Mapping Microsoft Dynamics data into EDGEBIC is a column-mapping exercise rather than a development project: you export items, work centers, routings, open orders, and optionally reported hours to Excel or CSV, then drag each source column heading onto the matching EDGEBIC field once and save it as a reusable import mask. This reference lists what maps to what, which columns are mandatory, how unit conversion and blank cells behave, and what every row outcome means when a run finishes.

EDGEBIC by User Solutions integrates with Dynamics through those masks rather than a certified connector, so nothing is installed inside the ERP and nothing enters its update path. If you have not read the end-to-end version, start with the complete Dynamics integration guide. This post is the lookup table you keep open while building masks.

The load order

Import in dependency order. Later files reference records that earlier files created.

#Dynamics exportEDGEBIC entity typeDepends on
1ItemsProductNothing
2Work centersWorkcenterNothing
3Routings / operationsBOR (bill of routing)Items and work centers
4Open production ordersSalesOrderItems
5Reported hours (optional)ActualsScheduled jobs

Two entity types have no ERP origin and are built from a spreadsheet you write yourself: Shift (one row per shift with a start and end pair per weekday, a blank pair meaning the day is off) and PlantHoliday (closures by name and date). These two define the calendar every date is computed against, so they deserve ten careful minutes rather than five. A one-sided weekday, a start time with no end time, fails the row, so fill both cells of a pair or blank both to make it a day off.

Auto-create is on by default, so a routing file naming a work center that has not been imported yet creates it on the fly. That is a useful safety net and a poor strategy: an auto-created work center has a name and nothing else, meaning one machine, no shift assignment, and no efficiency. Load the work center file properly first.

Items to Product

EDGEBIC target fieldMandatorySource column
Product_IdYesThe item identifier. Natural key, matched case-insensitively
Product_Name, DescriptionDescriptive text
UOMUnit of measure
Unit_Price, Lead_Time, CategoryOptional planning and quoting attributes
Size, Weight, Country_Of_OriginOptional descriptive columns

Only the identifier is required. Everything else can arrive later through a second, narrower refresh file, because blank cells preserve existing values on an update run. Watch identifier formatting across exports: matching ignores case but not leading zeros, so 0000123456 and 123456 create two products. Make every export render the identifier the same way, usually by formatting the column as text with the padding kept.

Work centers to Workcenter

This is the file where scheduling accuracy is won or lost, because it carries capacity.

EDGEBIC target fieldMandatoryWhat it drives
Workcenter IdYesNatural key. Routing steps match on it
Workcenter NameLabel on the Gantt and in reports
Number_Of_InstancesHow many identical machines the center holds. Blank defaults to 1
Capacity, EfficiencyRated capacity and the efficiency applied to it
Setup_Time_HoursDefault setup, overridden per routing step where present
Hourly_RateCost rollups
Is_BottleneckMarks the constraint so the engine can anchor around it
One_Per_Day_FlagOne job per machine per day, for long-changeover centers
Use_Global_Shifts, Shift_NamesCalendar assignment
Pieces_Per_HourRate-based capacity where the center is measured in output
Min_Batch_Size, Max_Batch_SizeBatching limits
Is_Active, Color, TypeHousekeeping and Gantt color

Number_Of_Instances is the highest-value column on the page and the one most ERP exports do not carry, because ERP data models generally describe a work center as a capacity figure rather than a count of machines. A cell of four identical machines imported with one instance produces a plan roughly four times too long, and it fails quietly: nothing errors, the dates are simply wrong. Fill it deliberately for every multi-machine center. The arithmetic is in how EDGEBIC calculates work center capacity.

If your export expresses capacity as an available-hours figure that already embeds a machine count, do not carry that number into Capacity unchanged while also setting instances, or you will count the same capacity twice. Pick one representation: instances plus the shift calendar is the one the engine reasons about best.

Machine pools have no export column

Planners think in pools of interchangeable machines, and EDGEBIC models that as a work center group. The membership is not a static assignment: a routing step bound to a group re-evaluates every member on each reschedule, picks by strategy (earliest completion, primary first, or earliest start), and applies a per-member efficiency factor so a slower machine is chosen only when it still finishes first. Operations already started keep the machine they started on, because recorded work is never moved.

None of that fits in an export column. Import the members as ordinary work centers, then create the group inside EDGEBIC and add them: a one-time configuration per pool, and one of the settings that most changes what the schedule looks like. The concept is defined in what a work center group is and the procedure is in how to create work center groups.

Routings to BOR

EDGEBIC target fieldMandatoryWhat to put in it
End_ProdYesItem identifier this routing builds
Sub_ProdYesWork center id (operation row) or component item (material row)
Op_FlagYesTrue for an operation, false for a material or component
No_ReqYesHours required per unit
Seq_NoOperation sequence, in gaps of 10
Next_SeqLeave blank; chaining happens automatically
Setup_TimeSetup hours at this step
Queue_TimeBuffer hours before the step may start
Flow_Step, Transit_DaysOverlap between steps, and transport time
Parallel_OpParent step's work center name for parallel or alternate steps
Alt_TypeParallel-Independent, Parallel-Dependent, or Alternative
Res_MultApplicable machine instances for this step
Fam_DeptDepartment for auto-created work centers

Op_Flag is the field people get wrong first. True means "this row is an operation running on a work center". False means "this row is a component consumed at this point in the routing". Mixing them produces a routing full of work centers that are actually parts, and it is visible immediately in the graphical designer.

Why the import takes two passes

A routing cannot be written row by row, because step 10 must point at step 20 and step 20 does not exist yet. So the import runs in two passes. Pass one validates each row, resolves or creates the items and work centers it names, and buffers the row. Pass two groups the buffer by end product, sorts by sequence number, writes the steps, and wires the chain: 10 to 20, 20 to 30, and the terminal step to the finished item so the routing renders connected. Check that visually after the first import: a routing missing its final link draws as a chain floating free of the item it builds.

Two rules follow from the same mechanism. All of one item's steps must travel in one file, because a run wipes and recreates that item's steps on first reference, and splitting across two runs means the second wipe deletes the first run's work. And re-importing is safe for running orders, because every scheduled job carries a frozen snapshot of the routing it was planned with.

Outside processing maps cleanly as an operation row on a work center that represents the vendor, with the turnaround expressed as transit days. That keeps the outside time visible on the Gantt rather than buried inside one long step.

Orders to SalesOrder

EDGEBIC target fieldMandatorySource
Product_Id(BOR)YesItem being built
QtyYesOrder quantity
Job_DateYesRelease or start date
Sales_Order(Ref#)Order reference: shared references group into one sales order, jobs auto-number {Ref}-{line}
Job_NumberYour ERP order number carried across
Due_Date, Order_Date, PriorityPromise, entry, and ranking
Customer_NameAuto-created when missing
Unit_Price, User_NotesOptional

Two mask options control the date logic when the export carries only one date: one treats the job date as the due date, the other derives the job date backward from the due date. Choose the one matching how your export is built, once, on the mask.

Reported hours to Actuals

Job number, work center id, and actual date are mandatory. Hours and pieces are both optional, and either can be derived from the other using the operation's rate. A Complete column marks the operation finished, and an explicit start column overrides the default of using the earliest imported date.

The import always overwrites the days a file carries, so re-running a corrected extract fixes the numbers rather than doubling them. Days a file does not mention are preserved unless you explicitly ask for them to be cleared. Actuals import last, because each row has to find an operation on a job that is already scheduled.

Conversions, blanks, and zeros

SituationBehavior
Minutes in the exportConversion factor 0.016667 on that mask column
Seconds in the exportConversion factor 0.000278
Hours quoted per 100 piecesConversion factor 0.01
Blank cell on an updateExisting value preserved
Zero in a cell on an updateZero is written: it is a value, not a blank
Unmapped columnIgnored entirely
Mandatory field unmappedRun aborts before reading any row
One bad rowFails alone and the run continues, unless you choose strict mode

Different columns in the same file can carry different factors, so a routing export mixing per-lot run times with per-changeover setup minutes lands correctly in a single run.

Reading the outcomes

Every row resolves to Created, Updated, Reused, or Failed. Reused is the default for a record that already exists, so a weekly item file of 8,000 rows reporting Created 14, Reused 7,986 is the desired result rather than a failure. When counts look wrong, the per-run log file carries one line per row with the exact reason for every failure.

What import cannot bring, and why it matters

The settings that most differentiate a schedule have no column in any ERP export: the sequence-dependent setup matrix, operator skills and certifications, work center group strategies, bottleneck anchoring, and lot streaming transfer batches. Those are configured once in EDGEBIC and then apply to every imported order afterwards. The EDGEBIC product overview maps the engine, and the ERP integration architecture explains why one mask design serves every ERP.

For the questions that come up before a project starts, see the Dynamics integration FAQ, and for the case that usually precedes the decision, Dynamics scheduling gaps and how EDGEBIC fills them. The Infor and Global Shop Solutions references show how little the method changes from one platform to the next, and the ERP scheduling add-on page frames the category.

Each entity type has a short mandatory list and everything else is optional. Products need a product id. Work centers need a work center id. Routings need end product, step name, an operation flag, and hours required. Orders need product, quantity, and a job date. Actuals need job number, work center id, and the actual date. If a mandatory field is unmapped in the mask, the run aborts before reading a single row.

Use a conversion factor on that mask column. Minutes become hours with a factor of 0.016667, seconds with 0.000278, and a time quoted per 100 pieces becomes per piece with 0.01. The multiplication happens before the value is stored, so the file needs no pre-processing in Excel. Factors are saved with the mask, which makes the conversion permanent, repeatable, and auditable through the per-run log.

Dependency order: items first, then work centers, then routings, then open orders, then reported hours. Routings reference both items and work centers, and orders reference items, so loading upstream data first stops the auto-create behavior from inventing thin placeholder records. Auto-create is on by default and will fill gaps, but a record created that way carries only the name it was given.

No, and trying usually costs a month. Import what the ERP holds today, schedule it, and compare the dates with what your planner believes. The disagreements are your defect list and they arrive specific: a wrong hours-per-unit shows up as an order finishing implausibly early. Because a routing re-import wipes and recreates that item's steps, each corrected file replaces the last cleanly rather than layering on top of it.

Expert Q&A: Deep Dive

Q: Our production BOM and routing come out of Dynamics as two separate exports. Do we merge them, and where do components go?

A: Keep them separate for the first pass and load only the routing, because operations are what the scheduler needs to build a plan. Components belong in the same routing file as rows with the operation flag set false, which tells the engine the row is a part consumed at that point rather than an operation running on a work center. The practical order is to get the operations correct first, confirm the routing draws as one connected chain in the designer, and then add the component rows in a second version of the same file. Remember the wipe rule when you do: all of one item's rows, operations and components together, must travel in one file, because a run recreates that item's steps from what it reads.

Q: We run one company database across three sites and the work center codes repeat per site. Do those collide in EDGEBIC?

A: Yes, because the work center identifier is the natural key and there is no site dimension above it. Two centers both called WELD-1 become one record with combined load, which produces a schedule that looks plausible and is wrong. Fix it on the export side with a site prefix so they arrive distinct, something like S1-WELD-1 and S2-WELD-1, and then use the department column to tag each with its site so views stay filterable. Do this before routings are loaded, because routing steps match on the work center identifier and re-pointing them afterwards means re-exporting and re-importing every affected routing.

Frequently Asked Questions

Ready to Transform Your Production Scheduling?

User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team

User Solutions Team

Manufacturing Software Experts

User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.

Let's Solve Your Challenges Together