- Home
- Blog
- EDGEBIC How-To
- How to Set a Job Priority in EDGEBIC
To set a job priority in EDGEBIC, type a number into the Priority cell on the Drive Schedule grid or drag the row by its grip handle, then click Save Changes and run the scheduler. Lower numbers schedule first: priority 1 is planned before priority 2. On a loaded plant this single column does more work than any other setting, because EDGEBIC by User Solutions plans one job at a time and each job claims real capacity as it goes. The queue order is the plan.
This is the mechanics of the field. For the strategy behind the numbers, job priority and sequencing strategy goes deeper, and the EDGEBIC how-to hub indexes every task post.
Before You Start
- The jobs you want to reorder exist on the Drive Schedule grid.
- You know which jobs are already running. Recorded work is never moved by a re-run, so reprioritizing a job that is half built only affects its remaining steps.
- You are ready to run the scheduler afterwards, because priority edits do not move bars on their own.
The Steps
Option A: type the number
- Open the Schedule area and select the Drive Schedule tab.
- Click into the Priority cell on the row you want to change.
- Type the new number. Lower means more important.
- Repeat for any other rows.
- Click Save Changes on the filter bar. The button appears only while there are unsaved edits.
Option B: drag the row
- Find the grip handle, the six-dot column at the left edge of the row. Its tooltip reads "Drag to reorder priority".
- Drag the row up or down. An insert indicator shows where it will land.
- Drop it. Every affected priority renumbers automatically to match the new order.
- Click Save Changes.
Then plan
- Tick the jobs whose plans should reflect the new order. Unticked jobs keep their existing schedules and their reserved capacity.
- Run the scheduler and confirm the job counts in the dialog that appears.
What Changes When You Save
| Surface | Effect |
|---|---|
| The order records | The priority numbers are written. |
| The plan | Nothing moves until the next scheduling run for those jobs. |
| The next run's queue | Jobs are sorted by priority, then start date, then due date, and planned in that sequence. |
| Capacity | Each job claims capacity as it is planned, so a job promoted above another takes the slot the other one used to hold. |
| Jobs you did not tick | Untouched. Their bars stay and their reservations are respected. |
The scope rule is the part planners underuse. Ticked rows define what gets re-planned. If you promote one job and tick only that job, everything else keeps its dates, and your promoted job fits into whatever capacity is genuinely free. If you tick everything, the whole plan is rebuilt against the new queue, which is more powerful and more disruptive.
How to Check It Worked
Run the scheduler, then compare the Start Date, Item Start and Job End columns before and after on the two jobs whose relative order you changed. The promoted job should start no later than it did. On a busy work center it should also visibly displace the demoted job.
If nothing moved at all, check the obvious cause first: the constrained work center may have had free capacity for both jobs anyway, in which case priority was never the binding constraint. Then check that you actually clicked Save Changes before running.
Common Mistakes
Navigating away without saving. Inline edits are staged, not auto-saved. If you leave the grid while Save Changes is still showing, the edits are lost and nobody tells you afterwards why the run ignored your reordering.
Using dense numbering. Number in bands: 10, 20, 30. Inserting a rush job between 10 and 20 becomes a single edit instead of renumbering the whole list. The engine only reads the order, so gaps cost nothing.
Expecting priority to move bars by itself. It does not. Priority edits change master data, and the plan reflects the change only after the next run. This catches people who reorder ten rows, glance at an unchanged Gantt, and conclude the feature is broken.
Reprioritizing after the run instead of before it. Setting the queue first and running once is one movement of the bars. Running, disliking the sequence, reordering, and running again moves them twice, and the floor notices.
Leaving deliberate ties. Ties break by start date then due date, which may or may not match your intent. If the order matters, give the jobs different numbers.
What to Do Next
Priority is the first lever when a job needs to jump the queue; how to schedule a rush order walks the whole sequence for a genuine emergency. If a job is landing later than expected even at priority 1, the checklist in how to see why a job is late will find the real constraint. For background on sequencing rules as a discipline, priority rules in the job shop covers the classic approaches, and the EDGEBIC product page covers the platform.
Expert Q&A: Deep Dive
Q: Why do you recommend numbering 10, 20, 30 instead of 1, 2, 3?
A: Because bands leave room to insert. With dense numbering, dropping a rush job between the first and second job forces every row below it to renumber, and a renumbered grid is hard to review and easy to get wrong. With bands, the rush job becomes priority 15 and nothing else moves. The engine does not care about the size of the gaps: it only cares about the order, so 10, 20, 30 sorts exactly like 1, 2, 3 while leaving nine slots between each pair. This becomes valuable the first time three rush jobs arrive in the same week.
Q: Two jobs both sit at priority 2. Which one does the engine plan first?
A: Ties break by start date, then by due date. So a priority 2 job that may start Monday is planned before a priority 2 job that may not start until Wednesday, and if their start dates match, the earlier due date wins. This is usually sensible, but leaving deliberate ties is a bad habit on a busy plant: the job planned first claims the capacity, and the one planned second fits around it. If the order between two jobs actually matters to you, give them different numbers rather than trusting the tie-break to agree with you.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.