How to Close One Shift for a Holiday in EDGEBIC

User Solutions TeamUser Solutions Team
|
6 min read

To close one shift for a holiday in EDGEBIC by User Solutions, set a per-day capacity override of zero on that shift for the date, on each work center that runs it. An override is keyed to a work center, a shift, and a date together, which is precisely the reach you need: the night shift goes to zero while the day shift keeps its hours.

The instinct is to look for a holiday tab on the shift record. There isn't one. EDGEBIC's scheduling engine understands closures at three scopes, plant, shift, and machine, but only the plant scope has a screen in the current release. Anything narrower is expressed with overrides, and this page covers the shift case.

Before You Start

  • You know which shift is off and on which date.
  • You know this is not a plant holiday. A plant holiday would close every shift, which is a different and much blunter tool.
  • You know which work centers run that shift. You will enter one override per work center, so it helps to have the list.
  • You can rerun the scheduler so existing plans reflect the closure.

Step 1: Open the Work Center's Per-Day Capacity

Open the Workcenter tab. On a work center that runs the shift you are closing, click the per-day capacity button on its row. The alternate route is Schedule > Resource Calendar, where you can double-click a date cell on that work center's Total Capacity row.

Step 2: Select the Shift You Are Closing

Pick the shift in Shift:. This is the field that makes the closure shift-specific rather than whole-day, and it is the one people skip. An override entered while the wrong shift is selected reduces capacity somewhere you were not looking, and the crew you meant to send home stays scheduled.

Step 3: Zero the Date

Adjust the From: and To: range so the date is visible, find its row, and type 0 in the Capacity (h) column. The change saves as you edit and the Overridden column ticks.

Add a Reason. Something a stranger can read six months later: Festival day, night crew off. This is the field that makes the closed day explain itself, and it is genuinely better documentation than a closure record with just a name.

Step 4: Repeat for Every Work Center on That Shift

The override closes one work center's shift, so a plant with six machines running nights needs six entries. Work down the list.

This is the honest cost of the current release: a single shift-level closure record would be one entry, and it does not exist yet. If the closure applies to the entire plant anyway, a plant holiday is one entry and the right choice. Overrides are for when genuinely one crew is off and the others are working.

Step 5: Reschedule

Run Schedule / Re-Schedule so any work that was planned for that shift on that date moves to available capacity. Entering the zeros changes the calendar but does not move existing bars on its own.

What Changes When You Save

SurfaceEffect
The chosen shift on that date, per work center overriddenZero capacity
Other shifts on the same machinesUnchanged; they keep running
Work centers you did not overrideStill open on that shift, which is the thing to double-check
Existing schedulesNot moved until you rerun
The override itselfPersists until you click Reset

How to Check It Worked

  1. Reopen each work center's per-day capacity view and confirm the Overridden tick on the right date, with the right shift selected.
  2. Switch Shift: to the crew that is still working and confirm it shows normal capacity on that date.
  3. Count your overrides against your list of machines that run the shift. A missed machine is the failure mode here, and it is silent.
  4. Rerun the scheduler and confirm night work that was planned for that date has moved off the closed shift.

Common Mistakes

Using a plant holiday by accident. A plant holiday closes every shift and every work center. If you only mean one crew, the override route is what gives you the narrower reach.

Overriding one machine and assuming the shift is closed. Overrides are per work center. The rest of the machines keep running that shift until you zero them too.

Selecting the wrong shift. The override lands on whichever shift is selected in the dialog. On a two-shift machine, closing the wrong one leaves the crew you meant to send home fully scheduled.

Forgetting to rerun. The capacity view shows zero, but existing bars stay put until a reschedule moves them.

Never resetting. An override outlives the holiday. Clear it when the crew is back or you have built yourself a permanent hole.

Next

Closing one shift is the middle case between a plant-wide closure and a single machine. For a company-wide closure, read how to add a plant holiday. For a partial-day reduction across the plant, read how to schedule a half-day holiday, and to block a time window for a whole crew, how to block a time window across a whole shift. To take a single machine out for the day, how to block a machine for a maintenance day covers the same dialog. More single-task recipes are in the EDGEBIC how-to hub, and the platform overview is at /edgebic.

Expert Q&A: Deep Dive

Q: Our night crew has the day after a local festival off, but days still runs. How do I model that?

A: Zero the night shift for that date on every work center that runs nights. Open each work center's per-day capacity view, select the night shift, find the date, type 0 in the Capacity column, and add a reason such as Festival day, night crew off. The day shift is untouched and keeps its capacity, while the night shift contributes zero hours on that date. Then rerun the schedule so any night work planned for that day slides to the next available night or onto the day shift where the routing allows. If the plant runs many machines on nights this is repetitive, and that is a fair complaint: there is no single shift-level closure record in this release, so the override is entered per machine.

Q: I added the holiday to the plant calendar and now the day shift is closed too. How do I fix it?

A: You used a plant holiday, which closes every shift and every work center on that date, not just the crew you meant to send home. Remove it from the plant calendar, then zero the specific shift with per-day capacity overrides on the work centers that run it. Do not go looking for a holiday tab on the shift record; there is no shift-scoped closure screen in the current release, and the override is the mechanism that gives you exactly the reach you want. Rerun the schedule afterward so the plan reflects the corrected calendar.

Frequently Asked Questions

Ready to Transform Your Production Scheduling?

User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team

User Solutions Team

Manufacturing Software Experts

User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.

Let's Solve Your Challenges Together