Limiting Gantt editing in EDGEBIC by User Solutions is done in the scheduler Configuration under Appointment Permissions: clear checkboxes like Allow Drag, Allow Create, and Allow Delete to turn a station toward view-only, then save and apply. These are display and interaction settings on the machine where you set them, separate from account roles. Here is how to lock a Gantt down.
For the drag behavior itself, see how to change the drag mode on the Gantt, and for account-level control, how to add a user. Every task in this library is mapped on the EDGEBIC how-to hub.
Before You Start
- You know whether you want a machine-level display lock or an account-level restriction. Appointment Permissions are the former; roles are the latter.
- You can open the scheduler Configuration tab. It sits inside the Schedule area's Schedule View.
- You accept these settings are per machine. Each station keeps its own display configuration.
Step 1: Open the Scheduler Configuration
Open the Schedule tab and select the Schedule View sub-tab. Beside the scheduler view is the Configuration tab. Click it. The configuration is organized into General, Views, Appearance, Time and Schedule, and Manufacturing tabs.
Step 2: Find the Appointment Permissions Card
On the General tab, find the Appointment Permissions card. It is a set of checkboxes, each governing one Gantt gesture. Nothing here changes the schedule math: it only decides which interactions the Gantt on this machine allows.
Step 3: Clear the Interactions You Want to Block
Decide how locked-down the station should be, then clear the matching boxes.
| Checkbox | Default | Clear it to |
|---|---|---|
| Allow Create | Off | Keep new appointments from being drawn |
| Allow Edit | On | Stop bars from being opened and changed |
| Allow Delete | Off | Keep bars from being deleted |
| Allow Copy | Off | Keep bars from being copied |
| Allow Drag | On | Stop bars from being moved in time |
| Allow Resize | On | Stop bars from being lengthened or shortened |
| Drag Between Resources | On | Stop bars from moving to another work center row |
| Allow Conflicts | On | Refuse dropping a bar into an occupied slot |
| Multi-Select / Cell Multi-Select | Off / On | Control multi-selection behavior |
For a view-only shop-floor station, clear Allow Drag, Allow Resize, and Drag Between Resources, and clear Allow Edit too if operators do not log actuals from the Gantt.
Step 4: Save and Apply
Click Save and Apply Now Configuration at the bottom. The lock takes effect immediately on this machine. If you want to undo everything, Reset to Defaults returns the factory permissions.
A Note on Allow Conflicts
Turning Allow Conflicts off does not make EDGEBIC capacity-check drags. The model is override and warn: a manual drag is the planner's call, and the next scheduler run resolves feasibility. So do not rely on the conflict checkbox to prevent overbooking. Real capacity control comes from the schedule engine, not this toggle.
Appointment Permissions Versus Roles
These checkboxes lock the Gantt on one machine. To control what a person may do across the whole application regardless of which machine they sign in on, use roles and permissions under Security, covered in how to add a user. The two work together: a role decides whether someone reaches the schedule at all, and Appointment Permissions decide what the Gantt on this station lets them touch.
What Changes When You Save
Only what the Gantt on this machine allows. No schedule data changes, and the settings do not follow the user to another PC. Another planner on a different station keeps their own configuration until you export yours and they import it.
How to Check It Worked
Go back to the Gantt and try the gesture you blocked. If you cleared Allow Drag, a bar should not move when you try to drag it. If you cleared Allow Delete, the delete action should be unavailable. Confirm the interactions you left on still work, so a station meant to log actuals can still open a bar.
Common Mistakes
- Expecting the lock to follow the user. Appointment Permissions are per machine. A person on another PC is unaffected.
- Relying on Allow Conflicts for capacity. It refuses a drop into an occupied slot but does not capacity-check. Feasibility is on the planner and the next run.
- Locking a station that needs to log actuals. Leave Allow Edit on where operators open bars to record hours.
- Confusing this with roles. For account-wide control, use Security roles, not these display checkboxes.
Next Steps
- Move the configuration between machines with how to export your scheduler configuration.
- Set account rights with how to add a user.
- See how the Gantt fits the whole plan on the EDGEBIC product page.
Expert Q&A: Deep Dive
Q: We want the floor to see the schedule but never move a bar. What do I turn off?
A: In the scheduler Configuration, on the General tab, open the Appointment Permissions card and clear Allow Drag, Allow Resize, and Drag Between Resources, then save and apply. Leave Allow Edit on if operators still need to open a bar to log actuals, or clear it too for a pure view. This is a display and interaction setting stored on that machine, so it locks the Gantt on the station where you set it. For controlling what a whole account can do across the app, use roles and permissions instead.
Q: I cleared Allow Conflicts but the schedule still lets a machine look overbooked. Is it broken?
A: No, that is by design. Allow Conflicts governs whether the Gantt lets you drop a bar into an occupied slot, but turning it off does not make EDGEBIC capacity-check your drags. The model is override and warn: a manual drag is the planner's responsibility, and the next scheduler run is what resolves feasibility. If you want a machine to never appear overbooked, the real control is capacity data and a clean scheduler run, not the conflict checkbox.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.