- How to Add Teardown Time to a Routing Step in EDGE…
To add teardown time to a routing step in EDGEBIC by User Solutions, enter the teardown hours on the step, then optionally turn on Show Teardown Time so the cleanup shows after the operation on the Gantt. Teardown time is a cost and display figure. It adds to the routing step's total-time cost rollup and can be drawn as a segment after the operation, but it is not used in capacity allocation, so it does not push the next operation's start date later. Reach for it when you want post-run cleanup to appear in cost estimates and, if you choose, on the schedule view, without changing the plan's dates.
This recipe covers one specific task. For the setup figure that does reserve capacity, read how to add setup time to a routing step. For how the timing pieces fit together, see how EDGEBIC composes step timing and EDGEBIC Bill of Routing explained.
Before You Start
- The routing open, with the step that carries the cleanup identified.
- The teardown duration in hours, and a decision on whether cleanup must also block the machine. If it must, plan to use setup time or a short operation, because teardown alone does not reserve capacity.
- Access to Settings if you want the teardown segment drawn on the Gantt.
Step by Step
- Open the BOR tab and select the routing.
- Select the step that carries the cleanup or teardown.
- Enter the teardown hours for that step. This value feeds the step's total-time cost rollup.
- Click Update Standard BOR to save.
- To render the teardown on the schedule, open Settings, go to the Manufacturing tab, and under the setup and queue time segment options turn on Show Teardown Time. The Gantt then draws a teardown segment after the operation.
- Run Generate Schedule if you want the cost or display change reflected in a fresh plan.
What Changes When You Save
Saving the teardown hours updates the cost math right away: the step's total time now includes the cleanup, so the routing's estimated cost and any new quote simulation reflect it. The scheduled operation window does not grow, because teardown time is a cost element and reserves no capacity. With Show Teardown Time on, the Gantt draws a teardown segment after the operation, which is a visual overlay only. No dates shift from teardown time alone. If cleanup must actually block the machine or delay the next step, use setup time on the following job or model the cleanup as its own short operation, since those are the figures the scheduler acts on.
How to Check It Worked
Open the routing's cost estimate or run a quote simulation and confirm the total reflects the added cleanup time. If you enabled Show Teardown Time, open the Job View Gantt and look for the teardown segment after the operation. Confirm the next operation's start date has not changed, which is correct: teardown time is not a scheduling delay, so if a date moved, another field is responsible.
Common Mistakes
- Expecting teardown to hold the machine. It does not reserve capacity. If cleanup must block the machine, use setup time on the next run or a short operation.
- Confusing teardown with setup. Setup extends the scheduled window and is reserved before the run. Teardown is cost and display only after the run. They are not interchangeable.
- Hunting for the segment without enabling it. The teardown segment does not appear on the Gantt until Show Teardown Time is turned on in Settings, and it is off by default.
Related Reading
- How to add setup time to a routing step for the changeover figure that reserves capacity.
- How to change the hours on a routing step for the per-unit run time.
- EDGEBIC and the EDGEBIC how-to hub for the wider set of routing tasks.
Teardown time gives cleanup a home in your cost model and, when you want it, on the Gantt, while keeping the scheduled dates under the control of setup, queue, and operation hours, which are the figures the engine plans against.
Expert Q&A: Deep Dive
Q: Every paint run needs 30 minutes of booth cleanup that I want costed. Where does it go?
A: Set the teardown hours on the paint step to 0.5. That adds the half hour to the step's cost rollup, so quotes and cost estimates reflect the cleanup labor. If you also want the cleanup drawn after the paint bar, turn on Show Teardown Time in Settings. Remember it will not reserve the booth for the next job, so if cleanup must block the booth, model it as setup on the next run or a short operation instead.
Q: I need cleanup to actually hold the machine before the next job. Teardown or setup?
A: Use setup time on the next job, not teardown on the finished one. Setup time reserves capacity and extends the scheduled window, so it genuinely holds the machine. Teardown time is cost and display only and reserves nothing. If the cleanup belongs to the finishing job rather than the next one, model it as a short work-center step with its own hours so the machine is booked for that duration.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.