How to Schedule Lights-Out Machining With One Operator in EDGEBIC
To schedule lights-out machining with one operator in EDGEBIC by User Solutions, set the routing step's Required Skill and set its Operator attention to 0.0. At 0.0 the step is setup-only: a person sets the machine up, and the run books nobody, so post-setup hours execute on days nobody is rostered, including overnight. One operator can start many machines a day, limited only by the setup hours they can cover. The setup still needs a person, so the step will not start on a day when nobody qualified is around.
This post is the lights-out configuration task. For the wider picture of unattended machining as a shop strategy, see lights-out scheduling for CNC shops.
Before You Start
| Prerequisite | Why |
|---|---|
| The step has a Required Skill | The attention fraction only applies to skill-gated steps |
| At least one qualified operator is rostered | Setup still needs a person, so a start needs staffed hours |
| You know the real setup time on the step | Setup is what the one operator's capacity is spent on |
Step 1: Set the Required Skill
On the routing step, set Required Skill to the certification the setup needs, for example CNC-Setup. Without a skill, the attention fraction has nothing to gate, and the step schedules on machine capacity alone. The skill is what ties the setup to a qualified person.
Step 2: Set Operator Attention to 0.0
Set Operator attention to 0.0. This is the run-phase attention per machine-hour, and 0.0 means the run books nobody. Setup is unaffected: it always books one full person per slice. So the operator is spent on setups, and the machines run themselves afterward.
| Value | Plain meaning |
|---|---|
| 0.0 | Setup-only: the run books nobody, post-setup hours may run unstaffed |
| 0.5 | One person tends two machines during the run |
| 1.0 | Fully attended: one operator-hour per machine-hour |
| 2.0 | Two-person crew per machine-hour |
Step 3: Confirm the Stored Value
Check that the step actually stores 0.0, not just that the picker shows it. The default is 0.0, but a step edited earlier may carry an old 1.0, which would book a full operator for the whole run and defeat the lights-out plan. This is the single most common reason a lights-out cell books more labor than expected.
Step 4: Reschedule
Run Drive Schedule or a reschedule. Now each lights-out job costs the operator only its setup. Several machines can start the same day, the one operator setting each up in turn, and the run hours flow into the unstaffed evening. A job whose setup no longer fits the operator's remaining hours slides to the next day, so the cell fills exactly as far as one person's setup capacity allows.
What Changes When You Set Attention to 0.0
| Surface | Effect |
|---|---|
| The run phase | Books no operator hours; machine runs unattended after setup |
| The setup phase | Still books one full person, so a start needs a qualified operator |
| Capacity of one operator | Spent on setups: they can start many machines per day |
| Overnight and unstaffed days | Post-setup run hours may land there |
The attention fraction is the mechanism that lets one operator start a lights-out cell without the schedule overselling them. The full model, including fractional tending and crews above 1.0, is defined in what attend fraction means in operator scheduling.
How to Check It Worked
After rescheduling, each lights-out job consumes only its setup hours from the operator, not the full run, and several machines start the same day. The run hours appear on days and times nobody is rostered, which is the unattended running. If a job books a full operator for its whole run, the stored attention value is not 0.0. If a job will not start at all, no qualified operator is rostered to perform the setup.
Common Mistakes
- Leaving attention at 1.0 on a lights-out step. The run books a full operator and the cell cannot fill. Set it to 0.0.
- Setting attention 0.0 but forgetting the setup still needs a person. The step will not start on a day nobody qualified is rostered.
- Setting 0.5 to make the schedule fit. That borrows hours from a person who does not have them. Use the honest value: 0.0 for lights-out, 1.0 for attended.
- Not confirming the stored value. A step carrying an old 1.0 quietly defeats the plan. Verify it stores 0.0.
Next Steps
To make sure a qualified operator is available to perform the setups, review how to build a weekly operator roster. To require the setup skill in the first place, see how to require a skill on a routing step.
Every task in this library is indexed on the EDGEBIC how-to hub. To see one machinist start seven mills that run through the night, book a walkthrough of EDGEBIC and bring your lights-out cell.
Expert Q&A: Deep Dive
Q: We set a required skill on our lights-out cell and now the scheduler is booking a full operator for every hour of the run. What did we get wrong?
A: Operator attention is at 1.0, or it still carries an old value, so the run is being treated as fully attended. Set the step's Operator attention to 0.0, which is setup-only: one person sets the machine up, and the run books nobody. The post-setup hours can then execute on days nobody is rostered, including overnight, which is exactly what lights-out means. Check the value actually stored on the step, not just the picker. The default is 0.0, but a step that was edited earlier may carry a 1.0. Set it to 0.0 explicitly, reschedule, and the run hours stop consuming operator capacity. The setup still needs a person, so the step will not start on a day nobody qualified is around, but the run itself is free.
Q: One machinist runs seven mills overnight, each job an hour of setup then nine hours unattended. How does the schedule keep that honest?
A: With attention at 0.0, each job costs the operator only its setup: one hour of the machinist per job, not ten. Seven jobs cost seven of their eight rostered hours, so all seven mills can start the same day, the machinist setting each up in turn. The nine run-hours per machine are unconstrained by people and run into the unstaffed evening. The honesty comes from the setup still counting. An eighth job's setup fits the machinist's last hour, but a ninth job's setup slides to the next day, because there is no operator hour left to set it up. So the cell fills exactly as far as one person's setup capacity allows and no further. That is lights-out scheduling that does not oversell the one person who has to start every machine.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.