The EDGEBIC by User Solutions Dashboard Cockpit is one screen with four tabs, built for three different audiences, and every number on it carries a small chip that tells you how much to trust it. Where a report answers one question deeply, the dashboard answers "how are we doing right now?" at a glance. This guide covers what each tab is for, who should be reading it, and the two design decisions (data-quality chips and manual refresh) that shape how you use the whole thing.

The dashboard is the layer above the report catalog: tiles tell you something is off, reports tell you which job and which hour. For the click-by-click version of everything below, see how to use the dashboard tabs.

Four Tabs, Three Audiences

TabAudienceWhat it carries
CAPACITYPlanners and supervisors, the working defaultKPI tiles, work center utilization chart, capacity trends, job status donut, active jobs list, capacity and shift detail grids
STANDUPThe shop floor, on a wall-mounted screenSQDC band, andon strip per work center, bottleneck card, late-job punch list, dark theme applied automatically
EXECManagement review90-day tiles (throughput, on-time in full, backlog), multi-plant roll-up, top and bottom products
PLANNERWhoever owns the scheduleSchedule adherence, attainment, work-in-progress and late-job tiles, 14-day load heatmap, bottleneck and buffer panel

Nothing is duplicated for the sake of it. Each tab exists because a different person asks a different question of the same database, and giving all four to everyone is how dashboards end up ignored.

The Chips: How Much to Trust Each Number

The design decision that makes this cockpit unusual is that every tile declares its own provenance.

ChipMeaningHow to treat it
LiveA persisted real eventQuote it
PlanThe scheduler's projectionExpect it to move as actuals arrive
EstimateA heuristicDirectionally useful, not exact
OfflineThe source data does not exist yetShown as a dash, never a fake zero

That last row matters more than it sounds. The Safety and Quality tiles on the standup board sit at Offline because incident and defect logging are separate data sources; the exec margin tile sits at Offline until revenue is captured. A dash is honest absence. A zero would read as perfect performance, and a fabricated 100% would flatter every plant equally. The same principle runs through the reports, where OEE reads "n/a" instead of inventing a quality factor.

Hover any tile's info icon and you get its exact formula and data source in a sentence. That is the difference between a tile you can defend in a meeting and one you have to caveat.

The Capacity Tab: The Working Default

You land here. Six hero tiles run across the top:

TileWhat it showsHow it is computed
Production EfficiencyHow effectively resources are being usedProductive hours divided by available hours
On-Time DeliveryShare of completed jobs delivered by their due dateOn-time completions divided by total completions
Active JobsCurrent workloadCount of in-progress plus scheduled orders
OEEOverall equipment effectivenessAvailability times performance times quality
Capacity UtilizationShare of total capacity in useUsed hours divided by total available hours
BottleneckThe constraint work center, with a focus badgeThe flagged bottleneck work center

Below them, a work center utilization chart plots assigned against available hours per station, capacity trends plot total, assigned, and available over time, and an alerts panel lists current warnings. Sub-tabs go deeper: a capacity detail grid per work center with a department summary strip, a jobs view splitting scheduled from at-risk jobs, and a shifts view.

The Job Status Donut

Beside the active jobs list sits the donut, and it is worth learning properly because it encodes a distinction most shops make informally.

SliceRule
LateThe job finished after its due date, or it is unfinished and the plan itself lands past the due date. Structural lateness, flagged before the date arrives.
OverdueThe plan met the due date, but the date has passed and the job is not done. Execution lateness.
On timeThe due date is still open and the plan lands exactly on it, or the job actually finished on or before it.
EarlyThe due date is still open and the plan lands before it. The plan has slack.

Two subtleties. Whether a job has physically started is a small badge on the active jobs list, not a slice, because starting says nothing about whether it will be on time. And classification runs against the delivery-ready date, which is the scheduled end plus the product's end-item lead time, which is why job rows show a "Ready" date next to the "Due" date. The list sorts worst first, so the donut and the list together are your attention queue.

The Standup Tab: The Morning Huddle

Switch to Standup and the view changes to a dark theme built for a wall screen. It reads top to bottom in the order a huddle actually runs.

The SQDC band covers safety, quality, delivery, and cost, the four pillars of a lean daily management board (the framework is standard practice in the APICS and ASCM body of knowledge most planners already share). Delivery carries on-time in full; cost carries actual against estimated cost variance; safety and quality sit offline until their logs exist.

The andon strip gives one tile per work center, each showing that machine's andon state, and its colors are inferred from schedule actuals rather than machine sensors:

ColorMeaning
GreenRunning on plan, or about to start
YellowRunning more than 25% over its planned duration
RedMore than 10 minutes past planned start with no actual start
IdleNothing active
BlueMaterial wait
WhitePlanned downtime

That inference has one requirement: operators must punch in at operation start. A board that is all red by mid-morning is telling you about punch discipline, not about machines.

Below the strip, the bottleneck card and the late-job punch list, which on a good day simply says all orders are on track.

The Exec Tab: Ninety Days and Multiple Plants

Four strategic tiles cover throughput over the last seven days, on-time in full over the trend window, margin (offline until revenue exists), and backlog, which is a Live number because open order counts are persisted facts independent of any schedule.

The multi-plant roll-up assigns each job to one plant using a dominant-department rule: the department whose work centers consumed the most scheduled hours for that job wins it. That is a clean rule with one prerequisite, which is that every work center belongs to a department. A department whose throughput looks impossibly low is usually one with unassigned work centers rather than a quiet plant.

Top and bottom products rank the last 90 days by volume and by worst on-time performance, so the chronically late products that also ship in quantity surface first. That pairing is the list worth taking to an engineering review.

The Planner Tab: Measuring the Plan Itself

This is the tab that measures the schedule rather than the shop.

Schedule adherence is the share of operations that started within an hour either side of plan over the past 14 days, with a target of 90% or better. Its delta note ("35 ops moved off plan") is an investigation count rather than a statistic. Our schedule adherence KPI guide covers the generic metric; the number here is Live, because it is computed from real start events.

Attainment is the share of completed jobs that hit their due date, target 85% or better.

The 14-day heatmap colors every work center and day cell by load, which is assigned hours divided by that day's capacity. Red means oversold: more hours booked than the day holds. Hover a cell for the raw numbers. What to do about a red cell is the subject of reading a red day.

The Resource Calendar: The Planner's Ledger

Alongside the cockpit, the Resource Calendar in the Schedule area is the capacity ledger: work centers by time period, switchable between total capacity, hours assigned, backlog, available capacity, and utilization, in day, week, month, or quarter buckets.

Backlog is the mode most shops under-use. Assigned answers "what hours land in this period?"; backlog answers "how much work is still ahead of this station as of this period?". It is a forward sum of remaining hours, so it burns down as work is consumed: a 24-hour step spread over three days reads 24, then 16, then 8, then 0 rather than repeating 24 until it finishes. A backlog that grows week over week means work is arriving faster than the station clears it, which is a lateness warning weeks before the donut turns red.

Click any non-zero assigned or backlog cell and a job detail popup lists the exact allocations behind the number, with job, product, work center, shift, date, instance, hours, and pieces. The rows sum back to the cell under the same filters, which is what makes the number arguable rather than mysterious.

Dashboard or Report?

Same database, different lenses. Dashboards are glanceable and read the plan at a summary altitude. Reports are the drill-down and carry the authoritative formulas plus the built-in column glossary. For capacity specifically, the Work Center Utilization report is the authority, and the department capacity view shows the same numbers rolled up. When the two seem to disagree, they are usually answering different windows: a heatmap cell is one day, a report averages a range.

For the ways a correct tile still gets read wrong, see dashboard misreading mistakes. A wider cross-plant view built on these same signals is described in the EDGEBIC Control Tower roadmap, which is explicit that it is a planned direction and not a screen you can open today. For the whole system, the complete EDGEBIC guide is the pillar, and the documented results show what shops do with the numbers.

Want to see your own plant on this cockpit? Bring an export to a demo.

The Dashboard Cockpit is EDGEBIC's always-on overview screen, split into four tabs for three audiences. Capacity is the operational default with utilization charts and a job status donut. Standup is a dark, TV-friendly board for the morning meeting with an andon strip. Exec carries 90-day strategic tiles and a multi-plant roll-up. Planner carries schedule adherence, attainment, and a 14-day load heatmap.

Every cockpit tile carries a small chip naming where its number came from. Live means a persisted real event, so trust it. Plan means the scheduler's projection, which improves as actuals flow in. Estimate means a heuristic. Offline means the source data does not exist yet, and the tile shows a dash rather than a fabricated zero. The chip is what tells you whether a number belongs in a customer conversation.

Not by default. Each cockpit tab loads its snapshot when you switch to it, and the Refresh now button reloads on demand, which keeps a big schedule from being re-queried continuously in the background. The capacity tab additionally offers its own auto-refresh interval in its settings dialog, where zero disables it. Click Refresh now when a meeting starts so nobody argues over a stale tile.

Late means the plan itself misses the due date, or the job actually finished after it, so the problem is structural and visible before the date arrives. Overdue means the plan met the due date but the date has now passed with the job unfinished, so the problem is execution. They are separate slices because the fixes differ: Late needs capacity or a renegotiated date, Overdue needs someone to find out why the work stalled.

Expert Q&A: Deep Dive

Q: Which tab should be on the TV in the shop, and which should the planner keep open?

A: Standup belongs on the floor TV: switching to it applies a dark, high-contrast theme automatically, and it reads top to bottom in a five-minute huddle. The SQDC band, then an andon tile per work center, then the bottleneck card, then the late-job punch list, which on a good day says all orders on track. Planner is the tab the person who owns the schedule keeps open, because it carries the two metrics that measure the plan itself: schedule adherence (operations that started within an hour of plan over the past 14 days, target 90% or better) and attainment (completed jobs that hit their due date, target 85% or better), plus the 14-day load heatmap where an oversold day shows up as a red cell before anyone feels it.

Q: Our Safety and Quality tiles show a dash. Is the dashboard broken?

A: No, that is the Offline chip doing its job. Those tiles need an incident log and a defect log as data sources, and until those exist the honest display is a dash rather than a fabricated 100% or a zero that reads as perfect. The same honesty applies elsewhere: the margin tile stays offline until revenue data is captured, and OEE's quality factor reads n/a until kiosk punches carry good, scrap, and rework counts. A dashboard that invents numbers to fill space is worse than one with visible gaps, because you cannot tell which tiles to trust.

Frequently Asked Questions

Ready to Transform Your Production Scheduling?

User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team

User Solutions Team

Manufacturing Software Experts

User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.

Let's Solve Your Challenges Together