- How to Find Which Products Have No Routing in EDGE…
To find which products have no routing in EDGEBIC by User Solutions, open the Product tab and group or filter the grid on the BOR status column. That column sorts the entire catalog into three buckets: products with a routing, products with none, and products carrying the red legacy multiple-routings warning. One click tells you which products will fail the moment somebody orders them. For the wider list of catalog faults and their symptoms, read product setup mistakes in EDGEBIC.
Before you start
- You can see the Product tab and its grid.
- You understand what a missing routing costs: a product with no operations cannot be scheduled, so any order raised against it fails rather than queuing.
- You have time to act on the result. This audit is worth running right after a bulk import and before any major scheduling run.
- Know the two possible fixes in advance. Either build the routing, or retire the product if it is genuinely obsolete.
Steps
- Open the Product tab from the main navigation.
- Find the BOR column in the grid. It shows one of three values per row.
- Group by that column, or use its filter, to bucket the catalog by routing readiness. The three values are:
| Cell text | Meaning | Action |
|---|---|---|
| Active BOR | Exactly one routing exists. Healthy | None |
| No BOR | No routing yet | Build one, or retire the product |
| Red multiple-routings warning | The product resolves to more than one routing | Consolidate to a single routing |
- Work the No BOR bucket first. For each product, decide whether it needs a routing built or whether it is obsolete.
- Build the routing for products that need one. See how to build a routing step by step.
- Retire the obsolete ones rather than deleting them. See how to deactivate a product without losing history.
- Then work the legacy multiple-routings bucket. Filter the BOR column to that value to find them all at once, open the routing module, keep the correct routing, and remove the others.
There is a compressed version of the same signal in the grid: a checkmark beside the product identifier means it has a routing, and a circle means it does not.
What changes when you fix the gaps
Nothing changes from running the audit itself. It is a read-only view of the catalog.
What changes is what happens on the next scheduling run. Products that had no operations now have them, so orders raised against those products can be placed on work centers instead of failing. Products carrying the ambiguous multiple-routings condition now resolve to one known routing, so what gets scheduled and what gets quoted stop depending on which routing happened to be picked.
Retired products stop appearing in the dropdowns that create new orders, which removes the source of the next round of unschedulable jobs.
How to check it worked
- Re-group the grid on the BOR column. The No BOR bucket should now contain only products you deliberately left without a routing, typically purchased materials that appear inside other routings.
- Confirm the red multiple-routings bucket is empty.
- Open one of the routings you built and confirm it has steps in it. A routing that exists with no steps passes the column's check and still cannot be scheduled.
- Run the anomaly checks and confirm they come back clean. See how to run and read the anomaly report.
- Run the scheduler and confirm no job fails for a missing routing.
Common mistakes
Stopping at the column. A routing with zero steps reads as present and still gives the engine nothing to place. Open the ones you are unsure about.
Treating every no-routing row as a fault. Purchased materials and components that only appear inside other products' routings correctly have none of their own. Filter those out mentally before you start building.
Ignoring the legacy warning because nothing has broken. Multiple routings on one product do not error. They quietly make scheduling and quoting ambiguous, which is worse than a clean failure.
Renaming a work center without updating the routings. Routing steps carry the work center's name alongside its reference. When the name goes stale, the step resolves to no work center, books no capacity, and shows up in the anomaly checks rather than in the routing column.
All the single-task recipes are indexed in the EDGEBIC how-to library. To see how routing readiness feeds a finite capacity plan, visit the EDGEBIC product page.
Expert Q&A: Deep Dive
Q: We imported 300 products from an old system. What is the fastest way to find the ones that will not schedule?
A: Sort or group the product grid by the BOR status column immediately after the import. That gives you three clean buckets and tells you the size of the job before you start: how many products have routings, how many are missing them, and how many carry the legacy multi-routing warning. Work the no-routing bucket first, because those are the ones that will fail as soon as somebody orders them. Then work the legacy bucket, because those fail more quietly by picking an ambiguous routing rather than erroring outright.
Q: A product shows as having a routing but its jobs still will not schedule. Where next?
A: Open the routing and count the steps. A routing record can exist with nothing in it, which satisfies a has-a-routing check while giving the scheduler no operations to place, and the symptom is identical to having no routing at all. If the routing does have steps, check that each step resolves to a real work center: a step whose work center reference is stale, typically after a work center rename, behaves like a material step and books no capacity. Both faults show up in the anomaly checks, which is the second place to look.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.