How to Run the Optimization Suggestions Report in EDGEBIC

User Solutions TeamUser Solutions Team
|
7 min read

The BOR optimization suggestions report in EDGEBIC by User Solutions lives in the Reports hub: it scans your schedule against seven rules and returns a ranked list of routing and capacity changes that would buy back hours, each with an estimated impact. It is a decision-support scan, not an automatic fix. Every suggestion is yours to apply by hand and verify.

Keep one distinction clear: this report suggests improvements to your routing data, while the optimizer engine actually rearranges the schedule and returns a plan guaranteed never worse than the baseline, with its goal, its search, and its before-and-after numbers set out in the Explain dialog on the proposal. Use the suggestions report to clean up the inputs, then let the optimizer work against the better setup. Where both fit in the report family is in EDGEBIC reports explained. Every task in this library is mapped on the EDGEBIC how-to hub.

Before You Start

  • Jobs are scheduled. The report scans the current schedule for opportunities.
  • Your routings carry their real fields. Suggestions like lot streaming or parallel processing key off whether those fields are configured.
  • You are ready to make changes in the routing editor and re-run the schedule. The report itself changes nothing.

Step 1: Open the Report and Set the Range

Open Reports from the main navigation and click the BOR Optimization Suggestions card. A date range dialog appears with a default window covering the recent past and the near-term forward plan. Set the range you want to scan, then click OK. The report evaluates seven rules across the schedule and builds the results.

Step 2: Read the Ranked Suggestions

The main grid lists suggestions, each with a rule code, the job and operation it concerns, the work center, an estimated impact in hours, the number of affected jobs, a plain-language description of the issue, and a suggested change. Sort by estimated impact hours, highest first, and the single biggest opportunity sits at the top.

The seven rules flag: excessive wait gaps between sequential steps, a lot-streaming opportunity on a large job with no overlap configured, a bottleneck station not flagged as a constraint, one-per-day scheduling leaving instances idle, alternatives configured but never selected, parallel processing that is possible but not set up, and a queue time configured alongside a flow step that creates a known override.

Step 3: Read the Bottleneck Summary

Switch to the bottleneck summary tab for a per-station verdict: constraint, hot, at risk, ok, or idle. This is where a suggestion to flag a station as a bottleneck comes from. A station reading constraint that is not yet flagged is the report telling you to turn on anchor scheduling so the plan protects it.

Step 4: Apply One Change and Verify

Pick the top suggestion and read its suggested change. For a step-gap suggestion, for example, the report offers ranked options such as routing the delayed step to a less-loaded alternative, or enabling lot streaming on the blocking step. Make the change in the routing editor, re-run the schedule, then re-run this report. If the estimated impact on that row drops toward zero, the improvement was real. If it barely moves, the change did not touch the true constraint.

What Changes When You Apply a Suggestion

Nothing changes until you act. When you edit the routing and re-run the schedule, the engine replans with the new configuration: a newly flagged bottleneck triggers anchor scheduling, an enabled transfer batch lets partial quantities move downstream sooner, and a promoted alternative gives the scheduler another station to load. The report then reflects the new reality on its next run.

How to Check It Worked

Because the report makes no changes, verification is the re-run. Apply one change, re-run the schedule, and re-run the report. The suggestion you acted on should shrink or disappear, and the estimated impact should drop. If it does not, the opportunity was theoretical and the constraint lies elsewhere.

Common Mistakes

  • Treating estimated impact as guaranteed. The hours are an estimate the report cannot fully verify. The rerun is the proof, not the estimate.
  • Expecting the report to change the schedule. It is decision support. Every change is applied by you in the routing editor.
  • Confusing it with the optimizer engine. This report improves routing data by hand; the optimizer rearranges the plan. They are separate tools that work well in sequence.
  • Flagging a station as a bottleneck when it is not the real constraint. Over-protecting the wrong station pulls other utilization down. Confirm the constraint on the bottleneck summary first.

Expert Q&A: Deep Dive

Q: The report suggests enabling lot streaming on a big job with an estimated impact of 40 hours. Should I just do it?

A: Do it only after you confirm the estimate holds against your reality, because estimated impact hours are exactly that, an estimate the report cannot fully verify. The suggestion fires because the job is large and has no transfer batch or flow overlap configured, so its downstream steps wait for the whole quantity to finish upstream. Lot streaming lets a partial batch move on, which is where the 40 hours comes from. Make the change in the routing editor, then re-run the schedule and re-run this report: if the estimated impact on that row drops toward zero, the improvement was real. If it barely moves, the downstream station was not the constraint and the hours were theoretical. Verify by rerun, do not trust the estimate alone.

Q: How is this report different from running the optimizer?

A: This report suggests; the optimizer decides. The optimization suggestions report is a decision-support scan that flags routing and capacity opportunities, such as a bottleneck that is not flagged or an alternative station that is never used, and hands you a ranked list to act on by hand in the routing editor. The optimizer is a separate engine that actually rearranges the schedule and returns a plan guaranteed never worse than the baseline. Use the suggestions report to improve the underlying routing data, then let the optimizer work against the cleaner setup. They are complementary: one improves the inputs, the other improves the plan.

Frequently Asked Questions

Ready to Transform Your Production Scheduling?

User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team

User Solutions Team

Manufacturing Software Experts

User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.

Let's Solve Your Challenges Together