- Home
- Blog
- EDGEBIC How-To
- How to Set Pieces Required on a Routing Step in ED…
To set pieces required on a routing step in EDGEBIC by User Solutions, set the step's Unit Type to pieces (or both) and enter the piece requirement, with the step running on a pieces-based work center. The Unit Type column on the step decides whether the requirement is measured in hours, pieces, or both. When it is pieces, the scheduler reads the step's piece count and converts it to time using the work center's pieces-per-hour rate, so the machine must be configured as pieces-based first. This suits output-driven operations such as molding, stamping, or filling, where the floor thinks in parts per hour rather than hours per part.
This recipe covers one specific task. For entering time directly, see how to change the hours on a routing step. For how the machine rate turns into capacity, read how EDGEBIC calculates work center capacity and EDGEBIC work centers explained.
Before You Start
- A pieces-based work center exists for this operation, with a non-zero pieces-per-hour rate. Without the rate, a pieces-based step cannot be converted to time.
- The routing open, with the step you want to schedule by piece count identified.
- The piece requirement for the step, expressed the way the machine measures output.
Step by Step
- Confirm the work center's capacity type is pieces (or both). It appears as a read-only column on the work center grid and is loaded through the work center import rather than typed on the edit dialog.
- Open the BOR tab and select the routing.
- Select the step that should schedule by pieces.
- Set the step's Unit Type to pieces (or both if either pieces or an hours ceiling could be the binding constraint).
- Enter the piece requirement for the step.
- Click Update Standard BOR to save.
- Run Generate Schedule so the step is scheduled by piece count.
What Changes When You Save
On the next scheduling run, the step no longer consumes hours directly. Instead the scheduler reads its piece requirement and converts it to time using the step's own rate, the per-piece time you entered on it. A rate of 60 parts per hour, which is 0.0167 hours per piece, turns a 300-piece requirement into 5 hours of work, placed across the machine's shifts like any other operation. With Unit Type set to both, the scheduler honors whichever of the piece count or the hours ceiling is limiting. The rest of the routing composes normally: setup, queue, and downstream links behave the same as for an hours-based step.
How to Check It Worked
Open the Job View after scheduling and confirm the step's duration matches the piece count divided by the effective rate. For 300 pieces at 60 parts per hour, expect about 5 hours before setup. If the step schedules with an impossibly long or unbounded duration, the work center's pieces-per-hour rate is likely zero: set a non-zero rate and reschedule. If the duration is off by a consistent proportion, check the machine's efficiency factor.
Common Mistakes
- A zero piece rate on the machine. A pieces-based work center with no pieces-per-hour rate cannot convert pieces to time and produces an unbounded schedule. Always set a non-zero rate.
- Setting Unit Type to pieces on an hours-based machine. The conversion depends on the work center being pieces-based. Configure the machine first.
- Forgetting the efficiency factor. Effective throughput is the rate times the efficiency factor, so an unexpected factor changes the duration. Confirm it is sensible.
- Reaching for both when pieces is enough. Use both only when a real second constraint exists. For a purely output-driven step, pieces is simpler and clearer.
Related Reading
- How to add setup time to a routing step since setup composes with a pieces-based run the same way.
- How to build a routing step by step for the wider routing workflow.
- EDGEBIC and the EDGEBIC how-to hub for the full recipe index.
Scheduling a step by pieces lets you plan in the units your machine actually reports, so an output-rated press or molder consumes capacity the way the floor measures it, with the piece rate doing the conversion to time behind the scenes.
Expert Q&A: Deep Dive
Q: Our stamping press is rated in parts per hour, not hours per part. How do I route to it?
A: Configure the press as a pieces-based work center with its parts-per-hour rate, then on the routing step set the Unit Type to pieces and enter the piece requirement. The scheduler converts the pieces to time using the press rate, so you plan in the units the press actually reports. If you only knew hours per part, you could instead use the hours converter, but for an output-rated machine the pieces path matches how the floor measures it.
Q: Should I use pieces or both for the Unit Type on a molding step?
A: Use pieces when the operation is purely output-driven and time follows directly from the piece rate. Use both when either the piece count or an hours ceiling could be the binding constraint and you want the scheduler to respect whichever is limiting. For a straightforward molding run on a piece-rated machine, pieces is usually enough; reach for both only when there is a real second constraint to honor.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.