- An EDGEBIC Migration Checklist
An EDGEBIC migration checklist runs in six phases: prepare and clean data, build masks, import in dependency order, verify capacity, run a pilot, and expand. In EDGEBIC by User Solutions, every step is low risk because RMDB stays the system of record and imports come through saved masks. The checklist is a sequence of small, reversible steps, not a single cutover, so a small team can work it part time and finish when EDGEBIC has earned the schedule rather than when a deadline arrives.
How to use this checklist
Work the phases in order, but treat them as a loop, not a one-way march. Because import masks are saved and RMDB stays supported, you can go back a phase, fix something, and re-run in a click without penalty. The point of the checklist is that nothing surprises you: each phase has a clear job, and each job is small. The whole thing fits the phased approach on the RMDB to EDGEBIC guide.
The six phases at a glance
| Phase | Job | Key output |
|---|---|---|
| 1. Prepare | Pick the pilot cell, clean the scheduled tree | Clean, consistent source files |
| 2. Build masks | Map columns once per entity, save each mask | One saved mask per entity |
| 3. Import | Load in dependency order | Every reference resolved |
| 4. Verify | Set calendars, reconcile capacity | Capacity matches the current system |
| 5. Pilot | Schedule, compare dates, reconcile | Planner trust in the cell |
| 6. Expand | Widen cell by cell, then cut over | EDGEBIC owns the schedule |
Phase 1: prepare
- Choose the pilot cell. Pick a self-contained work area with a clear bottleneck, stable routings, and an engaged planner. Details are in planning an EDGEBIC pilot on one cell.
- Clean the scheduled tree. Standardize product and work center names across all files, fill required fields (setup and run times, quantities, due dates), and drop dead references. Clean only what scheduling reads, covered in cleaning your data before importing to EDGEBIC.
Phase 2: build masks
- Export each entity. Send products, work centers, customers, routings, and open orders out of RMDB in their existing layouts.
- Map columns once. Build one import mask per entity, mapping your columns to EDGEBIC's fields, and save each mask. The mechanics are in EDGEBIC import masks explained.
- Confirm blank-cell handling. Check how each mask treats empty cells so a blank does not clear a value you meant to keep.
Phase 3: import in dependency order
- Products and work centers first. These are the foundation everything references.
- Then customers, then routings, then orders. References link by name, so the target must exist before the pointer. The full reasoning is in the order to import your data into EDGEBIC.
- Let the two-pass routing import handle sequence. It wires step order inside the routing file for you.
Phase 4: verify capacity and calendars
- Set shifts, holidays, and calendars. Bring across your shift patterns and plant holidays, either through their import masks or by keying them in, then attach the calendars and add any per-day capacity overrides.
- Reconcile capacity before reading a date. Confirm EDGEBIC's capacity per work center matches your current system, work center by work center. This is the step that keeps every later date comparison honest, and it is the guard against wrong-but-plausible dates.
Phase 5: run the pilot
- Schedule the cell. Run a scheduling pass on the pilot cell.
- Compare dates. Line up EDGEBIC's dates against your existing plan for the same jobs, and reconcile every difference at the source. The validation discipline is in validating a migrated schedule against RMDB.
- Keep RMDB in charge. The plant runs on RMDB; the cell is a controlled comparison, the pattern in running RMDB and EDGEBIC side by side.
Phase 6: expand and cut over
- Widen cell by cell. Add a cell only when the planners stop double-checking the last one's dates.
- Handle open jobs at cutover. Let short jobs finish on RMDB and import new work clean, per migrating open jobs and actuals to EDGEBIC.
- Complete the cutover on your timeline. RMDB stays supported, so you finish when EDGEBIC has earned the schedule, covered in completing the cutover to EDGEBIC.
Where the effort actually is
The checklist looks long, but the effort is not evenly spread. Phases 2 and 3, building masks and importing, are the real work, and they are a few days done once. After that, every import is a one-click re-run of a saved mask. Phase 5, the pilot loop, is a planner spending a few minutes each cycle on a comparison. Nothing on the list is a standing full-time commitment, which is why a small team can work it part time.
The one item not to skip, however busy you are, is the capacity verification in phase 4. It is quick, and it is what makes every later comparison meaningful. Skip it and you will chase date differences that were only ever a missing holiday.
Why the checklist is low risk
Every phase is reversible. Cleaning happens in the spreadsheet, before anything is imported. Imports re-run in a click because the masks are saved. The pilot keeps RMDB as the system of record, so the plant is never at stake. And there is no forced cutover, because RMDB stays fully supported for as long as you want it. The result is a migration made of small, reversible steps, which is exactly how a cautious shop should take on a new tool.
The takeaway
An EDGEBIC migration checklist is six phases: prepare and clean, build masks, import in dependency order, verify capacity, run a pilot, and expand. The heavy work is front-loaded into mask building and cleaning, a few days done once, and everything after is a one-click re-run or a few minutes of comparison per cycle. Verify capacity before you read a date, keep RMDB in charge until EDGEBIC earns the schedule, and move at your own pace because there is no forced cutover. See the platform in full on the EDGEBIC overview, read the whole path on the RMDB to EDGEBIC guide, and turn the list into a timeline with a phased migration plan to EDGEBIC. For the whole subject end to end, read the complete guide to migrating to EDGEBIC.
Expert Q&A: Deep Dive
Q: We want a single document our team can work through so nobody skips a step. What does the whole checklist look like end to end?
A: The checklist has six phases, each a short set of tasks. Phase one, prepare: pick the pilot cell, and clean the scheduled tree so names match and required fields are filled. Phase two, build masks: create and save one import mask per entity, mapping columns once. Phase three, import: load in dependency order, products and work centers, then customers, then routings, then orders. Phase four, verify: set shifts, holidays, and calendars, and confirm capacity per work center against your current system before reading a date. Phase five, pilot: schedule the cell, compare EDGEBIC's dates against your existing plan, and reconcile every difference at the source. Phase six, expand: widen cell by cell as the planners trust the results, and complete the cutover only when EDGEBIC has earned it. RMDB stays supported throughout, so you work the list at your own pace, and every import step is a saved-mask re-run in a click.
Q: Our team is small and cannot dedicate someone full time to a migration. Can the checklist be worked part time?
A: Yes, the checklist is designed for exactly that, because the heavy work is front-loaded and one-time while the ongoing work is minutes per cycle. The mask building and data cleaning in phases two and three are the real effort, and they are a few days done once, not a standing commitment. After that, the pilot loop in phase five is a planner spending a few minutes each cycle comparing EDGEBIC's dates against the current plan for one cell, which fits alongside normal work. Because RMDB stays the system of record and imports re-run in a click, there is no pressure to finish by a date, so a small team can work the list part time over several weeks. The one thing not to skip, however busy you are, is the capacity verification in phase four, because it is what keeps every later comparison meaningful.
Frequently Asked Questions
Ready to Transform Your Production Scheduling?
User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team
Manufacturing Software Experts
User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.
Share this article
Related Articles
Migrating to EDGEBIC: The Complete Guide
The full path from RMDB, EDGEBI, a spreadsheet, or a whiteboard to EDGEBIC: what carries forward, what is hand-built, the import order, and how to validate the first schedule.
Migrating Your Tools and Fixtures to EDGEBIC
Tools and fixtures are not one of the eight import masks, so you build the list by hand. Here is what to enter, the quantity rule that ruins schedules when it is wrong, and where tools belong in the migration sequence.
Rehearsing Your EDGEBIC Migration Load
The data load is a repeatable operation, not a one-shot event. Every entity type is safe to re-import, and a reset takes you back to an empty plant, so plan to load your data three times before go-live.