EOQ
for production lot sizes (EOQPROD)
Alvin
Air Systems in Alvin , Texas , produces repair and
maintenance items for commercial air conditioning
systems. Alvin cannot use the standard EOQ for determining
production lot sizes. One problem is that the standard
EOQ assumes that an order quantity or lot of material
is received all at once. At Alvin , most production
lots take some time to complete and parts are placed
in stock on a daily basis until the run is over. A
related problem is that substantial sales usually
occur before the run is over. To solve these problems,
Alvin uses the modified EOQ model for production lot
sizes. Why? The EOQ must be larger than maximum investment
to account for sales made during the production run.