Glossary

Rough-Cut Capacity Planning (RCCP) — Manufacturing Glossary

User Solutions TeamUser Solutions Team
|
5 min read
Rough-Cut Capacity Planning RCCP load profile for manufacturing glossary
Rough-Cut Capacity Planning RCCP load profile for manufacturing glossary

Rough-Cut Capacity Planning (RCCP) is a high-level capacity validation technique that checks whether the Master Production Schedule (MPS) is feasible before running MRP. RCCP uses aggregate resource profiles to quickly identify major capacity conflicts at key work centers, allowing planners to adjust the MPS before investing time in detailed material planning.

At User Solutions we describe RCCP as the "sanity check" that prevents planners from running MRP against an impossible schedule. It takes minutes instead of hours and catches the big problems early.


How RCCP Works

RCCP uses a simplified approach to capacity validation:

  1. Define resource profiles for each finished product — the estimated hours required at each key work center to produce one unit.
  2. Multiply MPS quantities by the resource profile to calculate capacity loads.
  3. Load the results into weekly or monthly time buckets.
  4. Compare loaded hours against available hours at each key resource.
  5. Flag overloads for MPS adjustment.

Resource Profiles

A resource profile (also called a bill of resources or bill of labor) is a simplified summary of the routing. Instead of listing every operation, it aggregates hours by key work center:

ProductCNC Mill (hr/unit)Assembly (hr/unit)Test (hr/unit)
Product A0.80.50.2
Product B1.20.30.4
Product C0.41.00.3

These profiles capture the essential capacity consumption without the detail of full routings.


RCCP Example

A manufacturer has three key resources, each available 80 hours per week. The MPS for Week 15:

ProductMPS QtyCNC MillAssemblyTest
Product A6048 hr30 hr12 hr
Product B4048 hr12 hr16 hr
Product C2510 hr25 hr7.5 hr
Total106 hr67 hr35.5 hr
Available80 hr80 hr80 hr
StatusOver by 26 hrOKOK

RCCP immediately flags the CNC Mill as overloaded by 32.5% in Week 15. Before running MRP, the planner can:

  • Shift 15 units of Product B to Week 14 (which has spare CNC capacity)
  • Approve 10 hours of overtime for Week 15
  • Reassess whether all 60 units of Product A are truly needed in Week 15

This adjustment takes 15 minutes. Without RCCP, the planner would run MRP (2 hours), then run CRP (30 minutes), then discover the overload — wasting 2.5 hours on planning that was based on an infeasible MPS.


Why RCCP Matters for Scheduling

Validates the schedule before detailed planning. RCCP catches major feasibility problems at the MPS level, before MRP generates thousands of planned orders against an impossible plan.

Saves planning time. Adjusting the MPS and re-running RCCP is fast. Re-running MRP and CRP after discovering problems is slow. RCCP front-loads the feasibility check.

Focuses on bottlenecks. By checking only key resources, RCCP directs attention to the constraints that matter most. Scheduling software like Resource Manager DB handles detailed sequencing; RCCP ensures the aggregate plan is sound.

Supports S&OP decisions. RCCP operates at the level where Sales & Operations Planning makes decisions — aggregate product families and time periods. It provides the capacity data needed for executive-level production commitments.

Bridges business planning and execution. In the MRP II hierarchy, RCCP sits between the business plan and detailed MRP, ensuring that high-level commitments translate into achievable production plans.


  • Capacity Requirements Planning (CRP) — The detailed capacity check performed after MRP, complementing RCCP's high-level validation.
  • MRP II — The manufacturing management framework where RCCP validates the MPS before MRP processes it.
  • Planning Horizon — The time span across which RCCP evaluates capacity feasibility.

FAQ

RCCP is a high-level check done before MRP runs, using aggregate resource profiles against the master production schedule. CRP is a detailed check done after MRP, using actual routings and operation-level data. RCCP answers "is this MPS roughly feasible?" while CRP answers "exactly where are the capacity overloads?"

RCCP multiplies the MPS quantity for each product by a resource profile — the standard hours required per unit at each key work center. The result is loaded into time buckets. If any key resource exceeds available hours, the MPS needs adjustment before MRP runs.

Focus on bottleneck and critical resources — typically 5 to 10 key work centers that constrain throughput. Including every resource defeats the purpose of a rough-cut check. Common choices are CNC machining centers, assembly lines, paint booths, test stations, and critical labor skills.


This term is part of the Manufacturing Glossary. For a deep dive into material planning, see our MRP Guide.

Frequently Asked Questions

Ready to Transform Your Production Scheduling?

User Solutions has been helping manufacturers optimize their production schedules for over 35 years. One-time license, 5-day implementation.

User Solutions Team

User Solutions Team

Manufacturing Software Experts

User Solutions has been developing production planning and scheduling software for manufacturers since 1991. Our team combines 35+ years of manufacturing software expertise with deep industry knowledge to help factories optimize their operations.

Let's Solve Your Challenges Together