How to Add an Alternate Work Center to a Step in EDGEBIC
To add an alternate work center to a step in EDGEBIC by User Solutions you open the step's True Alternatives tab, add the fallback machine, and enter its own setup and hours. The scheduler then treats that machine as a substitute it may pick instead of the primary, which is how a routing dodges a bottleneck without you rerouting jobs by hand.
An alternate replaces the primary. A parallel machine runs alongside it. Getting that distinction right is the whole game, and it is covered from the concept side in parallel and alternate work centers explained. This post is the setup task for the alternate.
Before You Start
- The alternate machine exists as a work center, and it has shifts assigned. A machine with no shift returns no capacity and the scheduler simply skips it.
- You have the alternate's own numbers. An older, slower mill has larger setup and per-unit hours, and you enter its figures, not the primary's.
- You know when substitution is appropriate. Alternates suit a specific operation with a specific fallback. For "any of these machines, plant-wide," a Work Center Group is the better model.
Adding the Alternate
- Open the BOR tab, select the routing in Data Grid mode, and select the step. Expand the step detail panel.
- In the Parallel Processing section, open the True Alternatives tab.
- Click + Add True Alternative. In the Select Work Center popup, pick the fallback machine and click OK.
- In the alternative's row, enter the machine's own numbers: Setup Time and Hours Req'd as they apply on that machine. The scheduler uses these directly and does not scale the primary's hours to fit.
- Click Accept in the detail panel, then Update Standard BOR.
In the grid, the alternate appears as a child row under the step, marked with ⟳ and the tooltip True Alternative Work Center. In Designer mode the same thing is a node joined with a True Alternative connector (right-click a connector, Connector Type, True Alternative), and selecting it shows a True Alternative Work Center banner in Properties.
Choosing How the Scheduler Picks
When you run a schedule that touches a step with true alternatives, the Alternative Work Center Selection dialog appears: "One or more BOR steps have True Alternative work centers." You have two top-level choices, and three strategies under the automatic one.
| Choice | Behavior |
|---|---|
| Auto – system picks | The scheduler decides per step, using the strategy you select |
| Manual – I'll choose per step | You set the machine for each listed step in the Selected Work Center column |
| Strategy (Auto) | Meaning |
|---|---|
| Earliest Completion | Picks the machine that finishes soonest, weighing speed against existing queue. The fastest outcome wins |
| Primary First | Stays on the primary while it has same-day capacity; falls back only when the primary is fully booked today |
| Earliest Start | Prefers whichever machine can begin soonest, so same-day availability beats a faster machine that can only start tomorrow |
Which strategy fits depends on why you added the alternate. Earliest Completion suits a shop where hitting dates is everything and you do not care which mill runs the job, because it always takes the fastest finish. Primary First suits a shop with a preferred machine, perhaps the one with the best fixturing, that falls back only under real pressure. Earliest Start suits work where getting parts moving matters more than the exact finish, for instance to free a queue or start a downstream crew. You can also drop to Manual and set the machine per step yourself when the call is judgment rather than arithmetic.
What Changes When You Save
| Surface | Effect |
|---|---|
| New manufacturing orders | The selection dialog appears; steps may book onto the alternate per your strategy |
| Steps with recorded actuals | Locked to the machine that ran them; never swapped |
| Jobs already scheduled | Unchanged until rescheduled, and each keeps its own routing copy |
| The Gantt | The operation lands on one machine, chosen at schedule time |
Worked through: the primary mill is booked for three days, and a 20% slower second mill is free tomorrow. Waiting for the primary starts the operation Thursday at 51.0 hours. Under Earliest Completion, the alternate starts Wednesday at 1.0 setup plus 0.60 times 100, which is 61.0 hours, and finishes about a day and a half earlier despite being slower. Availability beat raw speed, which is exactly the trade the alternate exists to make.
How to Check It Worked
In the grid, the alternate should show as a ⟳ child row under its step with its own setup and hours. If those cells are empty, the scheduler has nothing to plan the alternate with.
Run a test schedule and watch for the Alternative Work Center Selection dialog. It appearing at all confirms the alternate registered. Choose Auto with Earliest Completion, then read the Job View Gantt: the operation should sit on whichever machine the strategy chose, as a single bar rather than two.
If the alternate should have been used but was not, the usual causes are the Primary First strategy while the primary still had same-day room, or a step with actuals that is locked to its machine.
Common Mistakes
Entering the primary's hours on the alternate. The alternate uses its own Setup Time and Hours Req'd. A slower machine with the fast machine's numbers plans as if it were fast, and the plan lies.
Setting a factor and expecting it to matter. A true alternative is driven by its own hours, not by a parallel factor. Factors apply to parallel machines, which are a different mechanism: see how to make two operations run in parallel.
Adding an alternate with no shift. A machine with no shift assigned returns no capacity and is silently skipped. Confirm the alternate has a working calendar first.
Confusing alternates with pools. Hand-configuring the same alternate on every step across a shop is the wrong tool for "any mill will do." A Work Center Group models a pool once, and per-step alternates are for a specific fallback on a specific operation.
Expecting a mid-run job to move. Steps with actuals are locked to their machine. The alternate is a candidate only for work that has not started.
Next Steps
If you actually want two machines on the operation at once rather than a choice between them, how to make two operations run in parallel is the task. For the broader configuration, see how to configure parallel and alternate work centers. The full task library is at the EDGEBIC how-to hub, and the platform overview is at EDGEBIC.
Expert Q&A: Deep Dive
Q: Our second mill is 20 percent slower. Will the scheduler ever actually use it, and is slower still worth it?
A: It will use it whenever finishing sooner wins, and slower often does win. Say the primary is booked three days out and the slower mill is free tomorrow. Under Earliest Completion the operation starts tomorrow on the slower machine and finishes a day and a half earlier than waiting for the fast one, even though the run itself is longer. Enter the slower mill's own hours on its row, and let the strategy weigh speed against availability.
Q: A step already has hours logged on the primary machine, and we just added an alternate. Could a reschedule move it?
A: No. A step with recorded actuals is locked to the machine that actually ran it, so the scheduler never swaps machines under work in progress. The alternate becomes a candidate only for steps that have not started. That protects the shop floor: a job halfway through milling on the primary stays there, and the alternate is available for the next job whose milling step has not begun yet.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
How to Create a Watched-File Integration in EDGEBIC
Create a watched-file integration in EDGEBIC: point it at the file your ERP drops, pick the target entity and import mask, set the debounce, and let a new file trigger the run.
How to Rehearse an Integration With the EDGEBIC Simulator
Use the built-in Simulator to provision demo data, watch real integration runs happen, and prove the mechanism before you point anything at a live ERP. Includes the tear-down rule.
How to Run an Integration Now and Pause All Schedules in EDGEBIC
Force one integration to run with Run Now, cancel a run in progress, disable a single definition, or tick Pause all schedules to stop every automatic sync for the session.