it during selection and the other machines carry on normally.

Deletion is the last resort and it is guarded. If the work center appears on any active routing step, alternative or parallel configuration, schedule, or capacity override, the delete is blocked until those references are removed or reassigned. That guard prevents orphaned routings, which break scheduling for every product that used the machine and surface as an error nowhere near the cause.

What Happens After You Save

ChangeEffect on the plan
New work centerNothing scheduled until a routing uses it and Drive Schedule runs
No.Instances changedCapacity multiplies or shrinks at the next scheduling run; existing bars do not move by themselves
Calendar toggled or editedNew calendar honored at the next run
Is Available off, or a future Effective DateScheduler skips the work center entirely; jobs re-route to alternates if configured, otherwise slide
Per-day capacity overrideSaved instantly, honored by the very next run, and it beats the shift formula
Cost per Hour changedNew quotes use the new rate; existing routing steps keep their inherited value until edited
DeleteBlocked while any active routing, schedule, or override references the work center

The single most common surprise is the first row of that table restated: saving master data never reschedules. Run Drive Schedule and review the result before you communicate dates.

Next

Configure the numbers, then understand what the engine does with them: how EDGEBIC calculates work center capacity walks the arithmetic day by day. Before you go live, read the configuration mistakes that cost the most, and if a machine goes quiet, the zero-capacity checklist finds it in five minutes.

Expert Q&A: Deep Dive

Q: I set up eight work centers this morning and nothing schedules on two of them. The other six are fine. Where do I look first?

A: Check whether any routing step actually points at those two. A work center with perfect configuration and no routing reference is simply idle, and this is the most common cause when most of the plant is working. If routings do target them, check the Shift Calendar column next: a work center left with Use Global Shifts on shows a green Global badge and inherits the plant hours, while one switched to Custom with an empty shift list has no working windows at all. Instance count of zero is the third candidate. Those three cover nearly every new work center case, and the full checklist is in our zero-capacity post.

Q: Our three-instance work center has a PM window next Tuesday where each machine is down for four hours. What do I type in the per-day override?

A: Enter the total for the day across all machines, not the per-machine figure. Three instances on an 8-hour shift normally offer 24 hours; losing 4 hours per machine leaves 4 hours each, so the override is 12, not 4. The engine uses the number verbatim and does not multiply it by the instance count. Add a reason (PM window, all three spindles) so the audit trail explains the plan later, and click Reset on that row when the machines are back to full hours.

Frequently Asked Questions

Ready to Transform Your Production Scheduling?

User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team

User Solutions Team

Manufacturing Software Experts

User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.

Let's Solve Your Challenges Together