Glossary

Time-Phased Order Point — Manufacturing Glossary

User Solutions TeamUser Solutions Team
|
5 min read
Time-phased order point TPOP planning grid for manufacturing glossary
Time-phased order point TPOP planning grid for manufacturing glossary

Time-Phased Order Point (TPOP) is an inventory planning method that applies MRP-style time-phased logic to independent demand items. Instead of triggering orders when inventory hits a static reorder point, TPOP projects inventory forward period by period, considering forecasted demand and scheduled receipts, and generates planned orders only when projected inventory will fall below zero or safety stock.

At User Solutions we see TPOP as the bridge between simple reorder-point systems and full MRP — giving manufacturers time-phased visibility for finished goods and service parts that do not have a parent BOM to drive their planning.


How Time-Phased Order Point Works

TPOP uses the same planning grid as MRP but substitutes forecast demand for BOM-driven dependent demand:

  1. Load demand forecasts into time buckets across the planning horizon.
  2. Add any known customer orders that consume the forecast.
  3. Subtract demand from projected on-hand inventory period by period.
  4. When projected inventory drops below safety stock, generate a planned order.
  5. Offset by lead time to determine the order release date.
  6. Apply lot sizing to determine order quantity.

The result is the same time-phased output that MRP produces — but driven by forecast instead of BOM explosion.


TPOP Example

A manufacturer stocks finished product FP-200 (industrial pump). Planning data:

  • On-hand inventory: 180 units
  • Safety stock: 50 units
  • Lead time: 2 weeks
  • Lot sizing: EOQ of 200
Week 1Week 2Week 3Week 4Week 5Week 6
Forecast Demand404550405545
Customer Orders352010000
Net Demand404550405545
Projected On-Hand14095455-50-95

Projected on-hand drops to 45 in Week 3 — below safety stock of 50. TPOP triggers a planned order:

  • Order quantity: 200 (EOQ)
  • Need date: Week 3
  • Release date: Week 1 (offset by 2-week lead time)

After the planned receipt:

Week 1Week 2Week 3Week 4Week 5Week 6
Projected On-Hand14095245205150105

Inventory stays above safety stock throughout. Compare this with a static reorder point of 120: the traditional method would have triggered an order in Week 2 when on-hand hit 95 — one week later than TPOP's time-phased view detected the problem.


Why TPOP Matters for Scheduling

Provides forward visibility for finished goods. TPOP shows when replenishment production or purchasing must start for finished goods, giving scheduling tools like Resource Manager DB the lead time needed to plan capacity.

More precise than reorder points. TPOP considers the timing and magnitude of future demand, not just the current inventory level. This prevents both premature ordering (when a dip is temporary) and late ordering (when demand is accelerating).

Integrates with MRP. TPOP-generated planned production orders for finished goods feed into MRP as the master production schedule, which then explodes BOMs for components. The two methods work together seamlessly.

Reduces finished goods inventory. By ordering based on projected need rather than fixed triggers, TPOP avoids the chronic over-ordering that static reorder points produce when demand is variable.


  • Independent Demand — The demand type that TPOP is designed to plan, driven by forecasts and customer orders.
  • Safety Stock — The buffer level that TPOP uses as its minimum inventory threshold.
  • Material Requirements Planning (MRP) — The planning method for dependent demand items that complements TPOP for independent demand.

FAQ

Traditional reorder point triggers an order when inventory drops below a fixed level, ignoring when future demand occurs. Time-phased order point uses MRP-style time-phased planning to project inventory period by period, ordering only when projected inventory will fall below zero or safety stock. TPOP is more precise because it considers the timing of known demand.

TPOP is best for independent demand items — finished goods and service parts — where demand comes from forecasts rather than BOM explosion. MRP handles dependent demand items (components) whose requirements are calculated from parent orders. Many systems use MRP for dependent demand and TPOP for independent demand items.

Yes. TPOP uses safety stock the same way MRP does — as a minimum inventory floor. When projected on-hand inventory would drop below the safety stock level, TPOP generates a planned order to replenish, offset by the item's lead time.


This term is part of the Manufacturing Glossary. For a deep dive into material planning, see our MRP Guide.

Frequently Asked Questions

Ready to Transform Your Production Scheduling?

User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team

User Solutions Team

Manufacturing Software Experts

User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.

Let's Solve Your Challenges Together