- Home
- Blog
- Outcomes & ROI
- How Overlapping Operations Shorten Delivery on Big…
How Overlapping Operations Shorten Delivery on Big Orders
Lot streaming lead time reduction comes from a single change in permission: the downstream operation is allowed to start on the first finished sublot instead of waiting for the entire order. Instead of 1,000 pieces sitting at the mill until the last one is cut, the first batch moves to drilling while milling keeps running. EDGEBIC by User Solutions expresses that overlap as a field on the routing step, and on a documented order it turns a 52-hour serial handoff into roughly 37 hours on the same two machines.
This post is about the delivery outcome. For the three overlap models and when each applies, see lot streaming explained. This post sits under the EDGEBIC results guide.
The Waste of the Serial Handoff
Most scheduling systems treat a routing as a relay race. Operation 20 cannot begin until operation 10 reports complete, because that is the simplest rule to code. It is also wrong on the shop floor, where the first finished pieces have been sitting in a tote for hours.
The waste is easy to see once you look for it. A 26-hour machining run feeding a 4-hour deburring bench occupies 30 hours of calendar under a serial rule. Physically it needs closer to 27. That extra day is not a capacity problem, a staffing problem, or a routing problem. It is a permission problem: nothing in the schedule ever told deburring it was allowed to start. Multiply that across a routing with six operations and a large lot, and the delivery you quote is inflated by handoffs that never had to happen. For where lead time hides in general, see reduce manufacturing lead time.
The Overlap Made Concrete
Lot streaming grants the permission with a rule instead of a phone call. The piece-count model is the one most job shops want. You state a number of pieces, and the engine computes when that many will exist:
flow time = setup + min(transfer batch, order quantity) x hours per piece
Take a 100-piece shaft order. Turning runs at 0.5 hours per piece with a 2-hour setup, and the transfer batch is 20 pieces with a half-hour move time. Twenty pieces exist at 2 + 20 x 0.5 = 12 hours after the lathe starts, plus 0.5 hours of handling, so drilling is cleared at hour 12.5. The full turning run is 52 hours. Under a serial rule drilling waits all 52. The overlap pulls the job's elapsed time down to roughly 37 hours on exactly the same two machines. See the lot streaming overlap walkthrough for the arithmetic run end to end.
That 15-hour recovery cost nothing. No machine was added, no shift was worked. A field on the routing step told the second operation it could start when the work was physically ready.
Three Models, One Outcome
Delivery compression takes a different form depending on what "ready to move" means at the station:
| Model | What it fits | What the successor waits for |
|---|---|---|
| Piece-count transfer batch | Discrete parts: machining, fabrication, assembly | Setup plus batch size times hours per piece |
| Start-to-start lag | Continuous processes: paint, chemicals, extrusion | A fixed number of hours after the upstream step starts |
| One-piece flow | Lean cells, short cycles, high-value parts | Setup plus a single piece cycle |
The continuous-process case matters because plenty of shops have processes with no discrete pieces to count. A paint booth running 08:00 to 12:00 with a one-hour lag clears the curing oven to start at 09:00 instead of noon: three hours of compression, no counting required. See what is lot streaming for the concept and what a transfer batch is for the piece-count term.
Overlap Versus Parallel: Not the Same Lever
Lot streaming is often confused with running jobs in parallel, and the difference decides which one you reach for. Lot streaming overlaps sequential operations on the same routing: drilling starts on the first pieces while turning finishes the rest. Parallel processing runs one operation across several machines at once, which is a capacity play. See splitting a large order across parallel work centers for that mechanism.
They stack. A long routing can overlap its sequential steps and split its heaviest single operation across machines, and the delivery gains compound. But they answer different questions, and lot streaming has the lower cost of the two because it adds no iron, only permission.
What Overlap Cannot Do
It cannot exempt the downstream step from capacity. Overlap grants an early start; it does not create free hours on the second machine. If the drill is loaded, drilling begins at the later of the transfer-batch time and the drill's next open window. The plan tells you that honestly rather than pretending the overlap is free.
It cannot help where the handoff is already tight. A short upstream operation feeding a long downstream one has little serial waste to recover. The gain is largest where a long operation feeds a shorter one, which is exactly the shaft case, and it shrinks toward zero as the two run times converge.
It cannot be configured on a process it does not fit. Piece-count streaming is ignored on continuous-process work centers by design. Putting a piece count on a paint line does nothing, and the start-to-start lag is the model that belongs there instead. Choosing the model is a work center question, not a matter of taste.
It cannot substitute for a real bottleneck fix. Overlap compresses the handoff between operations; it does not add capacity at the machine that is genuinely the constraint. Where the constraint is the limit, protect it first. See protecting the constraint to lift plant output.
Want to know how much serial waste is inflating your quoted lead times? Bring a long multi-operation routing to a demo and we will run it serial and overlapped on your own numbers.
Lot streaming shortens delivery by letting a downstream operation start before the upstream operation has finished the whole order, so the two run in overlap instead of in sequence. In EDGEBIC you set a transfer batch on the routing step, and the engine clears the next step to begin the moment that many pieces exist. On a documented 100-piece shaft order, that pulls a 52-hour serial handoff down to roughly 37 hours on the same two machines, with no extra capacity added.
No. Lot streaming overlaps sequential operations: drilling starts on the first finished pieces while turning is still running the rest of the lot. Parallel processing runs one operation across several machines at once. They compress delivery through different mechanisms and can be used together. Lot streaming needs no extra machine, only permission for the next step to start early, which is why it is often the cheapest lead-time gain available on a long multi-operation routing.
Yes, through the start-to-start lag model. For a continuous process such as paint or extrusion, you mark the work center as continuous-process and set a lag in hours on the step. With a one-hour lag on a booth running 08:00 to 12:00, the curing oven is cleared to start at 09:00 instead of noon: three hours of compression with no piece counting. The piece-count model is deliberately ignored on continuous-process work centers so nobody configures pieces on a process that has none.
Expert Q&A: Deep Dive
Q: We machine a 100-piece order for 52 hours and drilling just sits waiting. How much time does overlap actually save?
A: On the documented case, drilling waits all 52 hours under a serial rule even though the first pieces were done in the first afternoon. Set a 20-piece transfer batch with turning at 0.5 hours per piece, a 2-hour setup, and half an hour of move time, and 20 pieces exist at 12.5 hours after the lathe starts. Drilling is cleared then, so the job's elapsed time falls from 52 hours to about 37 on the same two machines. That is a day and a half of delivery recovered on one order by changing a field, not by adding a machine or a shift.
Q: If we start the next step on 20 pieces, does the schedule still respect capacity on the second machine?
A: Yes. Overlap only grants permission to start early; it does not exempt the downstream step from finite capacity. Drilling still books real hours against the drill's shifts and cannot begin before the transfer batch exists or before the drill is free. If the drill is loaded, the step starts at the later of the two constraints. Lot streaming compresses the handoff where the downstream machine has room, and where it does not, the plan tells you honestly instead of pretending the overlap is free.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
What a Plan Built on Yesterday's Data Costs You
A schedule is only as current as its last data refresh. What goes wrong when that refresh depends on someone remembering, what an automatic sync changes, and the limits worth knowing before you trust it.
The Furnace Does Not Care How Many Hours Are Left
Batch equipment takes one job per chamber per day whatever the clock says. Scheduling it as pooled hours over-promises the constraint by a factor you can calculate.
How an Adherence Percentage Becomes an Investigation List
A percentage tells you the plan is not being followed and nothing else. The count of operations behind it is a finite work list, and pairing it with attainment tells you which of two problems you have.
